WILSON LANE CURRENT CONSTRUCTION PROGRAMME 9.3.22 ID
1
Task Name
Dur
Wills Street
2
Tender Submission and review
3
Receive tender doc's
7
Off site works
11
Stage 1 Subcontract letting
17
Construction
18
Stage 1 Building Permit Structure Basement
Start
Finish
% Comple
1307 d
Fri 30/06/17
Tue 13/06/23 32%
20 d
Fri 30/06/17
Mon 31/07/17 100%
35 d
Fri 30/06/17
Wed 23/08/17 100%
166 d
Thu 24/08/17
Fri 25/05/18
10 d
Thu 31/08/17
Thu 14/09/17 100%
1111 d
Mon 21/05/18
Tue 13/06/23 27%
849 d
Mon 21/05/18
Fri 25/03/22
8d
Mon 21/05/18
24
Civil/Excavation Works
12 d
Wed 30/05/18
Fri 15/06/18
100%
29
Concrete/Bored Piers Capping beam
37 d
Mon 18/06/18
Tue 7/08/18
100%
38
Bulk and detailed excavation Top Half
8d
Wed 8/08/18
Fri 17/08/18
100%
41
Shotcrete Grid Top Half
8d
Mon 20/08/18
46
Sewer
44 d
Thu 12/07/18
Tue 11/09/18 100%
52
Bulk and detailed excavation Bottom Half
10 d
Thu 30/08/18
Wed 12/09/18 100%
55
Shotcrete Grid 5 Bottom Half
8d
Thu 13/09/18
Mon 24/09/18 100%
60
Lift pit & Shaft
14 d
Thu 13/09/18
Tue 2/10/18
100%
66
Structure Basement
759 d
Tue 25/09/18
Fri 25/03/22
96% 100%
Wed 30/05/18 100%
Wed 29/08/18 100%
67
Install stormwater pits pumps and Grates to Basement
8d
Tue 25/09/18
Thu 4/10/18
68
Detailed excavation of Pad footings
3d
Tue 25/09/18
Thu 27/09/18 100%
69
FRP Pad Footings
8d
Thu 27/09/18
Mon 8/10/18 100%
70
Structural Engineer Inspection
0d
Mon 8/10/18
Mon 8/10/18 100%
71
Install sand fabric & Mesh
10 d
Tue 9/10/18
Mon 22/10/18 100%
72
Structural Engineer Inspection
0d
Mon 22/10/18
Mon 22/10/18 100%
73
Pour slab
2d
Tue 23/10/18
Wed 24/10/18 100%
74
Slab Cure Time
3d
Thu 25/10/18
Mon 29/10/18 100%
75
Christmas Shutdown Delay
40 d
Tue 30/10/18
Wed 16/01/19 100%
76
Install PCP Retention System
Mon 21/01/19 100%
77
Delay until receipt of executed contract
78 79
Second Stage of Project
272 d
Thu 10/03/22
Fri 25/03/22
Delay until receipt of executed contract
95%
Tue 13/06/23 0%
Second Stage of Project Second Stage - Critical Documents
10 d
Thu 10/03/22
Fri 25/03/22
0%
80
Receipt of Building Permit and Town Planning Requirements (By others)
10 d
Thu 10/03/22
Fri 25/03/22
0%
Receipt of Building Permit and Town Planning Requirements (By others)
81
Confirm "For Construction" Docs
10 d
Thu 10/03/22
Fri 25/03/22
0%
Confirm "For Construction" Docs
82
Confirm Concrete Outline Plan
5d
Mon 21/03/22
Fri 25/03/22
0%
83
Final Construction Design - FROZEN
0d
Fri 25/03/22
Fri 25/03/22
0%
84
Second Stage - Critical Documents
Thu 17/01/19 Tue 22/01/19
Stage 2 Subcontract letting
Confirm Concrete Outline Plan 25/03/22 Stage 2 Subcontract letting
85 d
Tue 29/03/22
Mon 15/08/22 0%
85
Issue construction doc's to Precast Concrete Trade
2d
Tue 29/03/22
Wed 30/03/22 0%
86
Review and let Precast Concrete package
2d
Thu 31/03/22
Fri 1/04/22
0%
Review and let Precast Concrete package
87
Issue construction doc's to Structure trades
4d
Tue 29/03/22
Fri 1/04/22
0%
Issue construction doc's to Structure trades
88
Issue construction doc's to Services trades
4d
Mon 4/04/22
Thu 7/04/22
0%
89
Review and let Concrete package
3d
Mon 4/04/22
Wed 6/04/22 0%
90
Review and let Elec, Mech, Sprinklers & Hyd
3d
Thu 7/04/22
Mon 11/04/22 0%
91
Review and let Structural Steel package
10 d
Tue 12/04/22
Wed 4/05/22 0%
Review and let Structural Steel package
92
Issue construction doc's to Front Fascade
10 d
Fri 8/04/22
Mon 2/05/22 0%
Issue construction doc's to Front Fascade
93
Issue construction doc's to Remaining Trades
20 d
Tue 3/05/22
Wed 1/06/22 0%
94
Review and let Front Fascade package
10 d
Tue 3/05/22
Tue 17/05/22 0%
95
Review and let Remaining Trades
40 d
Wed 18/05/22
Tue 19/07/22 0%
96
Shop Drawings
81 d
Mon 4/04/22
Mon 15/08/22 0%
Issue construction doc's to Precast Concrete Trade
Issue construction doc's to Services trades Review and let Concrete package Review and let Elec, Mech, Sprinklers & Hyd
Issue construction doc's to Remaining Trades Review and let Front Fascade package Review and let Remaining Trades Shop Drawings
97
Precast Concrete
77 d
Mon 4/04/22
Tue 9/08/22
0%
Precast Concrete
98
Ground Floor
35 d
Mon 4/04/22
Thu 2/06/22
0%
Ground Floor
Tue 3/05/22
0%
99
Submit Precast Concrete Shop DWG's for approval
15 d
Mon 4/04/22
100
Consultants & Architects Review
5d
Wed 4/05/22
101
Fabricate Precast Concrete
15 d
Thu 12/05/22
25 d
Mon 30/05/22
102
1st Floor
Thu 2/06/22
10 d
Mon 30/05/22
Consultants & Architects Review
5d
Wed 15/06/22
Tue 21/06/22 0%
105
Fabricate Precast Concrete
10 d
Wed 22/06/22
Wed 6/07/22 0%
22 d
Wed 15/06/22
Mon 18/07/22 0% Thu 23/06/22 0%
Fri 10/06/22
Submit Precast Concrete Shop DWG's for approval
7d
Wed 15/06/22
108
Consultants & Architects Review
5d
Fri 24/06/22
109
Fabricate Precast Concrete
10 d
Mon 4/07/22
Mon 18/07/22 0%
22 d
Fri 24/06/22
Thu 28/07/22 0%
Fri 1/07/22
Submit Precast Concrete Shop DWG's for approval
7d
Fri 24/06/22
112
Consultants & Architects Review
5d
Wed 6/07/22
Wed 13/07/22 0%
113
Fabricate Precast Concrete
10 d
Thu 14/07/22
Thu 28/07/22 0%
22 d
Wed 6/07/22
Tue 9/08/22
0%
114
4th Floor & Roof
Consultants & Architects Review Fabricate Precast Concrete 2nd Floor Submit Precast Concrete Shop DWG's for approval Consultants & Architects Review
0%
111
Tue 5/07/22
Submit Precast Concrete Shop DWG's for approval
0%
107
3rd Floor
Fabricate Precast Concrete 1st Floor
Wed 6/07/22 0%
Submit Precast Concrete Shop DWG's for approval
110
Consultants & Architects Review
0%
104
2nd Floor
Submit Precast Concrete Shop DWG's for approval
Wed 11/05/22 0%
103
106
Fabricate Precast Concrete 3rd Floor Submit Precast Concrete Shop DWG's for approval
0%
Consultants & Architects Review Fabricate Precast Concrete 4th Floor & Roof Submit Precast Concrete Shop DWG's for approval
115
Submit Precast Concrete Shop DWG's for approval
7d
Wed 6/07/22
Fri 15/07/22
0%
116
Consultants & Architects Review
5d
Mon 18/07/22
Fri 22/07/22
0%
117
Fabricate Precast Concrete
10 d
Tue 26/07/22
Tue 9/08/22
0%
70 d
Mon 4/04/22
Thu 28/07/22 0%
Concrete Post Tension & Structural Design Ground Floor
118 119
Concrete Post Tension & Structural Design
30 d
Mon 4/04/22
Thu 26/05/22 0%
120
Submit PT & Concrete Shop DWG's for approval
15 d
Mon 4/04/22
Tue 3/05/22
121
Consultants & Architects Review
5d
Wed 4/05/22
Wed 11/05/22 0%
122
Procure PT Components
10 d
Thu 12/05/22
Thu 26/05/22 0%
25 d
Wed 4/05/22
Thu 9/06/22
123
Ground Floor
1st Floor
0%
Submit PT & Concrete Shop DWG's for approval
10 d
Wed 4/05/22
Wed 18/05/22 0%
125
Consultants & Architects Review
5d
Thu 19/05/22
Thu 26/05/22 0%
126
Procure PT Components
10 d
Fri 27/05/22
25 d
Thu 19/05/22
2nd Floor
Thu 9/06/22
Tue 28/06/22 0%
Submit PT & Concrete Shop DWG's for approval
10 d
Thu 19/05/22
Thu 2/06/22
0%
129
Consultants & Architects Review
5d
Fri 3/06/22
Thu 9/06/22
0%
130
Procure PT Components
10 d
Fri 10/06/22
Tue 28/06/22 0%
25 d
Fri 3/06/22
Wed 13/07/22 0%
3rd Floor
132
Submit PT & Concrete Shop DWG's for approval
10 d
Fri 3/06/22
Mon 20/06/22 0%
133
Consultants & Architects Review
5d
Tue 21/06/22
Tue 28/06/22 0%
134
Procure PT Components
10 d
Wed 29/06/22
Wed 13/07/22 0%
25 d
Tue 21/06/22
Thu 28/07/22 0%
135
4th Floor
136
Submit PT & Concrete Shop DWG's for approval
10 d
Tue 21/06/22
137
Consultants & Architects Review
5d
Wed 6/07/22
Wilson Lane Current Program 30.11.21
Tue 5/07/22
Fabricate Precast Concrete
Submit PT & Concrete Shop DWG's for approval Consultants & Architects Review Procure PT Components 1st Floor Submit PT & Concrete Shop DWG's for approval Consultants & Architects Review Procure PT Components
0%
128
131
Consultants & Architects Review
0%
124
127
3rd Quarter Sep
Jul
96%
Site set up
3d
1st Half
May
100%
19
691 d
1st Half 1st Quarter Mar
Jan
0%
Wed 13/07/22 0%
2nd Floor Submit PT & Concrete Shop DWG's for approval Consultants & Architects Review Procure PT Components 3rd Floor Submit PT & Concrete Shop DWG's for approval Consultants & Architects Review Procure PT Components 4th Floor Submit PT & Concrete Shop DWG's for approval Consultants & Architects Review
Nov
Jan
1st Quarter Mar
May
Jul
WILSON LANE CURRENT CONSTRUCTION PROGRAMME 9.3.22 ID
138 139 140
Task Name
Dur
Procure PT Components Services & Concrete Temporary Propping Design Basement, Ground Floor
Start
10 d
Thu 14/07/22
30 d
Tue 12/04/22
Finish
% Comple
Thu 28/07/22 0% Fri 3/06/22
1st Half Jan
1st Quarter Mar
0%
Services & Concrete Temporary Propping Design Basement, Ground Floor
15 d
Tue 12/04/22
Thu 12/05/22 0%
141
Submit Services Shop DWG's for approval
10 d
Tue 12/04/22
Wed 4/05/22 0%
142
Consultants & Architects Review
5d
Thu 5/05/22
Thu 12/05/22 0%
143
1st Floor, 2nd Floor, 3rd Floor, 4th Floor
20 d
Thu 5/05/22
Fri 3/06/22
0%
Consultants & Architects Review Submit Services Shop DWG's for approval
Submit Services Shop DWG's for approval
15 d
Thu 5/05/22
Fri 27/05/22
0%
Consultants & Architects Review
5d
Mon 30/05/22
Fri 3/06/22
0%
65 d
Thu 5/05/22
Mon 15/08/22 0%
Structural Steel
Wed 6/07/22 0%
1st Floor, 2nd Floor, 3rd Floor, 4th Floor
147
40 d
Thu 5/05/22
148
Submit Steel Shop DWG's for approval
20 d
Thu 5/05/22
Fri 3/06/22
0%
149
Consultants & Architects Review
5d
Mon 6/06/22
Fri 10/06/22
0%
150
Fabricate Steel
15 d
Wed 15/06/22
Wed 6/07/22 0%
45 d
Mon 6/06/22
Mon 15/08/22 0%
151
1st Floor, 2nd Floor, 3rd Floor, 4th Floor
Roof
Consultants & Architects Review
Submit Steel Shop DWG's for approval Consultants & Architects Review Fabricate Steel Roof Submit Steel Shop DWG's for approval
152
Submit Steel Shop DWG's for approval
15 d
Mon 6/06/22
Wed 29/06/22 0%
153
Consultants & Architects Review
5d
Thu 30/06/22
Wed 6/07/22 0%
154
Fabricate Roof Steel
25 d
Thu 7/07/22
Mon 15/08/22 0%
50 d
Wed 18/05/22
Wed 3/08/22 0%
Fascade
Wed 3/08/22 0%
1st Floor, 2nd Floor, 3rd Floor, 4th Floor
155 156
Fascade
Consultants & Architects Review Fabricate Roof Steel
50 d
Wed 18/05/22
157
Submit Fascade Shop DWG's for approval
20 d
Wed 18/05/22
Fri 17/06/22
0%
158
Consultants & Architects Review
5d
Mon 20/06/22
Fri 24/06/22
0%
159
Fabricate Fascade
25 d
Tue 28/06/22
Wed 3/08/22 0%
253 d
Mon 11/04/22
Tue 13/06/23 0%
Stage 2 Building Permit Works Structure Ground Floor
160
1st Floor, 2nd Floor, 3rd Floor, 4th Floor
Stage 2 Building Permit Works
Submit Fascade Shop DWG's for approval Consultants & Architects Review Fabricate Fascade
161
Structure Ground Floor
49 d
Mon 11/04/22
Mon 4/07/22 0%
162
Re-Mobilise to Site
4d
Mon 11/04/22
Thu 14/04/22 0%
163
Install Masonry to Basement
7d
Tue 26/04/22
Wed 4/05/22 0%
164
Shotcrete to side of Ramp
3d
Thu 5/05/22
Tue 10/05/22 0%
165
Form, Reo + Pour In-Situ Wall in Basement
7d
Wed 11/05/22
Thu 19/05/22 0%
166
Complete Precast Works
3d
Thu 5/05/22
Tue 10/05/22 0%
167
Install Frames and ply
12 d
Thu 19/05/22
Mon 6/06/22 0%
Install Frames and ply
168
Install all services including fire collars
5d
Wed 1/06/22
Tue 7/06/22
0%
Install all services including fire collars
169
Install reo to deck
5d
Wed 1/06/22
Tue 7/06/22
0%
170
Install pt to deck
2d
Thu 2/06/22
Fri 3/06/22
0%
171
Install edge form
5d
Tue 7/06/22
Wed 15/06/22 0%
172
Hold point review all heights & grades
0d
Wed 15/06/22
Wed 15/06/22 0%
15/06/22
173
Engineers Inspection
0d
Wed 15/06/22
Wed 15/06/22 0%
15/06/22
174
Pour 1st half slab
1d
Thu 16/06/22
Thu 16/06/22 0%
Pour 1st half slab
175
Install reo to deck
5d
Wed 8/06/22
Thu 16/06/22 0%
Install reo to deck
176
Install pt to deck
2d
Thu 16/06/22
177
Install edge form
3d
Thu 16/06/22
Mon 20/06/22 0%
178
Hold point review all heights & grades
0d
Mon 20/06/22
Mon 20/06/22 0%
20/06/22
179
Engineers Inspection
0d
Mon 20/06/22
Mon 20/06/22 0%
20/06/22
180
Pour 2nd half slab
1d
Tue 21/06/22
Tue 21/06/22 0%
181
FRP Columns
3d
Wed 22/06/22
Fri 24/06/22
0%
FRP Columns
182
Cure Ground Slab
3d
Wed 22/06/22
Fri 24/06/22
0%
Cure Ground Slab
183
Install Precast On Ground Floor + PC19
5d
Tue 28/06/22
Mon 4/07/22 0%
26 d
Thu 30/06/22
Tue 9/08/22
184
Structure First Floor
Fri 17/06/22
185
Install Frames and ply
10 d
Thu 30/06/22
Thu 14/07/22 0%
186
Install edge form & handrail
3d
Fri 15/07/22
Tue 19/07/22 0%
187
Install all services including fire collars
3d
Wed 13/07/22
188
Install reo to deck
5d
Wed 13/07/22
Tue 19/07/22 0%
189
Install pt to deck
2d
Tue 19/07/22
Wed 20/07/22 0%
190
Engineers Inspection
0d
Wed 20/07/22
Wed 20/07/22 0%
191
Pour 1st half slab
1d
Thu 21/07/22
Thu 21/07/22 0%
192
Install edge form & handrail
3d
Wed 20/07/22
193
Install all services including fire collars
3d
Mon 18/07/22
Wed 20/07/22 0%
194
Install reo to deck
5d
Thu 21/07/22
Thu 28/07/22 0%
195
Install pt to deck
2d
Thu 28/07/22
Fri 29/07/22
0%
196
Engineers Inspection
0d
Fri 29/07/22
Fri 29/07/22
0%
197
Pour 2nd half slab
1d
Mon 1/08/22
198
FRP Columns
4d
Tue 2/08/22
Fri 5/08/22
0%
199
Install Precast On 1st Floor + PC23
3d
Thu 4/08/22
Tue 9/08/22
0%
25 d
Fri 5/08/22
200
Structure Second Floor Apartments
Fri 15/07/22
Fri 22/07/22
Install Masonry to Basement Shotcrete to side of Ramp Form, Reo + Pour In-Situ Wall in Basement Complete Precast Works
Install reo to deck Install pt to deck Install edge form
Install pt to deck Install edge form
Pour 2nd half slab
Install Precast On Ground Floor + PC19 Structure First Floor Install Frames and ply Install edge form & handrail Install all services including fire collars
0%
0%
Install reo to deck Install pt to deck 20/07/22 Pour 1st half slab Install edge form & handrail Install all services including fire collars Install reo to deck Install pt to deck 29/07/22 Pour 2nd half slab
Mon 1/08/22 0%
Tue 13/09/22 0%
201
Install Frames and ply
10 d
Fri 5/08/22
202
Install edge form & handrail
3d
Tue 23/08/22
Thu 25/08/22 0%
203
Install all services including fire collars
3d
Thu 18/08/22
Tue 23/08/22 0%
204
Install reo to deck
5d
Thu 18/08/22
Thu 25/08/22 0%
205
Install pt to deck
2d
Thu 25/08/22
Fri 26/08/22
0%
206
Engineers Inspection
0d
Fri 26/08/22
Fri 26/08/22
0%
207
Pour 1st half slab
1d
Mon 29/08/22
Mon 29/08/22 0%
208
Install edge form & handrail
3d
Fri 26/08/22
Tue 30/08/22 0%
209
Install all services including fire collars
3d
Wed 24/08/22
210
Install reo to deck
5d
Mon 29/08/22
211
Install pt to deck
2d
Fri 2/09/22
Mon 5/09/22 0%
212
Engineers Inspection
0d
Mon 5/09/22
Mon 5/09/22 0%
213
Pour 2nd half slab
1d
Tue 6/09/22
Tue 6/09/22
214
FRP Columns
4d
Wed 7/09/22
Tue 13/09/22 0%
215
Install Precast On 2nd Floor
2d
Fri 9/09/22
Tue 13/09/22 0%
216
Structure Third Floor Apartments
24 d
Thu 8/09/22
Mon 17/10/22 0%
Fri 19/08/22
0%
Fri 26/08/22
0%
Fri 2/09/22
0%
Install Frames and ply
9d
Thu 8/09/22
Wed 21/09/22 0%
218
Install edge form & handrail
3d
Thu 22/09/22
Wed 28/09/22 0%
219
Install all services including fire collars
3d
Tue 20/09/22
Thu 22/09/22 0%
220
Install reo to deck
5d
Tue 20/09/22
Wed 28/09/22 0%
221
Install pt to deck
2d
Wed 28/09/22
Thu 29/09/22 0%
222
Engineers Inspection
0d
Thu 29/09/22
Thu 29/09/22 0%
223
Pour 1st half slab
1d
Fri 30/09/22
224
Install edge form & handrail
3d
Thu 29/09/22
Mon 3/10/22 0%
225
Install all services including fire collars
3d
Tue 27/09/22
Thu 29/09/22 0%
Fri 30/09/22
FRP Columns Install Precast On 1st Floor + PC23 Structure Second Floor Apartments Install Frames and ply Install edge form & handrail Install all services including fire collars Install reo to deck Install pt to deck 26/08/22 Pour 1st half slab Install edge form & handrail Install all services including fire collars Install reo to deck Install pt to deck 5/09/22 Pour 2nd half slab
0%
217
Wilson Lane Current Program 30.11.21
Re-Mobilise to Site
0%
0%
0%
Nov
1st Floor, 2nd Floor, 3rd Floor, 4th Floor
145
Structural Steel
3rd Quarter Sep
Jul Procure PT Components
Submit Services Shop DWG's for approval
144 146
1st Half
May
FRP Columns Install Precast On 2nd Floor Structure Third Floor Apartments Install Frames and ply Install edge form & handrail Install all services including fire collars Install reo to deck Install pt to deck 29/09/22 Pour 1st half slab Install edge form & handrail Install all services including fire collars
Jan
1st Quarter Mar
May
Jul
WILSON LANE CURRENT CONSTRUCTION PROGRAMME 9.3.22 ID
Task Name
Dur
Start
Finish
% Comple
226
Install reo to deck
5d
Fri 30/09/22
Thu 6/10/22
0%
227
Install pt to deck
2d
Thu 6/10/22
Fri 7/10/22
0%
228
Engineers Inspection
0d
Fri 7/10/22
Fri 7/10/22
0%
229
Pour 2nd half slab
1d
Tue 11/10/22
Tue 11/10/22 0%
230
FRP Columns
4d
Wed 12/10/22
Mon 17/10/22 0%
231
Install Precast On 3rd Floor
2d
Fri 14/10/22
Mon 17/10/22 0%
19 d
Fri 14/10/22
Mon 14/11/22 0% Tue 25/10/22 0%
232
Structure Fourth Floor Apartments
233
Install Frames and ply
8d
Fri 14/10/22
234
Install edge form & handrail
3d
Wed 26/10/22
235
Install all services including fire collars
3d
Mon 24/10/22
236
Install reo to deck
5d
Mon 24/10/22
Fri 28/10/22
0%
237
Install pt to deck
2d
Fri 28/10/22
Thu 3/11/22
0%
238
Engineers Inspection
0d
Thu 3/11/22
Thu 3/11/22
0%
239
Pour 1st half slab
1d
Fri 4/11/22
Fri 4/11/22
0%
240
Install edge form & handrail
3d
Thu 3/11/22
Mon 7/11/22 0%
241
Install all services including fire collars
3d
Thu 27/10/22
Thu 3/11/22
242
Install reo to deck
5d
Fri 4/11/22
243
Install pt to deck
2d
Thu 10/11/22
Fri 11/11/22
0%
244
Engineers Inspection
0d
Fri 11/11/22
Fri 11/11/22
0%
1d
Mon 14/11/22
Mon 14/11/22 0%
19 d
Tue 15/11/22
Mon 12/12/22 0%
245 246
Pour 2nd half slab Structure Roof
Fri 28/10/22
1st Quarter Mar
May
1st Half 3rd Quarter Sep Install reo to deck
Jul
FRP Columns Install Precast On 3rd Floor Structure Fourth Floor Apartments Install Frames and ply Install edge form & handrail Install all services including fire collars Install reo to deck Install pt to deck 3/11/22 Pour 1st half slab Install edge form & handrail Install all services including fire collars Install reo to deck
Thu 10/11/22 0%
1d
Tue 15/11/22
Tue 15/11/22 0%
Install Columns
5d
Wed 16/11/22
Tue 22/11/22 0%
249
Install Structural Steel
7d
Wed 23/11/22
Thu 1/12/22
250
Install Purlins to roof
6d
Fri 2/12/22
Mon 12/12/22 0%
251
Structural Engineer Inspection
0d
Mon 12/12/22
Mon 12/12/22 0% Thu 15/12/22 0%
Install pt to deck 11/11/22 Pour 2nd half slab Structure Roof Land surveyor column locations Install Columns Install Structural Steel
0%
Install Purlins to roof 12/12/22 Strip form work
102 d
Fri 8/07/22
253
Strip Basement Floor & back Prop
0d
Fri 8/07/22
254
Remove Basement Floor props
0d
Tue 27/09/22
Tue 27/09/22 0%
255
Strip Ground Floor & back prop
0d
Thu 18/08/22
Thu 18/08/22 0%
256
Remove Ground Floor props
0d
Thu 27/10/22
Thu 27/10/22 0%
257
Strip First Floor and back prop
0d
Tue 27/09/22
Tue 27/09/22 0%
258
Remove First Floor props
0d
Wed 30/11/22
Wed 30/11/22 0%
259
Strip Second floor & back Prop
0d
Thu 27/10/22
Thu 27/10/22 0%
260
Strip Third floor & back Prop
0d
Wed 30/11/22
Wed 30/11/22 0%
30/11/22
261
Fully tension grout all peno
0d
Wed 30/11/22
Wed 30/11/22 0%
30/11/22
262
Remove Props Second Floors
0d
Wed 30/11/22
Wed 30/11/22 0%
30/11/22
263
Remove Props Third Floor
0d
Thu 15/12/22
Thu 15/12/22 0%
29 d
Fri 9/12/22
Tue 14/02/23 0%
252
264
Roofing
Fri 8/07/22
0%
265
Install Handrail and access towers to roof
5d
Fri 9/12/22
Thu 15/12/22 0%
266
Pull wire to roof
3d
Fri 16/12/22
Tue 20/12/22 0%
267
Install Insulation & Roof sheeting
6d
Thu 12/01/23
Thu 19/01/23 0%
268
Install flashing Trims Gutters and DP's
3d
Fri 20/01/23
Tue 24/01/23 0%
269
Install Plant structure
10 d
Fri 20/01/23
Tue 7/02/23
270
Install Plant to roof area
5d
Wed 8/02/23
Tue 14/02/23 0%
137 d
Wed 28/09/22
Wed 24/05/23 0%
271
External Fascades
May
Pour 2nd half slab
0%
Land surveyor column locations
1st Quarter Mar
Jan
7/10/22
Wed 26/10/22 0%
248
Nov
Install pt to deck
0%
247
Strip form work
1st Half Jan
8/07/22 27/09/22 18/08/22 27/10/22 27/09/22 30/11/22 27/10/22
15/12/22 Roofing Install Handrail and access towers to roof Pull wire to roof Install Insulation & Roof sheeting Install flashing Trims Gutters and DP's Install Plant structure
0%
Install Plant to roof area External Fascades Install Steel Sub-Framing West Canopy
272
Install Steel Sub-Framing West Canopy
10 d
Wed 28/09/22
Wed 12/10/22 0%
273
Install Roofing Components for West canopy
15 d
Thu 13/10/22
Mon 7/11/22 0%
274
Install Steel Sub-Framing for Balconies
15 d
Thu 1/12/22
275
Stormwater Rough-In
10 d
Thu 1/12/22
Thu 15/12/22 0%
276
Install Balustrade Cladding
20 d
Fri 16/12/22
Wed 8/02/23 0%
277
Install Waterproofing on Balconies
15 d
Wed 1/02/23
Thu 23/02/23 0%
Install Waterproofing on Balconies
278
Install Timber Strapping
15 d
Wed 1/02/23
Thu 23/02/23 0%
Install Timber Strapping
279
Install Remainging Metal Cladding
20 d
Thu 9/02/23
Thu 9/03/23
0%
280
Install Metal Balustrades
20 d
Fri 24/02/23
Fri 24/03/23
0%
281
Install/Paint Misc Soffits on Balconies
10 d
Tue 28/03/23
Tue 18/04/23 0%
282
Install Tiling on Balconies
25 d
Wed 19/04/23
Wed 24/05/23 0%
142 d
Wed 28/09/22
Wed 31/05/23 0%
283 284
External Framing and Rough in
57 d
Wed 28/09/22
Install kingspan to soffit
10 d
Thu 1/12/22
Thu 15/12/22 0%
286
Rough in mech to ceiling
10 d
Wed 28/09/22
Wed 12/10/22 0%
287
Rough in sprinkler to ceiling
10 d
Wed 5/10/22
Wed 19/10/22 0%
288
Rough in Hydro &Elec
10 d
Thu 13/10/22
Wed 26/10/22 0%
289
Install external wall framing & finishes
15 d
Thu 1/12/22
59 d
Fri 28/10/22
Light weight Frames and cladding Ground Floor
Fri 13/01/23
Fri 13/01/23
Install Roofing Components for West canopy Install Steel Sub-Framing for Balconies
0%
285
290
Light weight Frames and cladding Basement
Fri 13/01/23
0%
Stormwater Rough-In Install Balustrade Cladding
Install Remainging Metal Cladding Install Metal Balustrades Install/Paint Misc Soffits on Balconies Install Tiling on Balconies External Framing and Rough in Light weight Frames and cladding Basement Install kingspan to soffit Rough in mech to ceiling Rough in sprinkler to ceiling Rough in Hydro &Elec Install external wall framing & finishes
0%
Tue 21/02/23 0%
Light weight Frames and cladding Ground Floor Install Internal external wall framing
291
Install Internal external wall framing
12 d
Fri 28/10/22
Thu 17/11/22 0%
292
Install Alluminium windows frames
13 d
Fri 18/11/22
Wed 7/12/22 0%
Install Alluminium windows frames
293
Install Glass Blocks
5d
Wed 30/11/22
Wed 7/12/22 0%
Install Glass Blocks
294
Install glazing
10 d
Thu 8/12/22
Thu 12/01/23 0%
295
Install substrate for Tiling
8d
Thu 8/12/22
Mon 19/12/22 0%
296
Install Tiling
8d
Thu 12/01/23
Mon 23/01/23 0%
Install Tiling
297
Install Misc cladding
8d
Thu 12/01/23
Mon 23/01/23 0%
Install Misc cladding
298
Install remaiming soffits
10 d
Tue 24/01/23
299
Paint Caulk and defect
7d
Fri 10/02/23
Tue 21/02/23 0%
55 d
Thu 1/12/22
Fri 17/03/23
Thu 15/12/22 0%
300
Light weight Frames and cladding First Floor
Thu 9/02/23
0%
Install Internal external wall framing
10 d
Thu 1/12/22
302
Install Alluminium windows frames
10 d
Fri 16/12/22
Fri 20/01/23
0%
303
Install Glass Blocks
5d
Fri 16/12/22
Fri 13/01/23
0%
304
Install glazing
10 d
Mon 23/01/23
Wed 8/02/23 0%
305
Install battening system for metal cladding
13 d
Thu 9/02/23
Tue 28/02/23 0%
306
Install Metal Cladding
8d
Tue 21/02/23
Thu 2/03/23
307
Install Misc cladding
6d
Tue 21/02/23
Tue 28/02/23 0%
308
Install remaiming soffits
5d
Fri 3/03/23
Thu 9/03/23
0%
309
Paint Caulk and defect
5d
Fri 10/03/23
Fri 17/03/23
0%
61 d
Fri 16/12/22
Wed 19/04/23 0% Tue 31/01/23 0%
Light weight Frames and cladding Second Floor
311
Install external wall framing
15 d
Fri 16/12/22
312
Install Alluminium windows frames
7d
Wed 1/02/23
313
Install glazing
10 d
Mon 13/02/23
Wilson Lane Current Program 30.11.21
Fri 10/02/23
Install remaiming soffits
0%
301
310
Install glazing Install substrate for Tiling
Paint Caulk and defect Light weight Frames and cladding First Floor Install Internal external wall framing Install Alluminium windows frames Install Glass Blocks Install glazing Install battening system for metal cladding Install Metal Cladding
0%
0%
Mon 27/02/23 0%
Install Misc cladding Install remaiming soffits Paint Caulk and defect Light weight Frames and cladding Second Floor Install external wall framing Install Alluminium windows frames Install glazing
Jul
WILSON LANE CURRENT CONSTRUCTION PROGRAMME 9.3.22 ID
Task Name
Dur
Start
Finish
% Comple
314
Install Brickwork
12 d
Mon 13/02/23
315
Install Misc cladding
10 d
Mon 27/02/23
316
Install remaiming soffits
10 d
Tue 14/03/23
Tue 28/03/23 0%
317
Paint Caulk and defect
7d
Mon 3/04/23
Wed 19/04/23 0%
58 d
Wed 1/02/23
Mon 8/05/23 0%
318
Light weight Frames and cladding third Floor
Wed 1/03/23 0% Fri 10/03/23
Install external wall framing
15 d
Wed 1/02/23
Thu 23/02/23 0%
320
Install Alluminium windows frames
7d
Fri 24/02/23
Mon 6/03/23 0%
321
Install glazing
10 d
Tue 7/03/23
Tue 21/03/23 0%
322
Install Brickwork
12 d
Tue 7/03/23
Thu 23/03/23 0%
323
Install Misc cladding
10 d
Tue 21/03/23
Tue 4/04/23
324
Install remaiming soffits
10 d
Wed 5/04/23
Thu 27/04/23 0%
325
Paint Caulk and defect
7d
Fri 28/04/23
Mon 8/05/23 0%
93 d
Tue 13/12/22
Wed 31/05/23 0%
Light weight Frames & cladding fourth Floor Install external wall framing
15 d
Tue 13/12/22
Tue 24/01/23 0%
328
Install Alluminium windows frames
7d
Wed 25/01/23
Tue 7/02/23
329
Install glazing
10 d
Wed 8/02/23
330
Install Brickwork
12 d
Wed 8/02/23
Fri 24/02/23
0%
331
Install Misc cladding
10 d
Wed 22/02/23
Tue 7/03/23
0%
332
Install remaiming soffits
10 d
Wed 8/03/23
Wed 22/03/23 0%
333
Paint Caulk and defect
5d
Thu 25/05/23
Wed 31/05/23 0%
117 d
Fri 18/11/22
Tue 13/06/23 0%
335
Fit Off & Commission
1st Half Jul
3rd Quarter Sep
Nov
1st Quarter Mar Install Brickwork
Jan
Install Misc cladding Install remaiming soffits Paint Caulk and defect Light weight Frames and cladding third Floor Install external wall framing Install Alluminium windows frames Install glazing Install Brickwork Install Misc cladding Install remaiming soffits Paint Caulk and defect Light weight Frames & cladding fourth Floor Install external wall framing Install Alluminium windows frames
0%
Install glazing
Wed 22/02/23 0%
Install Brickwork Install Misc cladding Install remaiming soffits Paint Caulk and defect Fit Off & Commission Internal Rough in and fit off Ground Floor
88 d
Fri 18/11/22
Tue 2/05/23
Rough in ceiling space elec mech and Hydro Fire
5d
Fri 18/11/22
Thu 24/11/22 0%
337
Rough in wall space elec mech and Hydro Fire
5d
Fri 25/11/22
Thu 1/12/22
0%
Rough in wall space elec mech and Hydro Fire
338
Sheet rooms Wet areas first Including ceiling
3d
Fri 2/12/22
Wed 7/12/22 0%
Sheet rooms Wet areas first Including ceiling
339
Stop & Sand walls and celings wet areas
2d
Thu 8/12/22
340
Paint Ceilings to wet areas
2d
Mon 12/12/22
341
Sheet Plaster walls
11 d
Thu 8/12/22
342
Install timber pertical board
9d
Thu 8/12/22
Tue 20/12/22 0%
Install timber pertical board
343
Install grid framing
6d
Mon 12/12/22
Mon 19/12/22 0%
Install grid framing
344
Sheet ceiling
3d
Tue 20/12/22
345
Stop and sand walls
3d
Mon 16/01/23
Wed 18/01/23 0%
Stop and sand walls
346
Light cut out and Mech&Fire Peno's
3d
Mon 16/01/23
Wed 18/01/23 0%
Light cut out and Mech&Fire Peno's
347
Pre Paint (Base Coat)
3d
Thu 19/01/23
Mon 23/01/23 0%
Pre Paint (Base Coat)
348
Defect plaster
3d
Fri 20/01/23
Tue 24/01/23 0%
Defect plaster
349
Final coats of Paint to walls and ceilings
8d
Mon 23/01/23
Fri 3/02/23
0%
350
Install AP
1d
Tue 7/02/23
Tue 7/02/23
0%
351
Fit Off elec and Plumbinng wet areas
10 d
Tue 24/01/23
Thu 9/02/23
0%
352
ITP ITR DDA compliant install Sanitary hardware
0d
Thu 9/02/23
Thu 9/02/23
0%
353
Fit off sanitary Hardware and fixtures
3d
Fri 10/02/23
Tue 14/02/23 0%
Fit off sanitary Hardware and fixtures
354
Remaining Vinyl
5d
Wed 8/02/23
Tue 14/02/23 0%
Remaining Vinyl
355
Remaining Floor coverings and covings
6d
Wed 15/02/23
Thu 23/02/23 0%
356
Fit off Jambs
5d
Thu 23/02/23
Wed 1/03/23 0%
357
Install Joinery
6d
Wed 1/03/23
Wed 8/03/23 0%
358
Hang doors and Hardware Arch and skirts
10 d
Thu 9/03/23
Thu 23/03/23 0%
359
Paint Jams and Doors
10 d
Fri 24/03/23
Mon 17/04/23 0%
360
Fit off door Furniture
5d
Tue 18/04/23
Mon 24/04/23 0%
361
Fit Off Mech elec Fire Hydro
20 d
Wed 15/03/23
Thu 20/04/23 0%
362
Trims transitions and tactiles
3d
Mon 24/04/23
Thu 27/04/23 0%
363
Builders Clean Caulk and defect
3d
Fri 28/04/23
Tue 2/05/23
80 d
Thu 1/12/22
Wed 3/05/23 0%
Internal Rough in and fit off Level 1
Fri 9/12/22
0%
May
336
364
Internal Rough in and fit off Ground Floor
May
0%
327
334
1st Quarter Mar
0%
319
326
1st Half Jan
Rough in ceiling space elec mech and Hydro Fire
Stop & Sand walls and celings wet areas
0%
Paint Ceilings to wet areas
Tue 13/12/22 0% Fri 13/01/23
Fri 13/01/23
Sheet Plaster walls
0%
Sheet ceiling
0%
Final coats of Paint to walls and ceilings Install AP Fit Off elec and Plumbinng wet areas 9/02/23
Remaining Floor coverings and covings Fit off Jambs Install Joinery Hang doors and Hardware Arch and skirts Paint Jams and Doors Fit off door Furniture Fit Off Mech elec Fire Hydro Trims transitions and tactiles Builders Clean Caulk and defect
0% Internal Rough in and fit off Level 1 Rough in ceiling space elec mech and Hydro Fire
365
Rough in ceiling space elec mech and Hydro Fire
5d
Thu 1/12/22
366
Rough in wall space elec mech and Hydro Fire
5d
Fri 9/12/22
Thu 15/12/22 0%
Rough in wall space elec mech and Hydro Fire
367
Sheet rooms Wet areas first Including ceiling
3d
Fri 16/12/22
Tue 20/12/22 0%
Sheet rooms Wet areas first Including ceiling
368
Stop & Sand walls and celings wet areas
2d
Thu 12/01/23
369
Paint Ceilings to wet areas
2d
Mon 16/01/23
Tue 17/01/23 0%
370
Sheet Plaster walls
10 d
Thu 12/01/23
Wed 25/01/23 0%
371
Install timber perticle board
8d
Thu 12/01/23
Mon 23/01/23 0%
372
Install grid framing
3d
Mon 16/01/23
Wed 18/01/23 0%
373
Sheet ceiling
3d
Mon 23/01/23
Wed 25/01/23 0%
374
Stop and sand walls
3d
Mon 30/01/23
Wed 1/02/23 0%
Stop and sand walls
375
Light cut out and Mech&Fire Peno's
3d
Mon 30/01/23
Wed 1/02/23 0%
Light cut out and Mech&Fire Peno's
376
Pre Paint (Base Coat)
3d
Thu 2/02/23
Tue 7/02/23
0%
377
Defect plaster
5d
Fri 3/02/23
Fri 10/02/23
0%
378
Final coats of Paint to walls and ceilings
13 d
Thu 9/02/23
379
Install AP
2d
Wed 1/03/23
Thu 2/03/23
380
Fit Off elec and Plumbinng wet areas
7d
Wed 8/02/23
Thu 16/02/23 0%
381
ITP ITR DDA compliant install Sanitary hardware
0d
Thu 16/02/23
Thu 16/02/23 0%
382
Fit off sanitary Hardware and fixtures
3d
Fri 17/02/23
Wed 22/02/23 0%
Fit off sanitary Hardware and fixtures
383
Remaining Vinyl
5d
Wed 15/02/23
Wed 22/02/23 0%
Remaining Vinyl
384
Remaining Floor coverings and covings
6d
Thu 23/02/23
Thu 2/03/23
385
Fit off Jambs
3d
Thu 2/03/23
Mon 6/03/23 0%
386
Install Joinery
3d
Mon 6/03/23
Wed 8/03/23 0%
387
Hang doors and Hardware Arch and skirts
9d
Thu 9/03/23
Wed 22/03/23 0%
388
Paint Jams and Doors
5d
Thu 23/03/23
Thu 30/03/23 0%
389
Fit off door Furniture
4d
Fri 31/03/23
Wed 5/04/23 0%
390
Fit Off Mech elec Fire Hydro
20 d
Wed 22/03/23
391
Trims transitions and tactiles
1d
Wed 5/04/23
Wed 5/04/23 0% Wed 3/05/23 0%
392 393
Builders Clean Caulk and defect Internal Rough in and fit off Level 2
3d
Mon 1/05/23
89 d
Mon 16/01/23
Thu 8/12/22
Fri 13/01/23
0%
Stop & Sand walls and celings wet areas
0%
Paint Ceilings to wet areas Sheet Plaster walls Install timber perticle board Install grid framing Sheet ceiling
Pre Paint (Base Coat) Defect plaster Final coats of Paint to walls and ceilings
Tue 28/02/23 0%
Fri 28/04/23
Tue 6/06/23
Install AP
0%
Fit Off elec and Plumbinng wet areas 16/02/23
Remaining Floor coverings and covings
0%
Fit off Jambs Install Joinery Hang doors and Hardware Arch and skirts Paint Jams and Doors Fit off door Furniture Fit Off Mech elec Fire Hydro
0%
0%
Trims transitions and tactiles Builders Clean Caulk and defect Internal Rough in and fit off Level 2 Rough in ceiling space elec mech and Hydro Fire
394
Rough in ceiling space elec mech and Hydro Fire
15 d
Mon 16/01/23
Wed 8/02/23 0%
395
Rough in wall space elec mech and Hydro Fire
10 d
Wed 1/02/23
Wed 15/02/23 0%
396
Sheet rooms Wet areas first Including ceiling
10 d
Thu 16/02/23
Thu 2/03/23
0%
Sheet rooms Wet areas first Including ceiling
397
Stop & Sand walls and celings wet areas
5d
Fri 3/03/23
Thu 9/03/23
0%
Stop & Sand walls and celings wet areas
398
Paint Ceilings to wet areas
8d
Fri 10/03/23
399
Sheet Plaster walls
20 d
Fri 24/02/23
400
Install timber perticle board
12 d
Fri 24/02/23
Tue 14/03/23 0%
401
Install grid framing
6d
Fri 10/03/23
Mon 20/03/23 0%
Wilson Lane Current Program 30.11.21
Wed 22/03/23 0% Fri 24/03/23
0%
Rough in wall space elec mech and Hydro Fire
Paint Ceilings to wet areas Sheet Plaster walls Install timber perticle board Install grid framing
Jul
WILSON LANE CURRENT CONSTRUCTION PROGRAMME 9.3.22 ID
Task Name
Dur
Start
402
Sheet ceiling
7d
Tue 21/03/23
403
Stop and sand walls
10 d
Fri 31/03/23
404
Light cut out and Mech&Fire Peno's
5d
Fri 31/03/23
405
Pre Paint (Base Coat)
5d
Mon 24/04/23
406
Defect plaster
3d
407
Final coats of Paint to walls and ceilings
408
Finish
% Comple
Thu 30/03/23 0%
1st Half Jan
1st Quarter Mar
May
1st Half Jul
3rd Quarter Sep
Nov
Jan
1st Quarter Mar Sheet ceiling
May
Jul
Fri 21/04/23
0%
Stop and sand walls
Thu 6/04/23
0%
Light cut out and Mech&Fire Peno's
Mon 1/05/23 0%
Pre Paint (Base Coat)
Fri 28/04/23
Tue 2/05/23
0%
Defect plaster
10 d
Mon 1/05/23
Fri 12/05/23
0%
Install AP
1d
Mon 15/05/23
Mon 15/05/23 0%
409
Fit Off elec and Plumbinng wet areas
8d
Tue 2/05/23
Thu 11/05/23 0%
410
ITP ITR DDA compliant install Sanitary hardware
0d
Thu 11/05/23
Thu 11/05/23 0%
411
Fit off sanitary Hardware and fixtures
3d
Fri 12/05/23
Tue 16/05/23 0%
Fit off sanitary Hardware and fixtures
412
Remaining Vinyl
5d
Wed 10/05/23
Tue 16/05/23 0%
Remaining Vinyl
413
Remaining Floor coverings and covings
6d
Wed 17/05/23
Wed 24/05/23 0%
414
Fit off Jambs
3d
Tue 23/05/23
Thu 25/05/23 0%
415
Install Joinery
3d
Wed 24/05/23
416
Hang doors and Hardware Arch and skirts
10 d
Wed 15/03/23
417
Paint Jams and Doors
7d
418
Fit off door Furniture
6d
419
Fit Off Mech elec Fire Hydro
10 d
Wed 24/05/23
420
Trims transitions and tactiles
4d
Thu 25/05/23
421 422
Builders Clean Caulk and defect Internal Rough in and fit off Level 3
Fri 26/05/23
Final coats of Paint to walls and ceilings Install AP Fit Off elec and Plumbinng wet areas 11/05/23
Remaining Floor coverings and covings Fit off Jambs Install Joinery
0%
Wed 29/03/23 0%
Hang doors and Hardware Arch and skirts
Thu 30/03/23
Mon 17/04/23 0%
Paint Jams and Doors
Tue 18/04/23
Wed 26/04/23 0%
4d
Thu 1/06/23
78 d
Thu 9/02/23
Tue 6/06/23
Fit off door Furniture Fit Off Mech elec Fire Hydro
0%
Trims transitions and tactiles
Tue 30/05/23 0% Tue 6/06/23
Builders Clean Caulk and defect
0%
Tue 13/06/23 0%
Internal Rough in and fit off Level 3 Rough in ceiling space elec mech and Hydro Fire
423
Rough in ceiling space elec mech and Hydro Fire
15 d
Thu 9/02/23
Thu 2/03/23
0%
424
Rough in wall space elec mech and Hydro Fire
10 d
Fri 24/02/23
Thu 9/03/23
0%
425
Sheet rooms Wet areas first Including ceiling
5d
Fri 10/03/23
Fri 17/03/23
0%
426
Stop & Sand walls and celings wet areas
6d
Mon 20/03/23
Tue 28/03/23 0%
427
Paint Ceilings to wet areas
8d
Wed 29/03/23
Mon 17/04/23 0%
428
Sheet Plaster walls
16 d
Mon 20/03/23
Wed 19/04/23 0%
429
Install timber perticle board
12 d
Mon 20/03/23
Wed 5/04/23 0%
430
Install grid framing
3d
Wed 29/03/23
431
Sheet ceiling
3d
Mon 17/04/23
Wed 19/04/23 0%
432
Stop and sand walls
5d
Thu 20/04/23
Thu 27/04/23 0%
433
Light cut out and Mech&Fire Peno's
3d
Thu 20/04/23
Mon 24/04/23 0%
434
Pre Paint (Base Coat)
5d
Fri 28/04/23
Thu 4/05/23
0%
435
Defect plaster
5d
Wed 3/05/23
Tue 9/05/23
0%
436
Final coats of Paint to walls and ceilings
10 d
Mon 8/05/23
Fri 19/05/23
0%
437
Install AP
1d
Mon 22/05/23
438
Fit Off elec and Plumbinng wet areas
3d
Fri 5/05/23
Tue 9/05/23
0%
439
ITP ITR DDA compliant install Sanitary hardware
0d
Tue 9/05/23
Tue 9/05/23
0%
440
Fit off sanitary Hardware and fixtures
3d
Wed 10/05/23
Fri 12/05/23
0%
Fit off sanitary Hardware and fixtures
441
Remaining Vinyl
5d
Mon 8/05/23
Fri 12/05/23
0%
Remaining Vinyl
442
Remaining Floor coverings and covings
6d
Mon 15/05/23
Mon 22/05/23 0%
443
Fit off Jambs
3d
Mon 22/05/23
Wed 24/05/23 0%
444
Install Joinery
3d
Wed 24/05/23
Fri 26/05/23
0%
445
Hang doors and Hardware Arch and skirts
10 d
Thu 6/04/23
Fri 28/04/23
0%
446
Paint Jams and Doors
7d
Mon 1/05/23
Tue 9/05/23
0%
447
Fit off door Furniture
6d
Wed 10/05/23
Wed 17/05/23 0%
448
Fit Off Mech elec Fire Hydro
14 d
Wed 24/05/23
Tue 13/06/23 0%
449
Trims transitions and tactiles
4d
Tue 23/05/23
450 451
Builders Clean Caulk and defect Internal Rough in and fit off Level 4
Fri 31/03/23
Rough in wall space elec mech and Hydro Fire Sheet rooms Wet areas first Including ceiling Stop & Sand walls and celings wet areas Paint Ceilings to wet areas Sheet Plaster walls Install timber perticle board Install grid framing
0%
Sheet ceiling Stop and sand walls Light cut out and Mech&Fire Peno's Pre Paint (Base Coat) Defect plaster Final coats of Paint to walls and ceilings Install AP
Mon 22/05/23 0%
Fri 26/05/23
Fit Off elec and Plumbinng wet areas 9/05/23
Remaining Floor coverings and covings Fit off Jambs Install Joinery Hang doors and Hardware Arch and skirts Paint Jams and Doors Fit off door Furniture Fit Off Mech elec Fire Hydro Trims transitions and tactiles
0%
6d
Mon 5/06/23
Tue 13/06/23 0%
81 d
Tue 31/01/23
Wed 7/06/23 0%
Builders Clean Caulk and defect Internal Rough in and fit off Level 4 Rough in ceiling space elec mech and Hydro Fire
452
Rough in ceiling space elec mech and Hydro Fire
15 d
Tue 31/01/23
Wed 22/02/23 0%
453
Rough in wall space elec mech and Hydro Fire
10 d
Wed 15/02/23
Wed 1/03/23 0%
454
Sheet rooms Wet areas first Including ceiling
8d
Thu 2/03/23
Tue 14/03/23 0%
455
Stop & Sand walls and celings wet areas
6d
Wed 15/03/23
Wed 22/03/23 0%
456
Paint Ceilings to wet areas
8d
Thu 23/03/23
Tue 4/04/23
457
Sheet Plaster walls
20 d
Tue 7/03/23
Wed 5/04/23 0%
458
Install timber perticle board
12 d
Tue 7/03/23
Thu 23/03/23 0%
459
Install grid framing
6d
Thu 23/03/23
460
Sheet ceiling
3d
Mon 3/04/23
Wed 5/04/23 0%
461
Stop and sand walls
5d
Thu 6/04/23
Thu 20/04/23 0%
462
Light cut out and Mech&Fire Peno's
3d
Thu 6/04/23
Tue 18/04/23 0%
463
Pre Paint (Base Coat)
5d
Fri 21/04/23
464
Defect plaster
5d
Thu 27/04/23
Wed 3/05/23 0%
465
Final coats of Paint to walls and ceilings
10 d
Tue 2/05/23
Mon 15/05/23 0%
466
Install AP
1d
Tue 16/05/23
Tue 16/05/23 0%
467
Fit Off elec and Plumbinng wet areas
3d
Mon 1/05/23
Wed 3/05/23 0%
468
ITP ITR DDA compliant install Sanitary hardware
0d
Wed 3/05/23
Wed 3/05/23 0%
469
Fit off sanitary Hardware and fixtures
3d
Thu 4/05/23
Mon 8/05/23 0%
Fit off sanitary Hardware and fixtures
470
Remaining Vinyl
5d
Tue 2/05/23
Mon 8/05/23 0%
Remaining Vinyl
471
Remaining Floor coverings and covings
6d
Tue 9/05/23
Tue 16/05/23 0%
472
Fit off Jambs
3d
Tue 16/05/23
Thu 18/05/23 0%
473
Install Joinery
3d
Thu 18/05/23
Mon 22/05/23 0%
474
Hang doors and Hardware Arch and skirts
10 d
Fri 24/03/23
Mon 17/04/23 0%
475
Paint Jams and Doors
7d
Tue 18/04/23
Thu 27/04/23 0%
476
Fit off door Furniture
6d
Fri 28/04/23
477
Fit Off Mech elec Fire Hydro
15 d
Thu 18/05/23
Wed 7/06/23 0%
478
Trims transitions and tactiles
4d
Wed 17/05/23
Mon 22/05/23 0%
479 480
Builders Clean Caulk and defect Sevices & Final Commissioning
Fri 31/03/23
Fri 28/04/23
Fri 5/05/23
0%
0%
Rough in wall space elec mech and Hydro Fire Sheet rooms Wet areas first Including ceiling Stop & Sand walls and celings wet areas Paint Ceilings to wet areas Sheet Plaster walls Install timber perticle board Install grid framing Sheet ceiling Stop and sand walls Light cut out and Mech&Fire Peno's Pre Paint (Base Coat)
0%
Defect plaster Final coats of Paint to walls and ceilings Install AP Fit Off elec and Plumbinng wet areas 3/05/23
Remaining Floor coverings and covings Fit off Jambs Install Joinery Hang doors and Hardware Arch and skirts Paint Jams and Doors Fit off door Furniture
0%
4d
Fri 2/06/23
Wed 7/06/23 0%
38 d
Wed 19/04/23
Tue 13/06/23 0% Wed 24/05/23 0%
Fit Off Mech elec Fire Hydro Trims transitions and tactiles Builders Clean Caulk and defect Sevices & Final Commissioning Install Main and Distribution Boards
481
Install Main and Distribution Boards
25 d
Wed 19/04/23
482
Install Mechanical Switch boards
22 d
Wed 19/04/23
483
Install water meters
2d
Mon 22/05/23
Tue 23/05/23 0%
484
Commissioning of fire services
5d
Wed 24/05/23
Tue 30/05/23 0%
485
Installation of FIP
4d
Wed 31/05/23
Mon 5/06/23 0%
486
receive 309
0d
Mon 5/06/23
Mon 5/06/23 0%
5/06/23
487
Receive occupancy
0d
Mon 5/06/23
Mon 5/06/23 0%
5/06/23
488
Practical Completion
0d
Tue 13/06/23
Tue 13/06/23 0%
Wilson Lane Current Program 30.11.21
Fri 19/05/23
0%
Install Mechanical Switch boards Install water meters Commissioning of fire services Installation of FIP
13/06/23