Wilson Lane Construction Programme - 9.3.22

Page 1

WILSON LANE CURRENT CONSTRUCTION PROGRAMME 9.3.22 ID

1

Task Name

Dur

Wills Street

2

Tender Submission and review

3

Receive tender doc's

7

Off site works

11

Stage 1 Subcontract letting

17

Construction

18

Stage 1 Building Permit Structure Basement

Start

Finish

% Comple

1307 d

Fri 30/06/17

Tue 13/06/23 32%

20 d

Fri 30/06/17

Mon 31/07/17 100%

35 d

Fri 30/06/17

Wed 23/08/17 100%

166 d

Thu 24/08/17

Fri 25/05/18

10 d

Thu 31/08/17

Thu 14/09/17 100%

1111 d

Mon 21/05/18

Tue 13/06/23 27%

849 d

Mon 21/05/18

Fri 25/03/22

8d

Mon 21/05/18

24

Civil/Excavation Works

12 d

Wed 30/05/18

Fri 15/06/18

100%

29

Concrete/Bored Piers Capping beam

37 d

Mon 18/06/18

Tue 7/08/18

100%

38

Bulk and detailed excavation Top Half

8d

Wed 8/08/18

Fri 17/08/18

100%

41

Shotcrete Grid Top Half

8d

Mon 20/08/18

46

Sewer

44 d

Thu 12/07/18

Tue 11/09/18 100%

52

Bulk and detailed excavation Bottom Half

10 d

Thu 30/08/18

Wed 12/09/18 100%

55

Shotcrete Grid 5 Bottom Half

8d

Thu 13/09/18

Mon 24/09/18 100%

60

Lift pit & Shaft

14 d

Thu 13/09/18

Tue 2/10/18

100%

66

Structure Basement

759 d

Tue 25/09/18

Fri 25/03/22

96% 100%

Wed 30/05/18 100%

Wed 29/08/18 100%

67

Install stormwater pits pumps and Grates to Basement

8d

Tue 25/09/18

Thu 4/10/18

68

Detailed excavation of Pad footings

3d

Tue 25/09/18

Thu 27/09/18 100%

69

FRP Pad Footings

8d

Thu 27/09/18

Mon 8/10/18 100%

70

Structural Engineer Inspection

0d

Mon 8/10/18

Mon 8/10/18 100%

71

Install sand fabric & Mesh

10 d

Tue 9/10/18

Mon 22/10/18 100%

72

Structural Engineer Inspection

0d

Mon 22/10/18

Mon 22/10/18 100%

73

Pour slab

2d

Tue 23/10/18

Wed 24/10/18 100%

74

Slab Cure Time

3d

Thu 25/10/18

Mon 29/10/18 100%

75

Christmas Shutdown Delay

40 d

Tue 30/10/18

Wed 16/01/19 100%

76

Install PCP Retention System

Mon 21/01/19 100%

77

Delay until receipt of executed contract

78 79

Second Stage of Project

272 d

Thu 10/03/22

Fri 25/03/22

Delay until receipt of executed contract

95%

Tue 13/06/23 0%

Second Stage of Project Second Stage - Critical Documents

10 d

Thu 10/03/22

Fri 25/03/22

0%

80

Receipt of Building Permit and Town Planning Requirements (By others)

10 d

Thu 10/03/22

Fri 25/03/22

0%

Receipt of Building Permit and Town Planning Requirements (By others)

81

Confirm "For Construction" Docs

10 d

Thu 10/03/22

Fri 25/03/22

0%

Confirm "For Construction" Docs

82

Confirm Concrete Outline Plan

5d

Mon 21/03/22

Fri 25/03/22

0%

83

Final Construction Design - FROZEN

0d

Fri 25/03/22

Fri 25/03/22

0%

84

Second Stage - Critical Documents

Thu 17/01/19 Tue 22/01/19

Stage 2 Subcontract letting

Confirm Concrete Outline Plan 25/03/22 Stage 2 Subcontract letting

85 d

Tue 29/03/22

Mon 15/08/22 0%

85

Issue construction doc's to Precast Concrete Trade

2d

Tue 29/03/22

Wed 30/03/22 0%

86

Review and let Precast Concrete package

2d

Thu 31/03/22

Fri 1/04/22

0%

Review and let Precast Concrete package

87

Issue construction doc's to Structure trades

4d

Tue 29/03/22

Fri 1/04/22

0%

Issue construction doc's to Structure trades

88

Issue construction doc's to Services trades

4d

Mon 4/04/22

Thu 7/04/22

0%

89

Review and let Concrete package

3d

Mon 4/04/22

Wed 6/04/22 0%

90

Review and let Elec, Mech, Sprinklers & Hyd

3d

Thu 7/04/22

Mon 11/04/22 0%

91

Review and let Structural Steel package

10 d

Tue 12/04/22

Wed 4/05/22 0%

Review and let Structural Steel package

92

Issue construction doc's to Front Fascade

10 d

Fri 8/04/22

Mon 2/05/22 0%

Issue construction doc's to Front Fascade

93

Issue construction doc's to Remaining Trades

20 d

Tue 3/05/22

Wed 1/06/22 0%

94

Review and let Front Fascade package

10 d

Tue 3/05/22

Tue 17/05/22 0%

95

Review and let Remaining Trades

40 d

Wed 18/05/22

Tue 19/07/22 0%

96

Shop Drawings

81 d

Mon 4/04/22

Mon 15/08/22 0%

Issue construction doc's to Precast Concrete Trade

Issue construction doc's to Services trades Review and let Concrete package Review and let Elec, Mech, Sprinklers & Hyd

Issue construction doc's to Remaining Trades Review and let Front Fascade package Review and let Remaining Trades Shop Drawings

97

Precast Concrete

77 d

Mon 4/04/22

Tue 9/08/22

0%

Precast Concrete

98

Ground Floor

35 d

Mon 4/04/22

Thu 2/06/22

0%

Ground Floor

Tue 3/05/22

0%

99

Submit Precast Concrete Shop DWG's for approval

15 d

Mon 4/04/22

100

Consultants & Architects Review

5d

Wed 4/05/22

101

Fabricate Precast Concrete

15 d

Thu 12/05/22

25 d

Mon 30/05/22

102

1st Floor

Thu 2/06/22

10 d

Mon 30/05/22

Consultants & Architects Review

5d

Wed 15/06/22

Tue 21/06/22 0%

105

Fabricate Precast Concrete

10 d

Wed 22/06/22

Wed 6/07/22 0%

22 d

Wed 15/06/22

Mon 18/07/22 0% Thu 23/06/22 0%

Fri 10/06/22

Submit Precast Concrete Shop DWG's for approval

7d

Wed 15/06/22

108

Consultants & Architects Review

5d

Fri 24/06/22

109

Fabricate Precast Concrete

10 d

Mon 4/07/22

Mon 18/07/22 0%

22 d

Fri 24/06/22

Thu 28/07/22 0%

Fri 1/07/22

Submit Precast Concrete Shop DWG's for approval

7d

Fri 24/06/22

112

Consultants & Architects Review

5d

Wed 6/07/22

Wed 13/07/22 0%

113

Fabricate Precast Concrete

10 d

Thu 14/07/22

Thu 28/07/22 0%

22 d

Wed 6/07/22

Tue 9/08/22

0%

114

4th Floor & Roof

Consultants & Architects Review Fabricate Precast Concrete 2nd Floor Submit Precast Concrete Shop DWG's for approval Consultants & Architects Review

0%

111

Tue 5/07/22

Submit Precast Concrete Shop DWG's for approval

0%

107

3rd Floor

Fabricate Precast Concrete 1st Floor

Wed 6/07/22 0%

Submit Precast Concrete Shop DWG's for approval

110

Consultants & Architects Review

0%

104

2nd Floor

Submit Precast Concrete Shop DWG's for approval

Wed 11/05/22 0%

103

106

Fabricate Precast Concrete 3rd Floor Submit Precast Concrete Shop DWG's for approval

0%

Consultants & Architects Review Fabricate Precast Concrete 4th Floor & Roof Submit Precast Concrete Shop DWG's for approval

115

Submit Precast Concrete Shop DWG's for approval

7d

Wed 6/07/22

Fri 15/07/22

0%

116

Consultants & Architects Review

5d

Mon 18/07/22

Fri 22/07/22

0%

117

Fabricate Precast Concrete

10 d

Tue 26/07/22

Tue 9/08/22

0%

70 d

Mon 4/04/22

Thu 28/07/22 0%

Concrete Post Tension & Structural Design Ground Floor

118 119

Concrete Post Tension & Structural Design

30 d

Mon 4/04/22

Thu 26/05/22 0%

120

Submit PT & Concrete Shop DWG's for approval

15 d

Mon 4/04/22

Tue 3/05/22

121

Consultants & Architects Review

5d

Wed 4/05/22

Wed 11/05/22 0%

122

Procure PT Components

10 d

Thu 12/05/22

Thu 26/05/22 0%

25 d

Wed 4/05/22

Thu 9/06/22

123

Ground Floor

1st Floor

0%

Submit PT & Concrete Shop DWG's for approval

10 d

Wed 4/05/22

Wed 18/05/22 0%

125

Consultants & Architects Review

5d

Thu 19/05/22

Thu 26/05/22 0%

126

Procure PT Components

10 d

Fri 27/05/22

25 d

Thu 19/05/22

2nd Floor

Thu 9/06/22

Tue 28/06/22 0%

Submit PT & Concrete Shop DWG's for approval

10 d

Thu 19/05/22

Thu 2/06/22

0%

129

Consultants & Architects Review

5d

Fri 3/06/22

Thu 9/06/22

0%

130

Procure PT Components

10 d

Fri 10/06/22

Tue 28/06/22 0%

25 d

Fri 3/06/22

Wed 13/07/22 0%

3rd Floor

132

Submit PT & Concrete Shop DWG's for approval

10 d

Fri 3/06/22

Mon 20/06/22 0%

133

Consultants & Architects Review

5d

Tue 21/06/22

Tue 28/06/22 0%

134

Procure PT Components

10 d

Wed 29/06/22

Wed 13/07/22 0%

25 d

Tue 21/06/22

Thu 28/07/22 0%

135

4th Floor

136

Submit PT & Concrete Shop DWG's for approval

10 d

Tue 21/06/22

137

Consultants & Architects Review

5d

Wed 6/07/22

Wilson Lane Current Program 30.11.21

Tue 5/07/22

Fabricate Precast Concrete

Submit PT & Concrete Shop DWG's for approval Consultants & Architects Review Procure PT Components 1st Floor Submit PT & Concrete Shop DWG's for approval Consultants & Architects Review Procure PT Components

0%

128

131

Consultants & Architects Review

0%

124

127

3rd Quarter Sep

Jul

96%

Site set up

3d

1st Half

May

100%

19

691 d

1st Half 1st Quarter Mar

Jan

0%

Wed 13/07/22 0%

2nd Floor Submit PT & Concrete Shop DWG's for approval Consultants & Architects Review Procure PT Components 3rd Floor Submit PT & Concrete Shop DWG's for approval Consultants & Architects Review Procure PT Components 4th Floor Submit PT & Concrete Shop DWG's for approval Consultants & Architects Review

Nov

Jan

1st Quarter Mar

May

Jul


WILSON LANE CURRENT CONSTRUCTION PROGRAMME 9.3.22 ID

138 139 140

Task Name

Dur

Procure PT Components Services & Concrete Temporary Propping Design Basement, Ground Floor

Start

10 d

Thu 14/07/22

30 d

Tue 12/04/22

Finish

% Comple

Thu 28/07/22 0% Fri 3/06/22

1st Half Jan

1st Quarter Mar

0%

Services & Concrete Temporary Propping Design Basement, Ground Floor

15 d

Tue 12/04/22

Thu 12/05/22 0%

141

Submit Services Shop DWG's for approval

10 d

Tue 12/04/22

Wed 4/05/22 0%

142

Consultants & Architects Review

5d

Thu 5/05/22

Thu 12/05/22 0%

143

1st Floor, 2nd Floor, 3rd Floor, 4th Floor

20 d

Thu 5/05/22

Fri 3/06/22

0%

Consultants & Architects Review Submit Services Shop DWG's for approval

Submit Services Shop DWG's for approval

15 d

Thu 5/05/22

Fri 27/05/22

0%

Consultants & Architects Review

5d

Mon 30/05/22

Fri 3/06/22

0%

65 d

Thu 5/05/22

Mon 15/08/22 0%

Structural Steel

Wed 6/07/22 0%

1st Floor, 2nd Floor, 3rd Floor, 4th Floor

147

40 d

Thu 5/05/22

148

Submit Steel Shop DWG's for approval

20 d

Thu 5/05/22

Fri 3/06/22

0%

149

Consultants & Architects Review

5d

Mon 6/06/22

Fri 10/06/22

0%

150

Fabricate Steel

15 d

Wed 15/06/22

Wed 6/07/22 0%

45 d

Mon 6/06/22

Mon 15/08/22 0%

151

1st Floor, 2nd Floor, 3rd Floor, 4th Floor

Roof

Consultants & Architects Review

Submit Steel Shop DWG's for approval Consultants & Architects Review Fabricate Steel Roof Submit Steel Shop DWG's for approval

152

Submit Steel Shop DWG's for approval

15 d

Mon 6/06/22

Wed 29/06/22 0%

153

Consultants & Architects Review

5d

Thu 30/06/22

Wed 6/07/22 0%

154

Fabricate Roof Steel

25 d

Thu 7/07/22

Mon 15/08/22 0%

50 d

Wed 18/05/22

Wed 3/08/22 0%

Fascade

Wed 3/08/22 0%

1st Floor, 2nd Floor, 3rd Floor, 4th Floor

155 156

Fascade

Consultants & Architects Review Fabricate Roof Steel

50 d

Wed 18/05/22

157

Submit Fascade Shop DWG's for approval

20 d

Wed 18/05/22

Fri 17/06/22

0%

158

Consultants & Architects Review

5d

Mon 20/06/22

Fri 24/06/22

0%

159

Fabricate Fascade

25 d

Tue 28/06/22

Wed 3/08/22 0%

253 d

Mon 11/04/22

Tue 13/06/23 0%

Stage 2 Building Permit Works Structure Ground Floor

160

1st Floor, 2nd Floor, 3rd Floor, 4th Floor

Stage 2 Building Permit Works

Submit Fascade Shop DWG's for approval Consultants & Architects Review Fabricate Fascade

161

Structure Ground Floor

49 d

Mon 11/04/22

Mon 4/07/22 0%

162

Re-Mobilise to Site

4d

Mon 11/04/22

Thu 14/04/22 0%

163

Install Masonry to Basement

7d

Tue 26/04/22

Wed 4/05/22 0%

164

Shotcrete to side of Ramp

3d

Thu 5/05/22

Tue 10/05/22 0%

165

Form, Reo + Pour In-Situ Wall in Basement

7d

Wed 11/05/22

Thu 19/05/22 0%

166

Complete Precast Works

3d

Thu 5/05/22

Tue 10/05/22 0%

167

Install Frames and ply

12 d

Thu 19/05/22

Mon 6/06/22 0%

Install Frames and ply

168

Install all services including fire collars

5d

Wed 1/06/22

Tue 7/06/22

0%

Install all services including fire collars

169

Install reo to deck

5d

Wed 1/06/22

Tue 7/06/22

0%

170

Install pt to deck

2d

Thu 2/06/22

Fri 3/06/22

0%

171

Install edge form

5d

Tue 7/06/22

Wed 15/06/22 0%

172

Hold point review all heights & grades

0d

Wed 15/06/22

Wed 15/06/22 0%

15/06/22

173

Engineers Inspection

0d

Wed 15/06/22

Wed 15/06/22 0%

15/06/22

174

Pour 1st half slab

1d

Thu 16/06/22

Thu 16/06/22 0%

Pour 1st half slab

175

Install reo to deck

5d

Wed 8/06/22

Thu 16/06/22 0%

Install reo to deck

176

Install pt to deck

2d

Thu 16/06/22

177

Install edge form

3d

Thu 16/06/22

Mon 20/06/22 0%

178

Hold point review all heights & grades

0d

Mon 20/06/22

Mon 20/06/22 0%

20/06/22

179

Engineers Inspection

0d

Mon 20/06/22

Mon 20/06/22 0%

20/06/22

180

Pour 2nd half slab

1d

Tue 21/06/22

Tue 21/06/22 0%

181

FRP Columns

3d

Wed 22/06/22

Fri 24/06/22

0%

FRP Columns

182

Cure Ground Slab

3d

Wed 22/06/22

Fri 24/06/22

0%

Cure Ground Slab

183

Install Precast On Ground Floor + PC19

5d

Tue 28/06/22

Mon 4/07/22 0%

26 d

Thu 30/06/22

Tue 9/08/22

184

Structure First Floor

Fri 17/06/22

185

Install Frames and ply

10 d

Thu 30/06/22

Thu 14/07/22 0%

186

Install edge form & handrail

3d

Fri 15/07/22

Tue 19/07/22 0%

187

Install all services including fire collars

3d

Wed 13/07/22

188

Install reo to deck

5d

Wed 13/07/22

Tue 19/07/22 0%

189

Install pt to deck

2d

Tue 19/07/22

Wed 20/07/22 0%

190

Engineers Inspection

0d

Wed 20/07/22

Wed 20/07/22 0%

191

Pour 1st half slab

1d

Thu 21/07/22

Thu 21/07/22 0%

192

Install edge form & handrail

3d

Wed 20/07/22

193

Install all services including fire collars

3d

Mon 18/07/22

Wed 20/07/22 0%

194

Install reo to deck

5d

Thu 21/07/22

Thu 28/07/22 0%

195

Install pt to deck

2d

Thu 28/07/22

Fri 29/07/22

0%

196

Engineers Inspection

0d

Fri 29/07/22

Fri 29/07/22

0%

197

Pour 2nd half slab

1d

Mon 1/08/22

198

FRP Columns

4d

Tue 2/08/22

Fri 5/08/22

0%

199

Install Precast On 1st Floor + PC23

3d

Thu 4/08/22

Tue 9/08/22

0%

25 d

Fri 5/08/22

200

Structure Second Floor Apartments

Fri 15/07/22

Fri 22/07/22

Install Masonry to Basement Shotcrete to side of Ramp Form, Reo + Pour In-Situ Wall in Basement Complete Precast Works

Install reo to deck Install pt to deck Install edge form

Install pt to deck Install edge form

Pour 2nd half slab

Install Precast On Ground Floor + PC19 Structure First Floor Install Frames and ply Install edge form & handrail Install all services including fire collars

0%

0%

Install reo to deck Install pt to deck 20/07/22 Pour 1st half slab Install edge form & handrail Install all services including fire collars Install reo to deck Install pt to deck 29/07/22 Pour 2nd half slab

Mon 1/08/22 0%

Tue 13/09/22 0%

201

Install Frames and ply

10 d

Fri 5/08/22

202

Install edge form & handrail

3d

Tue 23/08/22

Thu 25/08/22 0%

203

Install all services including fire collars

3d

Thu 18/08/22

Tue 23/08/22 0%

204

Install reo to deck

5d

Thu 18/08/22

Thu 25/08/22 0%

205

Install pt to deck

2d

Thu 25/08/22

Fri 26/08/22

0%

206

Engineers Inspection

0d

Fri 26/08/22

Fri 26/08/22

0%

207

Pour 1st half slab

1d

Mon 29/08/22

Mon 29/08/22 0%

208

Install edge form & handrail

3d

Fri 26/08/22

Tue 30/08/22 0%

209

Install all services including fire collars

3d

Wed 24/08/22

210

Install reo to deck

5d

Mon 29/08/22

211

Install pt to deck

2d

Fri 2/09/22

Mon 5/09/22 0%

212

Engineers Inspection

0d

Mon 5/09/22

Mon 5/09/22 0%

213

Pour 2nd half slab

1d

Tue 6/09/22

Tue 6/09/22

214

FRP Columns

4d

Wed 7/09/22

Tue 13/09/22 0%

215

Install Precast On 2nd Floor

2d

Fri 9/09/22

Tue 13/09/22 0%

216

Structure Third Floor Apartments

24 d

Thu 8/09/22

Mon 17/10/22 0%

Fri 19/08/22

0%

Fri 26/08/22

0%

Fri 2/09/22

0%

Install Frames and ply

9d

Thu 8/09/22

Wed 21/09/22 0%

218

Install edge form & handrail

3d

Thu 22/09/22

Wed 28/09/22 0%

219

Install all services including fire collars

3d

Tue 20/09/22

Thu 22/09/22 0%

220

Install reo to deck

5d

Tue 20/09/22

Wed 28/09/22 0%

221

Install pt to deck

2d

Wed 28/09/22

Thu 29/09/22 0%

222

Engineers Inspection

0d

Thu 29/09/22

Thu 29/09/22 0%

223

Pour 1st half slab

1d

Fri 30/09/22

224

Install edge form & handrail

3d

Thu 29/09/22

Mon 3/10/22 0%

225

Install all services including fire collars

3d

Tue 27/09/22

Thu 29/09/22 0%

Fri 30/09/22

FRP Columns Install Precast On 1st Floor + PC23 Structure Second Floor Apartments Install Frames and ply Install edge form & handrail Install all services including fire collars Install reo to deck Install pt to deck 26/08/22 Pour 1st half slab Install edge form & handrail Install all services including fire collars Install reo to deck Install pt to deck 5/09/22 Pour 2nd half slab

0%

217

Wilson Lane Current Program 30.11.21

Re-Mobilise to Site

0%

0%

0%

Nov

1st Floor, 2nd Floor, 3rd Floor, 4th Floor

145

Structural Steel

3rd Quarter Sep

Jul Procure PT Components

Submit Services Shop DWG's for approval

144 146

1st Half

May

FRP Columns Install Precast On 2nd Floor Structure Third Floor Apartments Install Frames and ply Install edge form & handrail Install all services including fire collars Install reo to deck Install pt to deck 29/09/22 Pour 1st half slab Install edge form & handrail Install all services including fire collars

Jan

1st Quarter Mar

May

Jul


WILSON LANE CURRENT CONSTRUCTION PROGRAMME 9.3.22 ID

Task Name

Dur

Start

Finish

% Comple

226

Install reo to deck

5d

Fri 30/09/22

Thu 6/10/22

0%

227

Install pt to deck

2d

Thu 6/10/22

Fri 7/10/22

0%

228

Engineers Inspection

0d

Fri 7/10/22

Fri 7/10/22

0%

229

Pour 2nd half slab

1d

Tue 11/10/22

Tue 11/10/22 0%

230

FRP Columns

4d

Wed 12/10/22

Mon 17/10/22 0%

231

Install Precast On 3rd Floor

2d

Fri 14/10/22

Mon 17/10/22 0%

19 d

Fri 14/10/22

Mon 14/11/22 0% Tue 25/10/22 0%

232

Structure Fourth Floor Apartments

233

Install Frames and ply

8d

Fri 14/10/22

234

Install edge form & handrail

3d

Wed 26/10/22

235

Install all services including fire collars

3d

Mon 24/10/22

236

Install reo to deck

5d

Mon 24/10/22

Fri 28/10/22

0%

237

Install pt to deck

2d

Fri 28/10/22

Thu 3/11/22

0%

238

Engineers Inspection

0d

Thu 3/11/22

Thu 3/11/22

0%

239

Pour 1st half slab

1d

Fri 4/11/22

Fri 4/11/22

0%

240

Install edge form & handrail

3d

Thu 3/11/22

Mon 7/11/22 0%

241

Install all services including fire collars

3d

Thu 27/10/22

Thu 3/11/22

242

Install reo to deck

5d

Fri 4/11/22

243

Install pt to deck

2d

Thu 10/11/22

Fri 11/11/22

0%

244

Engineers Inspection

0d

Fri 11/11/22

Fri 11/11/22

0%

1d

Mon 14/11/22

Mon 14/11/22 0%

19 d

Tue 15/11/22

Mon 12/12/22 0%

245 246

Pour 2nd half slab Structure Roof

Fri 28/10/22

1st Quarter Mar

May

1st Half 3rd Quarter Sep Install reo to deck

Jul

FRP Columns Install Precast On 3rd Floor Structure Fourth Floor Apartments Install Frames and ply Install edge form & handrail Install all services including fire collars Install reo to deck Install pt to deck 3/11/22 Pour 1st half slab Install edge form & handrail Install all services including fire collars Install reo to deck

Thu 10/11/22 0%

1d

Tue 15/11/22

Tue 15/11/22 0%

Install Columns

5d

Wed 16/11/22

Tue 22/11/22 0%

249

Install Structural Steel

7d

Wed 23/11/22

Thu 1/12/22

250

Install Purlins to roof

6d

Fri 2/12/22

Mon 12/12/22 0%

251

Structural Engineer Inspection

0d

Mon 12/12/22

Mon 12/12/22 0% Thu 15/12/22 0%

Install pt to deck 11/11/22 Pour 2nd half slab Structure Roof Land surveyor column locations Install Columns Install Structural Steel

0%

Install Purlins to roof 12/12/22 Strip form work

102 d

Fri 8/07/22

253

Strip Basement Floor & back Prop

0d

Fri 8/07/22

254

Remove Basement Floor props

0d

Tue 27/09/22

Tue 27/09/22 0%

255

Strip Ground Floor & back prop

0d

Thu 18/08/22

Thu 18/08/22 0%

256

Remove Ground Floor props

0d

Thu 27/10/22

Thu 27/10/22 0%

257

Strip First Floor and back prop

0d

Tue 27/09/22

Tue 27/09/22 0%

258

Remove First Floor props

0d

Wed 30/11/22

Wed 30/11/22 0%

259

Strip Second floor & back Prop

0d

Thu 27/10/22

Thu 27/10/22 0%

260

Strip Third floor & back Prop

0d

Wed 30/11/22

Wed 30/11/22 0%

30/11/22

261

Fully tension grout all peno

0d

Wed 30/11/22

Wed 30/11/22 0%

30/11/22

262

Remove Props Second Floors

0d

Wed 30/11/22

Wed 30/11/22 0%

30/11/22

263

Remove Props Third Floor

0d

Thu 15/12/22

Thu 15/12/22 0%

29 d

Fri 9/12/22

Tue 14/02/23 0%

252

264

Roofing

Fri 8/07/22

0%

265

Install Handrail and access towers to roof

5d

Fri 9/12/22

Thu 15/12/22 0%

266

Pull wire to roof

3d

Fri 16/12/22

Tue 20/12/22 0%

267

Install Insulation & Roof sheeting

6d

Thu 12/01/23

Thu 19/01/23 0%

268

Install flashing Trims Gutters and DP's

3d

Fri 20/01/23

Tue 24/01/23 0%

269

Install Plant structure

10 d

Fri 20/01/23

Tue 7/02/23

270

Install Plant to roof area

5d

Wed 8/02/23

Tue 14/02/23 0%

137 d

Wed 28/09/22

Wed 24/05/23 0%

271

External Fascades

May

Pour 2nd half slab

0%

Land surveyor column locations

1st Quarter Mar

Jan

7/10/22

Wed 26/10/22 0%

248

Nov

Install pt to deck

0%

247

Strip form work

1st Half Jan

8/07/22 27/09/22 18/08/22 27/10/22 27/09/22 30/11/22 27/10/22

15/12/22 Roofing Install Handrail and access towers to roof Pull wire to roof Install Insulation & Roof sheeting Install flashing Trims Gutters and DP's Install Plant structure

0%

Install Plant to roof area External Fascades Install Steel Sub-Framing West Canopy

272

Install Steel Sub-Framing West Canopy

10 d

Wed 28/09/22

Wed 12/10/22 0%

273

Install Roofing Components for West canopy

15 d

Thu 13/10/22

Mon 7/11/22 0%

274

Install Steel Sub-Framing for Balconies

15 d

Thu 1/12/22

275

Stormwater Rough-In

10 d

Thu 1/12/22

Thu 15/12/22 0%

276

Install Balustrade Cladding

20 d

Fri 16/12/22

Wed 8/02/23 0%

277

Install Waterproofing on Balconies

15 d

Wed 1/02/23

Thu 23/02/23 0%

Install Waterproofing on Balconies

278

Install Timber Strapping

15 d

Wed 1/02/23

Thu 23/02/23 0%

Install Timber Strapping

279

Install Remainging Metal Cladding

20 d

Thu 9/02/23

Thu 9/03/23

0%

280

Install Metal Balustrades

20 d

Fri 24/02/23

Fri 24/03/23

0%

281

Install/Paint Misc Soffits on Balconies

10 d

Tue 28/03/23

Tue 18/04/23 0%

282

Install Tiling on Balconies

25 d

Wed 19/04/23

Wed 24/05/23 0%

142 d

Wed 28/09/22

Wed 31/05/23 0%

283 284

External Framing and Rough in

57 d

Wed 28/09/22

Install kingspan to soffit

10 d

Thu 1/12/22

Thu 15/12/22 0%

286

Rough in mech to ceiling

10 d

Wed 28/09/22

Wed 12/10/22 0%

287

Rough in sprinkler to ceiling

10 d

Wed 5/10/22

Wed 19/10/22 0%

288

Rough in Hydro &Elec

10 d

Thu 13/10/22

Wed 26/10/22 0%

289

Install external wall framing & finishes

15 d

Thu 1/12/22

59 d

Fri 28/10/22

Light weight Frames and cladding Ground Floor

Fri 13/01/23

Fri 13/01/23

Install Roofing Components for West canopy Install Steel Sub-Framing for Balconies

0%

285

290

Light weight Frames and cladding Basement

Fri 13/01/23

0%

Stormwater Rough-In Install Balustrade Cladding

Install Remainging Metal Cladding Install Metal Balustrades Install/Paint Misc Soffits on Balconies Install Tiling on Balconies External Framing and Rough in Light weight Frames and cladding Basement Install kingspan to soffit Rough in mech to ceiling Rough in sprinkler to ceiling Rough in Hydro &Elec Install external wall framing & finishes

0%

Tue 21/02/23 0%

Light weight Frames and cladding Ground Floor Install Internal external wall framing

291

Install Internal external wall framing

12 d

Fri 28/10/22

Thu 17/11/22 0%

292

Install Alluminium windows frames

13 d

Fri 18/11/22

Wed 7/12/22 0%

Install Alluminium windows frames

293

Install Glass Blocks

5d

Wed 30/11/22

Wed 7/12/22 0%

Install Glass Blocks

294

Install glazing

10 d

Thu 8/12/22

Thu 12/01/23 0%

295

Install substrate for Tiling

8d

Thu 8/12/22

Mon 19/12/22 0%

296

Install Tiling

8d

Thu 12/01/23

Mon 23/01/23 0%

Install Tiling

297

Install Misc cladding

8d

Thu 12/01/23

Mon 23/01/23 0%

Install Misc cladding

298

Install remaiming soffits

10 d

Tue 24/01/23

299

Paint Caulk and defect

7d

Fri 10/02/23

Tue 21/02/23 0%

55 d

Thu 1/12/22

Fri 17/03/23

Thu 15/12/22 0%

300

Light weight Frames and cladding First Floor

Thu 9/02/23

0%

Install Internal external wall framing

10 d

Thu 1/12/22

302

Install Alluminium windows frames

10 d

Fri 16/12/22

Fri 20/01/23

0%

303

Install Glass Blocks

5d

Fri 16/12/22

Fri 13/01/23

0%

304

Install glazing

10 d

Mon 23/01/23

Wed 8/02/23 0%

305

Install battening system for metal cladding

13 d

Thu 9/02/23

Tue 28/02/23 0%

306

Install Metal Cladding

8d

Tue 21/02/23

Thu 2/03/23

307

Install Misc cladding

6d

Tue 21/02/23

Tue 28/02/23 0%

308

Install remaiming soffits

5d

Fri 3/03/23

Thu 9/03/23

0%

309

Paint Caulk and defect

5d

Fri 10/03/23

Fri 17/03/23

0%

61 d

Fri 16/12/22

Wed 19/04/23 0% Tue 31/01/23 0%

Light weight Frames and cladding Second Floor

311

Install external wall framing

15 d

Fri 16/12/22

312

Install Alluminium windows frames

7d

Wed 1/02/23

313

Install glazing

10 d

Mon 13/02/23

Wilson Lane Current Program 30.11.21

Fri 10/02/23

Install remaiming soffits

0%

301

310

Install glazing Install substrate for Tiling

Paint Caulk and defect Light weight Frames and cladding First Floor Install Internal external wall framing Install Alluminium windows frames Install Glass Blocks Install glazing Install battening system for metal cladding Install Metal Cladding

0%

0%

Mon 27/02/23 0%

Install Misc cladding Install remaiming soffits Paint Caulk and defect Light weight Frames and cladding Second Floor Install external wall framing Install Alluminium windows frames Install glazing

Jul


WILSON LANE CURRENT CONSTRUCTION PROGRAMME 9.3.22 ID

Task Name

Dur

Start

Finish

% Comple

314

Install Brickwork

12 d

Mon 13/02/23

315

Install Misc cladding

10 d

Mon 27/02/23

316

Install remaiming soffits

10 d

Tue 14/03/23

Tue 28/03/23 0%

317

Paint Caulk and defect

7d

Mon 3/04/23

Wed 19/04/23 0%

58 d

Wed 1/02/23

Mon 8/05/23 0%

318

Light weight Frames and cladding third Floor

Wed 1/03/23 0% Fri 10/03/23

Install external wall framing

15 d

Wed 1/02/23

Thu 23/02/23 0%

320

Install Alluminium windows frames

7d

Fri 24/02/23

Mon 6/03/23 0%

321

Install glazing

10 d

Tue 7/03/23

Tue 21/03/23 0%

322

Install Brickwork

12 d

Tue 7/03/23

Thu 23/03/23 0%

323

Install Misc cladding

10 d

Tue 21/03/23

Tue 4/04/23

324

Install remaiming soffits

10 d

Wed 5/04/23

Thu 27/04/23 0%

325

Paint Caulk and defect

7d

Fri 28/04/23

Mon 8/05/23 0%

93 d

Tue 13/12/22

Wed 31/05/23 0%

Light weight Frames & cladding fourth Floor Install external wall framing

15 d

Tue 13/12/22

Tue 24/01/23 0%

328

Install Alluminium windows frames

7d

Wed 25/01/23

Tue 7/02/23

329

Install glazing

10 d

Wed 8/02/23

330

Install Brickwork

12 d

Wed 8/02/23

Fri 24/02/23

0%

331

Install Misc cladding

10 d

Wed 22/02/23

Tue 7/03/23

0%

332

Install remaiming soffits

10 d

Wed 8/03/23

Wed 22/03/23 0%

333

Paint Caulk and defect

5d

Thu 25/05/23

Wed 31/05/23 0%

117 d

Fri 18/11/22

Tue 13/06/23 0%

335

Fit Off & Commission

1st Half Jul

3rd Quarter Sep

Nov

1st Quarter Mar Install Brickwork

Jan

Install Misc cladding Install remaiming soffits Paint Caulk and defect Light weight Frames and cladding third Floor Install external wall framing Install Alluminium windows frames Install glazing Install Brickwork Install Misc cladding Install remaiming soffits Paint Caulk and defect Light weight Frames & cladding fourth Floor Install external wall framing Install Alluminium windows frames

0%

Install glazing

Wed 22/02/23 0%

Install Brickwork Install Misc cladding Install remaiming soffits Paint Caulk and defect Fit Off & Commission Internal Rough in and fit off Ground Floor

88 d

Fri 18/11/22

Tue 2/05/23

Rough in ceiling space elec mech and Hydro Fire

5d

Fri 18/11/22

Thu 24/11/22 0%

337

Rough in wall space elec mech and Hydro Fire

5d

Fri 25/11/22

Thu 1/12/22

0%

Rough in wall space elec mech and Hydro Fire

338

Sheet rooms Wet areas first Including ceiling

3d

Fri 2/12/22

Wed 7/12/22 0%

Sheet rooms Wet areas first Including ceiling

339

Stop & Sand walls and celings wet areas

2d

Thu 8/12/22

340

Paint Ceilings to wet areas

2d

Mon 12/12/22

341

Sheet Plaster walls

11 d

Thu 8/12/22

342

Install timber pertical board

9d

Thu 8/12/22

Tue 20/12/22 0%

Install timber pertical board

343

Install grid framing

6d

Mon 12/12/22

Mon 19/12/22 0%

Install grid framing

344

Sheet ceiling

3d

Tue 20/12/22

345

Stop and sand walls

3d

Mon 16/01/23

Wed 18/01/23 0%

Stop and sand walls

346

Light cut out and Mech&Fire Peno's

3d

Mon 16/01/23

Wed 18/01/23 0%

Light cut out and Mech&Fire Peno's

347

Pre Paint (Base Coat)

3d

Thu 19/01/23

Mon 23/01/23 0%

Pre Paint (Base Coat)

348

Defect plaster

3d

Fri 20/01/23

Tue 24/01/23 0%

Defect plaster

349

Final coats of Paint to walls and ceilings

8d

Mon 23/01/23

Fri 3/02/23

0%

350

Install AP

1d

Tue 7/02/23

Tue 7/02/23

0%

351

Fit Off elec and Plumbinng wet areas

10 d

Tue 24/01/23

Thu 9/02/23

0%

352

ITP ITR DDA compliant install Sanitary hardware

0d

Thu 9/02/23

Thu 9/02/23

0%

353

Fit off sanitary Hardware and fixtures

3d

Fri 10/02/23

Tue 14/02/23 0%

Fit off sanitary Hardware and fixtures

354

Remaining Vinyl

5d

Wed 8/02/23

Tue 14/02/23 0%

Remaining Vinyl

355

Remaining Floor coverings and covings

6d

Wed 15/02/23

Thu 23/02/23 0%

356

Fit off Jambs

5d

Thu 23/02/23

Wed 1/03/23 0%

357

Install Joinery

6d

Wed 1/03/23

Wed 8/03/23 0%

358

Hang doors and Hardware Arch and skirts

10 d

Thu 9/03/23

Thu 23/03/23 0%

359

Paint Jams and Doors

10 d

Fri 24/03/23

Mon 17/04/23 0%

360

Fit off door Furniture

5d

Tue 18/04/23

Mon 24/04/23 0%

361

Fit Off Mech elec Fire Hydro

20 d

Wed 15/03/23

Thu 20/04/23 0%

362

Trims transitions and tactiles

3d

Mon 24/04/23

Thu 27/04/23 0%

363

Builders Clean Caulk and defect

3d

Fri 28/04/23

Tue 2/05/23

80 d

Thu 1/12/22

Wed 3/05/23 0%

Internal Rough in and fit off Level 1

Fri 9/12/22

0%

May

336

364

Internal Rough in and fit off Ground Floor

May

0%

327

334

1st Quarter Mar

0%

319

326

1st Half Jan

Rough in ceiling space elec mech and Hydro Fire

Stop & Sand walls and celings wet areas

0%

Paint Ceilings to wet areas

Tue 13/12/22 0% Fri 13/01/23

Fri 13/01/23

Sheet Plaster walls

0%

Sheet ceiling

0%

Final coats of Paint to walls and ceilings Install AP Fit Off elec and Plumbinng wet areas 9/02/23

Remaining Floor coverings and covings Fit off Jambs Install Joinery Hang doors and Hardware Arch and skirts Paint Jams and Doors Fit off door Furniture Fit Off Mech elec Fire Hydro Trims transitions and tactiles Builders Clean Caulk and defect

0% Internal Rough in and fit off Level 1 Rough in ceiling space elec mech and Hydro Fire

365

Rough in ceiling space elec mech and Hydro Fire

5d

Thu 1/12/22

366

Rough in wall space elec mech and Hydro Fire

5d

Fri 9/12/22

Thu 15/12/22 0%

Rough in wall space elec mech and Hydro Fire

367

Sheet rooms Wet areas first Including ceiling

3d

Fri 16/12/22

Tue 20/12/22 0%

Sheet rooms Wet areas first Including ceiling

368

Stop & Sand walls and celings wet areas

2d

Thu 12/01/23

369

Paint Ceilings to wet areas

2d

Mon 16/01/23

Tue 17/01/23 0%

370

Sheet Plaster walls

10 d

Thu 12/01/23

Wed 25/01/23 0%

371

Install timber perticle board

8d

Thu 12/01/23

Mon 23/01/23 0%

372

Install grid framing

3d

Mon 16/01/23

Wed 18/01/23 0%

373

Sheet ceiling

3d

Mon 23/01/23

Wed 25/01/23 0%

374

Stop and sand walls

3d

Mon 30/01/23

Wed 1/02/23 0%

Stop and sand walls

375

Light cut out and Mech&Fire Peno's

3d

Mon 30/01/23

Wed 1/02/23 0%

Light cut out and Mech&Fire Peno's

376

Pre Paint (Base Coat)

3d

Thu 2/02/23

Tue 7/02/23

0%

377

Defect plaster

5d

Fri 3/02/23

Fri 10/02/23

0%

378

Final coats of Paint to walls and ceilings

13 d

Thu 9/02/23

379

Install AP

2d

Wed 1/03/23

Thu 2/03/23

380

Fit Off elec and Plumbinng wet areas

7d

Wed 8/02/23

Thu 16/02/23 0%

381

ITP ITR DDA compliant install Sanitary hardware

0d

Thu 16/02/23

Thu 16/02/23 0%

382

Fit off sanitary Hardware and fixtures

3d

Fri 17/02/23

Wed 22/02/23 0%

Fit off sanitary Hardware and fixtures

383

Remaining Vinyl

5d

Wed 15/02/23

Wed 22/02/23 0%

Remaining Vinyl

384

Remaining Floor coverings and covings

6d

Thu 23/02/23

Thu 2/03/23

385

Fit off Jambs

3d

Thu 2/03/23

Mon 6/03/23 0%

386

Install Joinery

3d

Mon 6/03/23

Wed 8/03/23 0%

387

Hang doors and Hardware Arch and skirts

9d

Thu 9/03/23

Wed 22/03/23 0%

388

Paint Jams and Doors

5d

Thu 23/03/23

Thu 30/03/23 0%

389

Fit off door Furniture

4d

Fri 31/03/23

Wed 5/04/23 0%

390

Fit Off Mech elec Fire Hydro

20 d

Wed 22/03/23

391

Trims transitions and tactiles

1d

Wed 5/04/23

Wed 5/04/23 0% Wed 3/05/23 0%

392 393

Builders Clean Caulk and defect Internal Rough in and fit off Level 2

3d

Mon 1/05/23

89 d

Mon 16/01/23

Thu 8/12/22

Fri 13/01/23

0%

Stop & Sand walls and celings wet areas

0%

Paint Ceilings to wet areas Sheet Plaster walls Install timber perticle board Install grid framing Sheet ceiling

Pre Paint (Base Coat) Defect plaster Final coats of Paint to walls and ceilings

Tue 28/02/23 0%

Fri 28/04/23

Tue 6/06/23

Install AP

0%

Fit Off elec and Plumbinng wet areas 16/02/23

Remaining Floor coverings and covings

0%

Fit off Jambs Install Joinery Hang doors and Hardware Arch and skirts Paint Jams and Doors Fit off door Furniture Fit Off Mech elec Fire Hydro

0%

0%

Trims transitions and tactiles Builders Clean Caulk and defect Internal Rough in and fit off Level 2 Rough in ceiling space elec mech and Hydro Fire

394

Rough in ceiling space elec mech and Hydro Fire

15 d

Mon 16/01/23

Wed 8/02/23 0%

395

Rough in wall space elec mech and Hydro Fire

10 d

Wed 1/02/23

Wed 15/02/23 0%

396

Sheet rooms Wet areas first Including ceiling

10 d

Thu 16/02/23

Thu 2/03/23

0%

Sheet rooms Wet areas first Including ceiling

397

Stop & Sand walls and celings wet areas

5d

Fri 3/03/23

Thu 9/03/23

0%

Stop & Sand walls and celings wet areas

398

Paint Ceilings to wet areas

8d

Fri 10/03/23

399

Sheet Plaster walls

20 d

Fri 24/02/23

400

Install timber perticle board

12 d

Fri 24/02/23

Tue 14/03/23 0%

401

Install grid framing

6d

Fri 10/03/23

Mon 20/03/23 0%

Wilson Lane Current Program 30.11.21

Wed 22/03/23 0% Fri 24/03/23

0%

Rough in wall space elec mech and Hydro Fire

Paint Ceilings to wet areas Sheet Plaster walls Install timber perticle board Install grid framing

Jul


WILSON LANE CURRENT CONSTRUCTION PROGRAMME 9.3.22 ID

Task Name

Dur

Start

402

Sheet ceiling

7d

Tue 21/03/23

403

Stop and sand walls

10 d

Fri 31/03/23

404

Light cut out and Mech&Fire Peno's

5d

Fri 31/03/23

405

Pre Paint (Base Coat)

5d

Mon 24/04/23

406

Defect plaster

3d

407

Final coats of Paint to walls and ceilings

408

Finish

% Comple

Thu 30/03/23 0%

1st Half Jan

1st Quarter Mar

May

1st Half Jul

3rd Quarter Sep

Nov

Jan

1st Quarter Mar Sheet ceiling

May

Jul

Fri 21/04/23

0%

Stop and sand walls

Thu 6/04/23

0%

Light cut out and Mech&Fire Peno's

Mon 1/05/23 0%

Pre Paint (Base Coat)

Fri 28/04/23

Tue 2/05/23

0%

Defect plaster

10 d

Mon 1/05/23

Fri 12/05/23

0%

Install AP

1d

Mon 15/05/23

Mon 15/05/23 0%

409

Fit Off elec and Plumbinng wet areas

8d

Tue 2/05/23

Thu 11/05/23 0%

410

ITP ITR DDA compliant install Sanitary hardware

0d

Thu 11/05/23

Thu 11/05/23 0%

411

Fit off sanitary Hardware and fixtures

3d

Fri 12/05/23

Tue 16/05/23 0%

Fit off sanitary Hardware and fixtures

412

Remaining Vinyl

5d

Wed 10/05/23

Tue 16/05/23 0%

Remaining Vinyl

413

Remaining Floor coverings and covings

6d

Wed 17/05/23

Wed 24/05/23 0%

414

Fit off Jambs

3d

Tue 23/05/23

Thu 25/05/23 0%

415

Install Joinery

3d

Wed 24/05/23

416

Hang doors and Hardware Arch and skirts

10 d

Wed 15/03/23

417

Paint Jams and Doors

7d

418

Fit off door Furniture

6d

419

Fit Off Mech elec Fire Hydro

10 d

Wed 24/05/23

420

Trims transitions and tactiles

4d

Thu 25/05/23

421 422

Builders Clean Caulk and defect Internal Rough in and fit off Level 3

Fri 26/05/23

Final coats of Paint to walls and ceilings Install AP Fit Off elec and Plumbinng wet areas 11/05/23

Remaining Floor coverings and covings Fit off Jambs Install Joinery

0%

Wed 29/03/23 0%

Hang doors and Hardware Arch and skirts

Thu 30/03/23

Mon 17/04/23 0%

Paint Jams and Doors

Tue 18/04/23

Wed 26/04/23 0%

4d

Thu 1/06/23

78 d

Thu 9/02/23

Tue 6/06/23

Fit off door Furniture Fit Off Mech elec Fire Hydro

0%

Trims transitions and tactiles

Tue 30/05/23 0% Tue 6/06/23

Builders Clean Caulk and defect

0%

Tue 13/06/23 0%

Internal Rough in and fit off Level 3 Rough in ceiling space elec mech and Hydro Fire

423

Rough in ceiling space elec mech and Hydro Fire

15 d

Thu 9/02/23

Thu 2/03/23

0%

424

Rough in wall space elec mech and Hydro Fire

10 d

Fri 24/02/23

Thu 9/03/23

0%

425

Sheet rooms Wet areas first Including ceiling

5d

Fri 10/03/23

Fri 17/03/23

0%

426

Stop & Sand walls and celings wet areas

6d

Mon 20/03/23

Tue 28/03/23 0%

427

Paint Ceilings to wet areas

8d

Wed 29/03/23

Mon 17/04/23 0%

428

Sheet Plaster walls

16 d

Mon 20/03/23

Wed 19/04/23 0%

429

Install timber perticle board

12 d

Mon 20/03/23

Wed 5/04/23 0%

430

Install grid framing

3d

Wed 29/03/23

431

Sheet ceiling

3d

Mon 17/04/23

Wed 19/04/23 0%

432

Stop and sand walls

5d

Thu 20/04/23

Thu 27/04/23 0%

433

Light cut out and Mech&Fire Peno's

3d

Thu 20/04/23

Mon 24/04/23 0%

434

Pre Paint (Base Coat)

5d

Fri 28/04/23

Thu 4/05/23

0%

435

Defect plaster

5d

Wed 3/05/23

Tue 9/05/23

0%

436

Final coats of Paint to walls and ceilings

10 d

Mon 8/05/23

Fri 19/05/23

0%

437

Install AP

1d

Mon 22/05/23

438

Fit Off elec and Plumbinng wet areas

3d

Fri 5/05/23

Tue 9/05/23

0%

439

ITP ITR DDA compliant install Sanitary hardware

0d

Tue 9/05/23

Tue 9/05/23

0%

440

Fit off sanitary Hardware and fixtures

3d

Wed 10/05/23

Fri 12/05/23

0%

Fit off sanitary Hardware and fixtures

441

Remaining Vinyl

5d

Mon 8/05/23

Fri 12/05/23

0%

Remaining Vinyl

442

Remaining Floor coverings and covings

6d

Mon 15/05/23

Mon 22/05/23 0%

443

Fit off Jambs

3d

Mon 22/05/23

Wed 24/05/23 0%

444

Install Joinery

3d

Wed 24/05/23

Fri 26/05/23

0%

445

Hang doors and Hardware Arch and skirts

10 d

Thu 6/04/23

Fri 28/04/23

0%

446

Paint Jams and Doors

7d

Mon 1/05/23

Tue 9/05/23

0%

447

Fit off door Furniture

6d

Wed 10/05/23

Wed 17/05/23 0%

448

Fit Off Mech elec Fire Hydro

14 d

Wed 24/05/23

Tue 13/06/23 0%

449

Trims transitions and tactiles

4d

Tue 23/05/23

450 451

Builders Clean Caulk and defect Internal Rough in and fit off Level 4

Fri 31/03/23

Rough in wall space elec mech and Hydro Fire Sheet rooms Wet areas first Including ceiling Stop & Sand walls and celings wet areas Paint Ceilings to wet areas Sheet Plaster walls Install timber perticle board Install grid framing

0%

Sheet ceiling Stop and sand walls Light cut out and Mech&Fire Peno's Pre Paint (Base Coat) Defect plaster Final coats of Paint to walls and ceilings Install AP

Mon 22/05/23 0%

Fri 26/05/23

Fit Off elec and Plumbinng wet areas 9/05/23

Remaining Floor coverings and covings Fit off Jambs Install Joinery Hang doors and Hardware Arch and skirts Paint Jams and Doors Fit off door Furniture Fit Off Mech elec Fire Hydro Trims transitions and tactiles

0%

6d

Mon 5/06/23

Tue 13/06/23 0%

81 d

Tue 31/01/23

Wed 7/06/23 0%

Builders Clean Caulk and defect Internal Rough in and fit off Level 4 Rough in ceiling space elec mech and Hydro Fire

452

Rough in ceiling space elec mech and Hydro Fire

15 d

Tue 31/01/23

Wed 22/02/23 0%

453

Rough in wall space elec mech and Hydro Fire

10 d

Wed 15/02/23

Wed 1/03/23 0%

454

Sheet rooms Wet areas first Including ceiling

8d

Thu 2/03/23

Tue 14/03/23 0%

455

Stop & Sand walls and celings wet areas

6d

Wed 15/03/23

Wed 22/03/23 0%

456

Paint Ceilings to wet areas

8d

Thu 23/03/23

Tue 4/04/23

457

Sheet Plaster walls

20 d

Tue 7/03/23

Wed 5/04/23 0%

458

Install timber perticle board

12 d

Tue 7/03/23

Thu 23/03/23 0%

459

Install grid framing

6d

Thu 23/03/23

460

Sheet ceiling

3d

Mon 3/04/23

Wed 5/04/23 0%

461

Stop and sand walls

5d

Thu 6/04/23

Thu 20/04/23 0%

462

Light cut out and Mech&Fire Peno's

3d

Thu 6/04/23

Tue 18/04/23 0%

463

Pre Paint (Base Coat)

5d

Fri 21/04/23

464

Defect plaster

5d

Thu 27/04/23

Wed 3/05/23 0%

465

Final coats of Paint to walls and ceilings

10 d

Tue 2/05/23

Mon 15/05/23 0%

466

Install AP

1d

Tue 16/05/23

Tue 16/05/23 0%

467

Fit Off elec and Plumbinng wet areas

3d

Mon 1/05/23

Wed 3/05/23 0%

468

ITP ITR DDA compliant install Sanitary hardware

0d

Wed 3/05/23

Wed 3/05/23 0%

469

Fit off sanitary Hardware and fixtures

3d

Thu 4/05/23

Mon 8/05/23 0%

Fit off sanitary Hardware and fixtures

470

Remaining Vinyl

5d

Tue 2/05/23

Mon 8/05/23 0%

Remaining Vinyl

471

Remaining Floor coverings and covings

6d

Tue 9/05/23

Tue 16/05/23 0%

472

Fit off Jambs

3d

Tue 16/05/23

Thu 18/05/23 0%

473

Install Joinery

3d

Thu 18/05/23

Mon 22/05/23 0%

474

Hang doors and Hardware Arch and skirts

10 d

Fri 24/03/23

Mon 17/04/23 0%

475

Paint Jams and Doors

7d

Tue 18/04/23

Thu 27/04/23 0%

476

Fit off door Furniture

6d

Fri 28/04/23

477

Fit Off Mech elec Fire Hydro

15 d

Thu 18/05/23

Wed 7/06/23 0%

478

Trims transitions and tactiles

4d

Wed 17/05/23

Mon 22/05/23 0%

479 480

Builders Clean Caulk and defect Sevices & Final Commissioning

Fri 31/03/23

Fri 28/04/23

Fri 5/05/23

0%

0%

Rough in wall space elec mech and Hydro Fire Sheet rooms Wet areas first Including ceiling Stop & Sand walls and celings wet areas Paint Ceilings to wet areas Sheet Plaster walls Install timber perticle board Install grid framing Sheet ceiling Stop and sand walls Light cut out and Mech&Fire Peno's Pre Paint (Base Coat)

0%

Defect plaster Final coats of Paint to walls and ceilings Install AP Fit Off elec and Plumbinng wet areas 3/05/23

Remaining Floor coverings and covings Fit off Jambs Install Joinery Hang doors and Hardware Arch and skirts Paint Jams and Doors Fit off door Furniture

0%

4d

Fri 2/06/23

Wed 7/06/23 0%

38 d

Wed 19/04/23

Tue 13/06/23 0% Wed 24/05/23 0%

Fit Off Mech elec Fire Hydro Trims transitions and tactiles Builders Clean Caulk and defect Sevices & Final Commissioning Install Main and Distribution Boards

481

Install Main and Distribution Boards

25 d

Wed 19/04/23

482

Install Mechanical Switch boards

22 d

Wed 19/04/23

483

Install water meters

2d

Mon 22/05/23

Tue 23/05/23 0%

484

Commissioning of fire services

5d

Wed 24/05/23

Tue 30/05/23 0%

485

Installation of FIP

4d

Wed 31/05/23

Mon 5/06/23 0%

486

receive 309

0d

Mon 5/06/23

Mon 5/06/23 0%

5/06/23

487

Receive occupancy

0d

Mon 5/06/23

Mon 5/06/23 0%

5/06/23

488

Practical Completion

0d

Tue 13/06/23

Tue 13/06/23 0%

Wilson Lane Current Program 30.11.21

Fri 19/05/23

0%

Install Mechanical Switch boards Install water meters Commissioning of fire services Installation of FIP

13/06/23


Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.