SA M IH P SE L E Q
Appendix G. EH&S Compliance Checklist Environment, Health and Safety Compliance EH&S CHECKLIST – ITP Subcontractor: ARC PLUMBING
Project:
Work Description:
3 4 5 6 7 8 9 10 11 12 13 14 15
Status
Health or Environmental Items
Days of the Week
Method Statement being followed
Waste Management Plan being followed
Workers using personal protective equipment
Fall restraints being used to prevent falls more than 2.0 metres Handrails in place at slab edges
Are manual handling procedures adopted
Are measures in place to prevent items falling on personnel working below
Is there fencing and signage in place to isolate work area? Adequate task lighting supplied Are access ways clear
Are penetrations protected in your work area Is a first aider part of your team Is work area clean
Are all personnel inducted to site rules and SWP - WMS Have SDS sheets been supplied
Page 48 of 48
Sign off:
Date:
M
2
Safety Rep Name
Day:
Description of Safe Work Practices,
Item 1
Job No:
ARC Plumbing WHS Management Project Folder
T
W
T
Non Conformances/Corrective Action
F
Rectification Action
S
S
Action By
Action Date
Memo No.
(who)
(when)