Level 05: Erasmus Exchange - Valby Masking Proposal.

Page 19

Onsite Typical Erection Plan:

16.0 m

18.0 m

HC 01 HC 01 HC 01 HC 01 HC 04 HC 04 HC 04 HC 05 HC 02 HC 02 HC 02 HC 02 HC 02 HC 03

HC 01 HC 01 HC 01 HC 01 HC 04 HC 04 HC 04 HC 05 HC 02 HC 02 HC 02 HC 02 HC 02 HC 03

HC 11 HC 11 HC 11 HC 11 HC 11 HC 11 HC 02 HC 02 HC 07

HC 07 HC 06 HC 06 C HC 06 HC 06 HC 06

HC 02 HC 02 HC 02

HC 02 HC 02 HC 02 HC 02

D2

1. Once superstructure has been erected (Including stairwell) the hollow-core elements will be able to be inserted upon the LB walls. HC 02 2. First: the hollow decks closest to the stairwell (in all compartments) will be inserted & fixed, to allow a starting platform to work from. 1. Suitable formwork & Concrete Prop-systems to be used if necessary. 3. Followed by Flat B, inserting the decking from the internals to the external wall element. To allow a working platform to be formed & joined to the super-structural elements. 4. Flat F & adjacent flat B; will then be laid & formed into the existing party wall at same time. Given time to set before moving onto the next adjacent compartmentalised section of flats. 5. Finally Flat C will be placed to allow the stairwell’s opening. 6. Once all decking components have been inserted. 1. Floor build-up will commence, with the exception of the floor’s timber finish & ceiling’s plasterboard on the underside. 2. Allowing other contractor’s to work on this level for: 1. Electrics/Services. 2. Pre-fabricated wall panels. 3. Door/Window & wall façade insertion.


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.
Level 05: Erasmus Exchange - Valby Masking Proposal. by CJ Gregory. - Issuu