The Public Works Department is pleased to release the Project Updates Report for the various divisions- Planning,Capital, TSPLOST, and Engineering,ConstructionOperationsand Maintenance, Traffic Operations & Maintenance, and Solid Waste.
The report is a reference document for all active projects in the City of South Fulton that are in various stages of implementation that include procurement, design, right-of-way acquisition, construction, and maintenance. Also, it outlines other standalone activities/programs, i.e., streetlights, utilities, and traffic calming.
Thedocument is broken into threesections asoutlined below:
• SeeClickFix allows residents andbusinessowners to provide City of South Fulton staff with pictures, specificdescriptions, and other valuable information needed to get the job done efficiently.
• The Transportation Section containsinformation related to Construction Operations & Maintenance, Traffic Operations & Maintenance, and Utilities. A summary of the Capital Improvement (CIP) and TSPLOST projects is included; however, the fact sheets are omitted from this report. Instead, the department launched a web-based real time project reporting tool using this link available on the Public Works homepage.
• The Solid Waste section updatesthe reader on the residential collection program in the city.
Noteworthyaccomplishments
• Five gravel roads (Rocky Head Road, Thames Road, Oxford Road, Hall Road, and Jones Road) are being advanced to begin preliminary design
• T266 New Hope Sidewalks and OSI 613 Old Fairburn Road/Union Road/Stonewall Tell Road roundabouts had groundbreaking ceremonies and are continuing in construction.
• SU 700 Flat Shoals ATMS and T265 Old National Highway Sidewalks have been let and are in the rocure ent a roval rocess.
• T 277 Cochran over Camp Creek had a pre-construction meeting with the selected contractor, Southeastern Site Development. Construction should begin shortly.
• i berly ill at ascade oad- Contractor completed installing overhead signs and pole foundations for overhead signs.
• Fulton Industrial Boulevard ull e t ecla ation- Ten Corridors (E. Great Southwest, Villanova Dr., Frederick Court SW, Wharton Drive SW, Bucknell Drive, Westgate Dr SW, Indeco Blvd, Greensboro Drive, Fisk Drive SW, and Loyola Dr) are complete. Waterfront Drive SW ill be co leted in ugust
City of South Fulton CIP and T-SPLOST
III. TRANSPORTATION
Status of Capital and TSPLOST Projects in Design and ROW Phases Capital and TSPLOST Projects in Construction
• OSI 613/615: Old Fairburn Rd at Union Rd/Stonewall Tell Rd at Union Rd
• T284: Kimberly Road at Cascade Road Intersection Improvement
• Fulton Industrial Blvd Full Depth Reclamation
IV. CONSTRUCTION OPERATIONS AND MAINTENANCE
• In-House Staff
• BrightView
• Right-of-Way Maintenance Schedule
• Street Sweeper Schedule
• Gravel Road Maintenance
• DAF Concrete
V. TRAFFIC ENGINEERING, OPERATIONS, AND MAINTENANCE
• Traffic Operations and Maintenance
• Traffic Calming Program Update
VI. UTILITY PERMITS
VII. STREETLIGHTS
• Streetlights
• Streetlight Requests
• Capital & TSPLOST Projects
SECTION I:
SECTION II:
The City of South Fulton (COSF) 311 platform provides City officials with a centralized issue management system to manage issues from creation to resolution, engaging City of South Fulton residents throughout the process. The COSF mobile app and web tools allow residents and business owners to provide City of South Fulton staff with pictures, specific descriptions, and other valuable information needed to do the job efficiently. In addition, residents may seek information about city services or report non-emergency incidents by calling the city s 24 hour 311 Call Center at (470) 552 4311.
Summary of SCF Requests
Note: Category Others include Manhole Covers, Street Lights, Bridge Maintenance, and Graffiti
SECTION III: TRANSPORTATION
The City of South Fulton has a Capital and TSPLOST Program for implementing design projects that have been identified by City staff and stakeholders as a priority. Funding comes from the General Fund, TSPLOST sales tax collections and some Federal money.
TSPLOST-I program tax collections started in 2017 and ended in 2022, and TSPLOST-II program tax collections started in 2022 and will end in 2027. TSPLOST-I projects are being prioritized for completion and all TSPLOST-II projects will be in the concept or preliminary design stage.
The delivery of projects is centered around GDOT’s Plan Development Process (PDP). This process typically consists of the four major phases: Design, Environmental Clearance, Right-of-Way (Services and Acquisition) and Construction (including CEI). Additional details of these phases are depicted below, which detail the project development process utilized by Public Works.
The plan development process, start to finish, is illustrated below:
TSPLOST I: Projects moving toward Construction
SU-700 – Flat Shoals Road ATMS – The project received six bids and currently being evaluated
OSI-617 – Welcome All at Jailette Road – Pending final utility certification the city will prepare and advertise an ITB.
B-500/OSI-601 Butner Road at Camp Creek (bridge replacement and intersection improvement) – Final design, utility coordination and ROW acquisition continue in advance of advertisement later this year.
Projects in Right-of-Way (ROW) Acquisition
OSI-616 – Jones Road at Pittman Road/Stonewall Tell Road (TSPLOST-I) – Continuing in ROW Acquisition and final utility coordination before advertisement.
OSI-618 – Welcome All Road at Scarborough Road/Jailette Road (TSPLOST-I) – Continuing in ROW Acquisition and final utility coordination before advertisement.
T-270 – Demooney over Deep Creek (Capital Design/T-SPLOST-II Construction) – Continuing in ROW Acquisition before advertisement.
OSI 607 – Demooney Road at West Stubbs Road (TSPLOST-I) – Continuing in ROW Acquisition and final utility coordination before advertisement.
OSI 608 – Enon Road at Stonewall Tell Road (TSPLOST-I Design/T-SPLOST-II Construction) –Continuing in ROW Acquisition and final utility coordination before advertisement.
TSPLOST II: Projects in concept/design
Intersection Improvement projects
OSI-620 – Aldredge Road and Merk Road – Preliminary plans are currently under review.
OSI-629 – Ono Road/Hobgood Road at Rivertown Road – Preliminary plans are under review.
OSI-631 – Union Road and Thames Road – Preliminary plans ae under review.
OSI 600 – Bethsaida Road at Creel West – there was a July 10th public meeting. Design will be validated and authorized in August.
OSI 622 – Bethlehem Road at Cedar Grove Road – Concept in further revision by the design consultant before alternative selection and public meeting.
OSI 623 – Butner Road at Aldredge Road– Concept in further revision by the design consultant before alternative selection and public meeting.
OSI 628 – Old Fairburn Road at Thaxton Road – Concept in further revision by the design consultant before alternative selection and public meeting.
Sidewalk projects
P-914 – Union Road – Continuing in Concept development. After a public meeting, design will be validated and authorized.
P 902 – Bethsaida Road - There was a July 10th public meeting. Design will be validated and authorized in August.
P 903 – Cascade Road – Continuing in the concept development phase.
P 908 – Flat Shoals Road – Continuing in the concept development phase.
Bridge/Culvert Replacement projects
T-288 – Stacks Road over CSX RR – Continuing work on preliminary design before a plan review.
B-505 – Derrick Road over Deep Creek Tributary – Concept is under review by the city.
B-508 – Koweta Road over Deep Creek – Concept is under review by the city.
B-599 – Oglesby Road over Morning Creek Tributary - Concept design phase nearing completion for city review.
Federally Funded Projects
T-266 – New Hope Road Sidewalks – is in construction and a monthly report has been included.
T-277 – Cochran Road at Camp Creek (Bridge) – On July 31st, a pre-construction meeting was held. Expecting to have a groundbreaking ceremony following contractor mobilization.
T-265 – Old National Highway Sidewalks – Five bidders submitted proposals and bids, and these are under procurement review prior an award recommendation.
Gravel Road projects
RG 160 – Jones Road – The consultant has been granted NTP for developing the design.
RG 161 – Hall Road – The consultant has been granted NTP for developing the design.
RG 162 – Rocky Head Road – The consultant has been granted NTP for developing the design.
RG 163 – Thames Road -– The consultant has been granted NTP for developing the design.
RG 164 – Oxford Road – The consultant has been granted NTP for developing the design.
Bridge Repairs and Maintenance – Work continues on three bridges from the 2021 GDOT bridge repair set. Two of these (Mallory and Cascade) are in coordination with the CSX railroad and are requiring extra days of CSX flagman coordination to complete. They are 90% complete. One bridge (Burdett) required a partial wing wall design repair, which is under review by the contractor.
All 2023 GDOT bridge work is complete.
GDOT Projects within South Fulton
PI0011845/OSI-624: SR 14 at Washington Road Roundabout construction continues with grading operations with a projected completion in late 2025.
PI0013938 & PI0013939/T-272 & T-273: Buffington Road Projects - Contractor continues installing BMPs throughout the project. Water Quality monitoring, Traffic Control & Erosion Control throughout project. Storm Drain installation in progress. Projected completion in the fall of 2026.
PI0016605/B-502: Bethsaida Rd (CR 581) over Morning Creek – project was Let in July 2025 – contractor yet to be selected and a date to start construction is not yet determined.
PI0015593/T-285: SR 92 @ Butner Rd/Ridge Rd Roundabout project was Let in June 2025 – SD&C was selected as the contractor; a date to start construction is not yet determined.
PI0015642/T-280: Oakley Road over Broadanax Creek – Bridge replacement - ROW issue has been resolved, and construction has been given notice to proceed pending completion of utility relocation. There is a planned detour from August 4th until November 2nd. Project completion forecasted for December 2025.
PI0017398/OSI-605: SR 92 @ Jones Road/Demooney Road Roundabout – Design continuing following the PFPR that was held December 2024; ROW Authorization expected by January 2026. Let Date early 2027.
PI0019647: FIB and Westpark – Median conversion and R-CUT Design underway. PFPR was held on 4/21/25.
PI0019841: SR 138 at Bethsaida Road – Preliminary Plan review planned for August 2025. Letting is expected in 2027.
PI0013809: SR 14 / US 29 @ CSX Bridge Replacement: Coordination with CSX for operations is underway
PI0013724: SR 279 @ Jolly Road/ Sullivan Road Pedestrian improvements: Pipe install nearing completion which will be following by a lane paving
Prime Contractor: Contractor Rep.:
MONTHLY PROGRESS REPORT
OSI 613 and 615 Old Fairburn Rd Roundabouts
Period Begin
Period End 7/31/2025
Time Charges Begin Date 1/10/2025
Scheduled Completion Date 4/30/2026
Work Begin Date 3/6/2025
Summit Construction and Development, LLC
Olumayowa Odumade Phone:
Contact
Olumayowa Odumade
Olumayowa Odumade
Olumayowa Odumade
470-636-2859
470-636-2859
Scope of Work Performed This Month
470-636-2859
Company
470-636-2859 Summit CD
Clearing and grubbing complete
Erosion control 7 day inspection complete
Removing tree stumps throughout project
Progress and Schedule
Work items performed between the monthly report dates detailed above:
The targeted Project Schedule Status was predicted to be 43% as of the period ending date above. Summit CD
Scope of Work Planned For Next Month 7/1/2025 thru
Utility coordination meeting 7/23/2025
Continue removing tree stumps throughout projects Summit CD
The Physical Project Status is 30% completed as of the period ending date above.
Begin grading on Stonewall Tell Rd
Progress Photos are attached on the following pages
Prime Contractor:
Contractor Rep.:
CMC, Inc.
Sid Balar
MONTHLY PROGRESS REPORT
OSI614 Rivertown Road at Cedar Grove Road
Period Begin 7/1/2025 thru
Period End 7/31/2025
Time Charges Begin Date 2/1/2024
Scheduled Completion Date 7/31/2025
Work Begin Date 3/27/2024
Phone:
678-283-5760
ContactCompany
Riddhish Baldha
Riddhish Baldha
Siddharth Balar Name
470-894-5609
470-894-5609
678-283-5760
Scope of Work Performed This Month
CMC, Inc.
CMC, Inc.
CMC, Inc.
Work items performed between the monthly report dates detailed above:
Construction of sidewalk and curb and gutter complete
Adjusting fire hydrants and water valves to grade
Construction of ADA ramps and stamped concrete complete
Asphalt topping complete
Fine grading of slopes and shoulders throughout project
Permanent grassing
Progress and Schedule
The Physical Project Status is 99% completed as of the period ending date above.
The targeted Project Schedule Status was predicted to be 100% as of the period ending date above.
Project delays have been related to unforeseen utility delays related to water, cable, and power and obtaining easement from Fulton County on Parcel 2.
Scope of Work Planned For Next Month
Project clean up
Thermoplastic striping
Permanent grassing
Punchlist completion
Progress Photos are attached on the following pages
OSI614 Rivertown Road at Cedar Grove Road
OSI614 Rivertown Road at Cedar Grove Road
Prime Contractor: Contractor Rep.:
MONTHLY PROGRESS REPORT PI 0012637 New Hope Rd Sidewalk Improvements
Period End 7/31/2025
Time Charges Begin Date 9/12/2024
Scheduled Completion Date 3/6/2026
Work Begin Date 3/10/2025 DAF Concrete
404-395-8464 Company
404-395-8464
404-747-0885
Scope of Work Performed This Month
Work items performed between the monthly report dates detailed above:
Curb and gutter installation has taken place from Boat Rock Rd beyond Heatherland Drive SW
Sidewalk installation continuing and concrete driveway installation began
Storm drainage pipe installation continuing
Progress and Schedule
The Physical Project Status is 55% completed as of the period ending date above.
The targeted Project Schedule Status was predicted to be 60% as of the period ending date above.
Scope of Work Planned For Next Month
Continue concrete installation of curb and gutter, sidewalk, and driveways
Continue storm drainage pipe and structure installation
Utility coordination meetings and relocation
Maintain traffic control and lane closures by the use of flaggers and stop and go paddles 7/1/2025
Prime Contractor: SD&C INC.
MONTHLY PROGRESS REPORT
Fairburn Road Upgrade Project
Period Begin thru Period End 06/20/2025 07/20/2025
Time Charges Begin Date 5/19/2024
Scheduled Completion Date 5/30/2026 Work Begin Date 6/24/2024
Contractor Rep.: T. BUAH Phone: 678-334-7788
WECS KENNY COLEMAN 470 894 5609 REDROCK LAND SERVICES LLC
WTCS SD&C INC 404 288 2205 SD&C INC
WUCS SD&C INC 404 288 2205 SD&C INC
Scope of Work Performed This Month
Work Breakdown Structure (WBS)and performance report:
SD C and sub-contractor T&J preparing to perform relocation water meters.
SD&C and sub-contractor T&J disassembled 100ft casing
M&SJ Enterprises cut tree and shave stump @ sta# 158+84rt
Erosion control and onsite maintenance performed by contractor
Progress and Schedule
The Physical Project Status is 66% completed as of the period ending date above rading, Curb Gutter, Sidewalk Installation Traffic Signal Installationand Storm Drain Installation.
GA Power utility poles relocate 0 complete AT&T and Comcast completion 0%.
Project delays have been related to Georgia Power utility relocation, and street light poles relocations. Proposed 30-inch water main Bypass installation has been changed to a Jack and Bore method
Scope ofWork Planned for Next Mont
• Grading, Placing G.A.B and Continuing Constructing Sidewalk, Color Stamped Concrete Beauty Strip and Medians; Pavement widening from Station: 146+00 LT to 147+00LT and 49+00 RT to 50+00 RT, 145+17RT to 145+60RT, 50+81 to 51+40RT
• Relocate Fire Hydrant and Water Meters
• Relocation of Backflow Preventor at Walgreens.
• Water mains Bypass installation
• Build a dam on South Utoy Creek.
• Relocate Georgia Power utilities
• Erosion Control
• Catch Basin Ex -4 sta# 158+84rt
Progress Photos are attached on the following pages
Bypass Casing Fabricate
AT&T on-site relocating line from broken pole to a better pole so the broken pole could be removed
SD&C subcontractor on-site preparing area for Jack and Bore
Work items performed between the monthly report dates detailed above:
• Reedwick completed Hydrovac of overhead sign pole foundations
• Reedwick installed steel cage for overhead sign pole foundations @ STA# 104+34
• Electro Painters painted traffic poles and arms @STA# 110+00lt and 110+50rt
Progress and Schedule Progress Photos are attached on the following pages
• The Physical Project Status is 70 completed as of the period endingdate above.
Work items performed between the monthlyreport dates detailed above:
o Waiting for Reedwick to finish their scope of work.
o Will finish pavement striping work.
Reedwick on-site installing metal rebar cage for strain pole footing
Reedwick subcontractor on-site painting mast arm poles
MONTHLY PROGRESS REPORT
Prime Contractor:
Contractor Rep.:
Mandy Neese Phone:
Doug Kramer
Doug Kramer
Doug Kramer Name
Milling existing asphalt on Westgate Dr SW, Bucknell Ct SW, Loyola Dr SW, Fisk Dr SW, Greensboro Dr, Indeco Blvd, and Waterfront Dr SW Scope of Work Performed This Month
Soil cement placement on Westgate Dr SW, Bucknell Ct SW, Loyola Dr SW, Fisk Dr SW, Greensboro Dr, and Indeco Blvd
Asphalt binder and topping placement on Westgate Dr SW, Bucknell Ct SW, Loyola Dr SW, Fisk Dr SW, Greensboro Dr, and Indeco Blve. Progress and Schedule
The Physical Project Status is 84% completed as of the period ending date above. The targeted Project Schedule Status was predicted to be 83% as of the period ending date above.
SECTION IIIA: CONSTRUCTION OPERATIONS
Right of Way Maintenance is required to provide safe and multi-use roadsides. A wellmaintained right of way promotes a positive quality of life and is integral to the other functions such as utility installations, vehicle emergencies and sign placements. Right of way Maintenance serves to maintain a safe zone adjacent to the road pavement, improves drainage of stormwater from the road surface, and creates an attractive vista along road corridors. Accomplishments this month include:
Number of Potholes Repaired: 24 SeeClickFix
18463403
Pothole 4780 Mendel Ct SW 19259180
Pothole Northcutt Rd 19335367
Pothole 510 Stonebriar Way SW 19338867
Pothole Mays Ln SW 19345016
Pothole 5550 Koweta Rd 19345143
Pothole 5750 Chatteron Rd 19378965
Pothole 4958-4982 Estonian Dr 19401683
Pothole 1699-1733 Reynolds Rd SW 19406595
Pothole 7579-7751 Hobgood Rd 19419428
Pothole 5901 Campbellton Rd SW 19428921
Pothole Hobgood Rd & Herndon Rd 19433318
Pothole 7135 Bishop Rd 19433355
Pothole 7527 Bishop Rd 19482847
Pothole 9100 Clark Rd 19486091
Pothole Enon Rd 19486097
Pothole 3840-3852 Old Fairburn Rd SW 19486107
Pothole Bethlehem Rd 19529965
Pothole Cascade Rd SW & Fairburn Rd SW 18596753
Deep Base Repair 5180 Koweta Rd 19299431
Deep Base Repair 6253-6299 Nathaniel Ln 19376546
Deep Base Repair 2870 Jerome Rd 19392819
Deep Base Repair 4055-4097 W Stubbs Rd 19422579
Deep Base Repair 5537-5581 Halsey Trce SW 19472285
Deep Base Repair Bethlehem Rd & Cedar Grove Rd
Number of Storm Drains Maintained: 18
SeeClickFix Category Location
18682498
18955091
19102488
19177081
19226594
19249724
19374447
19374627
19376455
19382174
19391342
19395144
18803379
19114900
19177691
19219628
19347294
19423503
Clogged Culvert 7295 Thoreau Cir
Clogged Culvert 2420 Hallie Mill Rd
Clogged Culvert Cascade Rise Ct SW
Clogged Culvert 3528 Devon Chase Rd
Clogged Culvert 3950 Demooney Rd
Clogged Culvert 7215 Buck Creek Dr
Clogged Culvert Robin Ln & Diann Dr
Clogged Culvert Stonewall Tell Rd
Clogged Culvert 3640 Las Olas Dr
Clogged Culvert 4600 Fradon Ct
Clogged Culvert 2875 Carriage Ln
Clogged Culvert 5310 Happy Valley Cir SW
Clogged Inlet 505 Dot Dr
Clogged Inlet 4585 Stonewall Tell Rd
Clogged Inlet 220 Devilla Ct
Clogged Inlet 6338 Celtic Dr SW
Clogged Inlet 3285 Devilla Trace
Clogged Inlet Bethsaida Rd
POTHOLE REPAIR
Number of Dead Animals Received: 7
SeeClickFix
19394869 Remove Dead Animals in Right-of-Way 3945 Thaxton Rd SW 19287440 Remove Dead Animals in Roadway Union Rd SW
19334324 Remove Dead Animals in Roadway 600 Wild Boar Ct
19357576 Remove Dead Animals in Roadway 2350 Enon Rd SW
19419926 Remove Dead Animals in Roadway Butner Rd & Union Rd SW 19490917 Remove Dead Animals in Roadway 5705 Butner Rd
19430015 Remove Dead Animals in Roadway Enon Rd 19541024 Remove Dead Animals in Roadway 5460 Koweta Rd
Number of Gravel Roads Maintained: 13
SeeClickFix
19161855 Rough Road (Unpaved Road Maintenance) 7512–7574 Hall Rd
4-Aug11-Aug18-Aug25-Aug BURDETT ROAD OLD NATIONAL HWY (400 FT EAST) BURDETT WAY (350 FT
DR (CLAYTON COUNTY LINE) BETHSAIDA RD
CAMPBELL DRIVE ROOSEVELT HWY SPRING STREET
RIGHT-OF-WAY MAINTENANCE SCHEDULE
RIGHT-OF-WAY MAINTENANCE SCHEDULE
4-Aug11-Aug18-Aug25-Aug LESTER ROAD CITY LIMIT (SOUTH OF JONESBORO RD)NEWTON DR 1.88 4-Aug11-Aug18-Aug25-Aug
LOYOLA DR SW VILLANOVA DR SW END 0.144-Aug11-Aug18-Aug25-Aug
MCDOUGAL DRIVE SW WHARTON DRIVE SW JAMES ALDRIDGE BLVD
MILAM ROAD COUNTY LIMIT WEST OF GREENVIEW COUNTY LIMIT (WEST OF GARVEY DR) NORTH SIDE 1.56 4-Aug11-Aug18-Aug25-Aug
MILES
MILLS PLACE
RIGHT-OF-WAY MAINTENANCE SCHEDULE
UNION
RIGHT-OF-WAY MAINTENANCE SCHEDULE
SWEEPING SCHEDULE
SWEEPING SCHEDULE
SWEEPING SCHEDULE
SWEEPING SCHEDULE
SWEEPING SCHEDULE
AUGUST, 2025
GRAVEL ROAD MAINTENANCE
Scope
OLD WHITE MILL RD, SOUTH
WEXFORD RD, VALLEY LAKES RD, NORTHCUTT RD, PETERSBURG RD, PORTER TERRY RD, & WEST TEAL RD
• Removed tree debris from the right way.
• Repaired ditches
• Installed a cross drainpipe underneath road
• Resurfaced the roadway with the motor grader using GAB.
• Compacted roads
• Dust abatement application.
OLD WHITE MILL ROAD
SOUTH WEXFORD ROAD
VALLEY LAKES ROAD
NORTHCUTT ROAD
PETERSBURG ROAD
PORTER TERRY ROAD
WEST TEAL ROAD BEFORE AFTER
SECTION IIIB: TRAFFIC OPERATIONS
The Traffic Operations Crew is on constant patrol in the City of South Fulton to ensure that all signs and signals are clear to see and work properly. This consists of approximately 35,000 static signs, 69 Traffic Signals, 14 Traffic Beacons, 42 School Flashers and numerous Solar Flashing signs.
The following is what each category is used for and what they represent.
• Sign – Other Sign Down/Missing is used for missing signs, installing new signs, replacingorupgradingsigns. If thereareothersignsonthatpost, thecrewwillclean them.
• Sign – Long Term Repair is used to keep a requestopenuntilthe signcanbeobtained andinstalled.
• Sign – PreventativeMaintenance is usedfor the cleaningandstraightening of signs.
• Sign - Stop/YieldSign Down/Missing is usedfor responding to orfindingSTOP sign or YIELD sign that has been knocked down or missing. This category is respondedtoas anemergency.
• Signal - In Flash or Dark is used to let us know that the traffic signal is flashing all RED lights, ornolightsare visible. This category is respondedtoasanemergency.
• Signal - Other Issues is used to let us know if there are any other problems with the Traffic Signal, this can include a LED bulbnot working, if the crosswalk is being problematic, or thesignalnotchanging.
This month, the Traffic Operations Department acquired 201 new requests and closed 218.
The following are 218 SeeClickFix items, along with Categories that Traffic Operations responded to and completed this past month.
Examples of work completed this past month are highlighted in Exhibit A. Signal – In Flash or Dark: 7
Seeclickfix Locations
OTHER: 5
SeeClickFix Locations
19167727 Fulton Industrial Blvd SW
19387406 4770 Campbell Dr
19439962 Derrick Rd & Koweta Rd
19514802 Keels Ln & Deerrun Trl
19522803 W Stubbs Rd & Demooney Rd
Sign – Stop/Yield Sign Down/Missing: 16
SeeClickFix Locations
19370543 501 Cascade Rise Ct SW
19381217 1102 Westchase Ln SW
19394158 Sanford J Jones Blvd
19394473 Merk Rd
19402055 3895 Pebble Beach Dr
19403260 3630 Tate Rd
19429885 2513 Wyncreek Dr SW
19435919 5167-5175 Old Bill Cook Rd
19457134 2280 Enon Rd SW
19467059 5140 Dublin Dr SW
19488426 6239 Shell Dr SW
19489224 785 Stillrock Dr SW
19559034 6315 Connell Rd
19569326 5500-6102 Plantation Dr
19570303 605 Stonehill Dr SW
19571277 5702-5748 Tulane Dr SW
Signal – Other: 9
SeeClickFix Locations
19258712 Campbellton Rd & Stonewall Tell Rd
19371360 3850 Flat Shoals Rd
19371932 Feldwood Rd
19382963 3850 Flat Shoals Rd
19426076 4810 Campbellton Rd SW
19435301 6715 Old National Hwy
19488016 Highway 92
19515256 Campbellton Rd & Chattahoochee Dr SW
19564414 6559-6559 Campbellton Rd
Sign – Long Term Repair: 2
SeeClickFix Locations
19403289 4242 Winston Cir
19488355 Flat Shoals Rd & Red Oak Rd
Signal – Preventative Maintenence 4
SeeClickFix Locations
19371185 4505 Scarborough Rd
19423854 3975 Pierce Rd
19486888 5162-5230 Fulton Industrial Blvd SW
19518634 5291 Campbellton Rd SW
Sign – Preventaive Maintenance: 115
SeeClickFix Locations
19349112 4112-4198 Thaxton Rd SW
19370214 460 Cascade Rise Ct SW
19370299 340 Cascade Rise Ct SW
19370695 3054-3056 Merk Rd SW
19371323 525-599 Cascade Rise Ct SW
19372010 1503 Sandrock Ln SW
19381243 6600 Ashdale Dr
19383725 3125 Cadiz Cir
19385250 5215 Erin Rd SW
19385538 5105 Erin Rd SW
19385746 5075 Erin Rd SW
19394272 6590 Jones Rd
19394788 6355 Jones Rd
19394982 4855 Jones Rd
19395292 4639-4653 Jones Rd
19401280 3736 Makeover Ct
19401477 5440 Pennington Ct
19401577 5356 Pennington Ct
19401625 3655 Pebble Beach Dr
19401904 3715 Tate Rd
19402159 5581 Waverly Park
19402424 5891-5899 Vernier Dr
19402579 501-599 Ventura Ln
19402969 105 Pebble Beach Ct
19404343 3995 Pierce Rd
SeeClickFix Locations
19423858 Jonesboro Rd
19424691 1951-1957 Enon Rd SW
19425946 5937-5943 Buffington Rd
19426309 6001-6003 Buffington Rd
19426510 5965 Buffington Rd
19426850 6115 Lamp Post Pl
19436487 6877-6901 Rivertown Rd
19436829 7000 Rivertown Rd
19437344 7083 Rivertown Rd
19438316 Old Jonesboro Rd
19448782 5850 Penfield Pl
19467500 4945 Campbellton Rd SW
19467863 4965 Campbellton Rd SW
19468333 5483 Spelman Dr SW
19487854 335 Stoneview Pl SW
19489511 2669 Bluestone Dr SW
19490359 6247 Shell Dr SW
19508190 2801 The Meadows Way
19509500 5830 Deerfield Trl
19509941 Deerfield Trl
19518484 6002 Birdseye Trl
19518609 3465 W Stubbs Rd
19518936 6131 Lamp Post Pl
19519012 5462-5506 Campbellton Rd SW
19519081 6100 Ripple Way
19519383 3525 Stonewall Tell Rd
19519474 6112-6126 Lamp Post Pl
19519566 2295 Union Rd SW
19519595 3297-3389 Stonewall Tell Rd
19519809 2500-2594 Union Rd SW
19520038 2487-2499 Union Rd SW
19520273 4535-4557 Derrick Rd
19520366 2400 Union Rd SW
19520559 2400 Union Rd SW
19520601 6087 Lamp Post Pl
19520910 5965 Buffington Rd
19521184 Rivertown Rd
19521556 7083 Rivertown Rd
19521772 6950-7020 Rivertown Rd
19522064 7055-7081 Rivertown Rd
19522799 3172-3190 Stonewall Tell Rd
19528070 2565 Jolly Rd
SeeClickFix Locations
19528273 2640 Dunmoreland Ter
19528315 3215 Stonewall Tell Rd
19528419 3172-3190 Stonewall Tell Rd
19528745 3390 Stonewall Tell Rd
19529250 5850 Feldwood Rd
19529424 6403-6513 Feldwood Rd
19529719 2866-2884 Burdett Rd
19529858 2380 Burdett Ridge Dr
19529976 2674-2698 Burdett Rd
19530077 5843-5899 Old Carriage Dr
19530196 5910 Old Carriage Dr
19530263 2780 Burdett Rd
19530400 2740 Burdett Rd
19530560 2606 Burdett Rd
19531461 5832-5846 Feldwood Rd
19531471 7051-7127 Hall Rd
19545676 2603-2657 Union Rd SW
19545830 7390 Herndon Rd
19546208 2301-2315 Union Rd SW
19546712 4362 Parkaire Pl
19547513 4362 Parkaire Pl
19547974 4344-4390 Ridge Rd
19548079 4362 Parkaire Pl
19548308 4472-4472 Ridge Rd
19548627 7171-7171 Oakley Industrial Blvd
19548732 7524-7534 Hall Rd
19556649 4448 Welcome All Rd SW
19556652 4437 Welcome All Rd SW
19556718 4225 Welcome All Rd SW
19556759 401-499 Thistle Cv
19556786 4415-4479 Welcome All Rd SW
19557052 4689-4705 Creekside Cv
19557393 4605 Scarborough Rd
19557512 4721-4723 Scarborough Rd
19557634 4645-4645 Scarborough Rd
19557656 4655-4699 Scarborough Rd
19557854 6690 Greenbower Ln
19558006 4618-4620 Scarborough Rd
19558316 4555 Scarborough Rd
19558517 2605 Creel Rd
19558645 6690 Greenbower Ln
19558738 2755 Creel Rd
SeeClickFix Locations
19558955 2721-2725 Creel Rd
19559009 6310 Connell Rd
19559137 2733-2739 Creel Rd
19559428 Connell Rd
19562136 Bear Rock Dr SW
19576854 7142 Gotland St
Sign – Other Sign Down/Missing: 60
SeeClickFix Locations
19369793 4959 Campbellton Rd SW
19369913 871 Cascade Xing SW
19370082 4921 Campbellton Rd SW
19370427 1362 Boat Rock Rd SW
19371831 7400 Toccoa Cir
19374324 3878 Demooney Rd
19380989 3430 Davis Blvd
19381280 1201-1321 Reynolds Rd SW
19381669 Casa Blanca Ln SW
19381716 3835 Benchmark Dr
19381921 5700-5886 Vernier Dr
19382140 3750 Benchmark Dr
19382414 5701-5829 Bearing Way
19382693 3760 Springside Ln
19382902 1680 Reynolds Rd SW
19382942 3820 Clearwater Dr
19383129 5533-5599 Morning Creek Cir
19384045 1860 Reynolds Rd SW
19391593 2001-2015 Union Rd SW
19391772 3847-3899 Benchmark Dr
19392121 3825 Benchmark Dr
19392334 Merk Rd
19392610 3770 Benchmark Dr
19392837 3640 Tate Rd
19393493 3745 Pebble Beach Dr
19401228 3800 Pebble Beach Dr
19401348 3765 Pebble Beach Dr
19401432 3895 Pebble Beach Dr
19402377 3715 Pebble Beach Dr
19403978 3630 Tate Rd
19420854 Elva Dr SW
19425520 2445 Creel Rd
SeeClickFix Locations
19425764 2320–2358 Bethsaida Rd
19429579 2303-2515 Reynolds Rd
19435889 1845 New Hope Rd SW
19437430 3032-3034 Roosevelt Hwy
19437526 6602-6734 Plummer Rd SW
19440021 7095 Rivertown Rd
19447528 205 Willow Park Trl
19457286 2105-2105 Bethsaida Rd
19466936 7200 Connell Rd
19469277 2784 Palmview Ct SW
19469590 Bruce Pl SW & New Hope Rd SW
19469925 5741 Deerfield Trl
19470152 2700-2898 Swansea Ct
19480808 6395 Old National Hwy
19480817 2400–2434 Flat Shoals Rd
19486672 2821 Stonewall Ln SW
19490991 339 Woodmill Way SW
19509705 2816 E Hampton Ct
19510589 4430 Merrigold Way
19512883 5950 Canaan Woods Dr SW
19519004 3297-3389 Stonewall Tell Rd
19528009 5701-6021 Old Campbellton Rd SW
19528590 5266-5268 Northfield Blvd
19528748 2640 Dunmoreland Ter
19529465 2210 Burdett Ridge Dr
19546191 7433-7463 Herndon Rd
19571868 Bucknell Dr SW
19579575 5352-5378 Bucknell Dr SW
UPGRADING SIGNS THROUGHOUT THE CITY
FIXING TRAFFIC SIGNALS
REMOVING VEGETATION
low response from households to support traffic calming measures, request
Oaks at Flat Shaols
Bowhead Court Jonesboro Meadows 7
New Jersey Ave, NW Grove Park N/A
SpeedingApr 02, 2025 No
SpeedingJun 03, 2024 No
Study not conducted N/A
Study not conducted N/A
Staff emailed online petition to initiator for use and distribution. Staff have yet to receive petitions.
Request falls outside of jurisdiction for the CoSF
SECTION IIIC: UTILITY PERMITS
The purpose of utility permits is to help the City of South Fulton staff track and manage construction operations more efficiently. Each utility permit contains a unique reference number, special requirements before/ during operation, procedures, and contact information in case of emergencies. All this information is essential when dealing with construction operations in our Right of Way.
Permits
Locations
RWEP (25)199 1185 Research Center Dr SW
RWEP (25)200 Hall Rd & Jones Rd/ Harmony Manor Subdivision
RWEP (25)201 Location 1: Duquesne Dr and Purdue Dr - Location 2: Lagrange Blvd and Fulton Ind Blvd
RWEP (25)202 528 Ironstone Dr
RWEP (25)203 550 Wharton Dr SW
RWEP (25)204 Stonewall Tell Rd, Union Rd and Old Fairburn RD
Scope of Work
Trench 10' of 4" proposed buried conduit and pull 10' of 288ct buried fiber cable through proposed conduit.
Install: 2070' X 4'' plastic Main, and 12,135 X 2'' plastic main to service Harmony Manor subdivision
Trench (1) 8in SCH 80 HDPE duct and equipment with 6 1.5in HDPE ducts and one 228ct FOC approximately 925ft along Northside of Boat Rock Rd.
Directional bore to install 2-2" HDPE conduits and pull 1-24CT Greystone fiber optic cable.
Trench 312' of 4" new buried conduit and pull 312' of 1.25" buried innerduct through 4"
Complete
Complete
Complete
RWEP (25)205 6360 Stonelake Dr, South Fulton, Ga 30331
RWEP (25)206 Koweta Rd
RWEP (25)207 5825 Deerfield Trail
Hasn’t Started
Complete
Open trench 1821' and directional bore 1036' of 4" MHP STL gas main. Open trench 295' and directional bore 140' of 6" MHP STL gas main to renew existing 4" and 6" STL gas mains. In Progress
Bore install 2-2" HDPE conduits and pull new 2-24ct Greystone fiber and proposed bore pit remove and restore 35 sq ft of grass area to equal or better condition.
Open trench 17' and directional bore 43' of 4" MHP PLS gas main to provide natural gas to the new subdivision
Proposing to replace like for like equipment, such as fuses, guy wires and span guys to existing poles within the ROW of Deerfield Trail. 175' of guy wire will be replaced from pole 433 to 435
Hasn’t Started
Complete
Hasn’t Started
RWEP (25)208 Southwest of Dodson Rd CL New 144’ x 1.25” Plastic Service In Progress
Permits
RWEP (25)209 3745 The Great Dr, South Fulton, Ga 30349
RWEP (25)210 Bishop Rd
RWEP (25)211 5220 Northfield Blvd
RWEP (25)212 4762 Bakers Ferry Rd SW
Scope of Work
Trench and directional bore install 2-2" HDPE conduits and pull 1-48ct Greystone fiber optic cable.
Comcast is to over lash 3,849’ of new 48ct fiber to existing poles along Rivertown RD and Bishop RD to provide service to the Bishop Meadows Subdivision.
Proposing to install a new fuse and fiber glass cutout to an existing pole at 5220 Northfield Blvd. This permit is part of Georgia Power Company's GRID improvement program.
Comcast is to riser down 25' from an existing GPC pole and excavate, bore, & install 60' new 0.625" UG coax cable to be pulled through new 2" conduit within the row.
Complete
Complete
Hasn’t Started
Progress
RWEP (25)213 5480 Old National HWY
RWEP (25)214 5713 Harrier Ln, South Fulton, GA 30349
RWEP (25)215 2765 Jerome Road
RWEP (25)216 5750 Orly Terrace
RWEP (25)217 5462 Scofield Rd
RWEP (25)218 Stonewall Tell Road (Enclave at Stonewall Tell subdivision)
RWEP (25)219 4046 Hammock Trace, Atlanta, Ga 30349
RWEP (25)220 5595 Jerome Road
Proposing to install fiber glass cut out and trip saver equipment to existing pole, removing a recloser. Upgrading an existing fuse to existing poles in the ROW of Surrey Trail. No wirelines will be installed or removed. This permit is part of GRID
Installation of 4640' of FOC via Directional bore. Install new fiber pedestal installations Hasn’t Started
Proposing to replace steel pole equipment with fiberglass equipment to existing pole at the intersection of Longmeadow Lane and Jerome Road. Installing a wildlife guard and replacing a down guy wire to existing pole. This permit is part of GRID.
Proposing to replace a fuse and cut-out to an existing pole at the intersection of Orly Terrace and Pleasant Hill Rd. This permit is part of GRID.
Proposing to install a trip saver to an existing pole, along with fiberglass equipment. Removing fuses and steel equipment. No wirelines will be installed or removed. This permit is part of GRID.
Greystone plans to pull a three-phase tap across Stonewall Tell Road to serve as the riser pole for the Enclave at Stonewall Tell subdivision.
Directional bores install 2-1.5" HDPE conduit and pull 1-12ct FOC - 36" min cover.
Proposing to replace 2x45' poles and 1x 40' pole in ROW. Proposing to replace existing steel equipment such as arms and buckets with fiberglass equipment. Replacing down guy wires. This permit is part of GRID.
Progress
Hasn’t Started
Complete
In Progress
Hasn’t Started
Hasn’t Started
SECTION IIID: STREETLIGHTS
The Streetlight Program is established to address the need for adequate illumination of public streets or roadways within the City of South Fulton. The goal is to aid in the safety and systematic movement of vehicular traffic within the public traveled roadway. Lighting on roadways is not provided for personal security, such as lighting of yards, driveways, or private property. In-house staff assesses requests from residents, conducts field visits and works with power companies to address inquiries for new lights, repairs, and upgrades.
Last year, Mayor and Council approved a resolution adopting the Streetlight Masterplan. The masterplan provides options for street and pedestrian light poles, styles, spacing, lighting technology and control, and appropriate lighting levels for various locations such as: state roads, arterials minor residential streets, major street corridors including those with existing and proposed bike lanes, controlled intersections, roundabouts, uncontrolled pedestrian crossings, transit station street areas, and parks.
Additionally, the city is looking at various alternatives to upgrade the infrastructure, including solar lights. The city has spoken with a vendor with a good experience in providing high-quality solar lighting solutions. Two TSPLOST projects where the city has investigated the possibility of solar lighting are the combined OSI 601/OSI615 Old Fairburn Road-Stonewall Tell Road at Union Road roundabouts projects for overhead lighting and the P 901 Enon Road Sidewalk project for pedestrian scale lighting. Procurement options include a monthly fee to the power company or a one-time upfront purchase and installation cost to consider for each. Time to break even on the investment is 8-10 years.
Lastly, the department is developing a priority list to install and/or upgrade streetlights on all corridors with proposed and existing sidewalks, State routes, and intersections. All sidewalk projects will also include pedestrian lights. Upon completion, staff will meet with the power companies to draft an implementation plan that will include costs and schedules.
Requests for streetlights- new and upgrades- received to date are detailed in Exhibit A. There is an ample number of streetlights proposed during the construction of our capital and TSPLOST projects. The estimated number of lights, by project id, are listed in Exhibit B.
STREETLIGHT
Quote/Proposal
Quote/Proposal
Quote/Proposal
Quote/Proposal pending
Quote/Proposal pending
T-SPLOST AND CAPITAL PROJECTS
NUMBER OF STREETLIGHTS
SECTION IV:
Solid Waste Group Purpose and Responsibilities
The City of South Fulton Solid Waste Group is responsible for managing and regulating solid waste services within the city limits. Solid Waste is supported through the Solid Waste Enterprise fund. Specific responsibilities include managing residential solid waste, residential bulk collections, commercial collections, convenience cans, education and outreach. The group also operates the Merk Miles Citizens Convenience Center. This report covers the period of June 26 through July 25th .
Residential service includes weekly garbage and monthly bulk collection activities. In July, all key categories for requests were up, including newly constructed homes and bulk requests. These requests show that new homes coming online remain strong and likely residents are aware and know how to request Bulk Service.
Requests For Service
Source: TracEZ
Solid Waste hosted District 7 Recycling and Paper Shredding Event on July 26, 2025
Service Complaints
Service complaints increased in June and remained elevated in July, with a significant rise in Missed Curbside Garbage reports. This category continues to account for the majority of complaints and reflects a notable upward trend over the past three months
Service Complaints
Source: TracEZ
Deliveries and Maintenance
Deliveries and maintenance continue to grow. These activities are led by internal staff. Activities include servicing convenience cans throughout the city, maintaining the recycling program and the repair and replacement of carts.
Deliveries and Maintenance
Source: Solid Waste Group
Merk Miles Citizens Convenience Center
The City of South Fulton operates the Merk Miles Citizens Convenience Center through a thirdparty vendor. This facility accepts Municipal Solid Waste (MSW), Construction Debris (C&D) and recycling. Data is reported through June 2025. Recycling continues to grow. The total number of carts service remains flat but the amount per weight per vehicle continues to grow.
Merk Miles Recycling & Municipal Solid Waste Activity
Source: Latham Sanitation
Events and Activities in July Education
On July 18, staff from the Solid Waste Department visited the fire station to further educate the firefighters on the do's and don'ts of the recycling program that includes several important guidelines. Do rinse out all bottles, plastic cups, and cans before placing them in the bin to maintain sanitation. Don’t place paper towels in the recycling, as they are not accepted. These rules help keep the recycling area clean and safe for everyone. Solid Waste sponsored the landscaping design and plant installation at Wolf Creek as part of ongoing efforts to beautify the city. The project features low-maintenance, sustainable plantings that enhance the area’s visual appeal.
Special Events
The Solid Waste Department hosted the district 7 Paper Shredding and Recycling Event on July 26th from 11:00 AM to 2:00 PM at Tri-Counties Plaza. Thirty-one (31) residents participated in the recycling activities, and seventy-four (74) residents utilized the paper shredding service. The next event will be for District 5 on August 9, 2025, from 9:00 AM to 12:00 PM at the Burdette Tennis Center.