energystore superbead® IWI KIWA Agrement

Page 1

T:+44(0)1332383333 W:www.kiwa.co.uk/bda

SCOPE

ThisAgrémentrelatestoinjectedinternalwallinsulation(IWI),hereinaftertheSystem,basedonsuperbeadcavitywallinsulation(hereinafterCWI).The Systemisinstalledtoimprovethethermalinsulationofexternalclosedconstructioncavitywalls.TheSystemisonlyforuseinpropertieswithexteriormasonry wallsofatleast300mmthick,witharesidualcavityofatleast50mmbetweentheinternalfaceoftheexternalwallandaninternallining(oftraditionallathand plasterorrefurbishedwithinternaltimberstudworkandaplasterboardlining)hereinaftertheinnerleafTheSystemisforuseincavitywallsinexisting residentialbuildingsintheUKandIreland.

DESCRIPTION

TheSystemconsistsofagrey,spherical,closedcell,carbonenhancedexpandedpolystyrene(hereinafterEPS)beadmanufacturedwithapentaneexpanding agentinaccordancewithdraftBSEN16809-1.Awater-baseddispersionofacrylicco-polymeremulsion,air-drying,contactbondingadhesiveissimultaneously injectedwiththeEPSbeadswithappropriateinjectionmachinery.TheEPSbeadsarecoatedwiththebondingadhesiveintheinjectionguntobondandsetthe EPSbeadsandmaketheEPSbeadfillstableoverthelong-term.TheSystemisinjectedthroughaseriesofholes,drilledinapredeterminedpattern.Layersof EPSbeadsarebuiltupuntilthewholecavitywallisfullyfilledinaccordancewithBSEN16809-2.

SYSTEMILLUSTRATION

Nonerequired.

THIRD-PARTYACCEPTANCE

STATEMENT

ItistheopinionofKiwaLtd.,thattheSystemisfitforitsintendeduse,provideditisspecified,installedandusedinaccordancewiththisAgrément.

IssueDate:July2019 ©2019KiwaLtd. Page1of11
Derby
KiwaLtd. Unit5PrimeParkWay PrimeEnterprisePark
DE13QB
BAW-19-106-S-A-UK BDAAgrément® superbead InjectedInternalWallInsulation EnergystoreLtd. 21-23ShoreRoad Holywood BT189HX T:+44(0)2890301500 E:info@energystoreltd.com W:www.energystoreltd.com
CraigDevine OperationsManager,BuildingProducts AlpheoMlothaCEngFIMMMMBA HeadofOperations,BuildingProducts

SUMMARYOFAGRÉMENT

ThisdocumentprovidesindependentinformationtoSpecifiers,buildingcontrolpersonnel,contractors,installersandotherconstructionindustryprofessionals consideringthefitnessfortheintendeduseoftheSystem.ThisAgrémentcoversthefollowing:

Conditionsofuse;

InitialFactoryProductionControl,QualityManagementSystemandtheAnnualVerificationprocedure; PointsofattentionfortheSpecifierandexamplesofdetails; Installation;

IndependentlyassessedSystemcharacteristicsandotherinformation; CompliancewithnationalBuildingRegulations,otherregulatoryrequirementsandThird-Partyacceptance; Sources,includingcodesofpractice,testandcalculationreports.

MAJORPOINTSOFASSESSMENT

Adequacyoffill-walls,includingpartiallyfilledcavitywalls,canbefullyfilledsufficientlywiththeSystem(seesection2.1.10)

Thermalinsulationproperties-theSystemimprovesthethermalinsulationofthewallstructure(seesection2.1.10).

Condensationrisk-theSystemcancontributetolimitingtheriskofinterstitialandsurfacecondensation(seesection2.1.10).

Resistancetoprecipitationincludingwind-drivenrainpenetration-theSystemwillresistthetransferofwateracrossthecavitytotheinnerleaf(see section2.1.10).

Resistancetogroundmoisture-theSystemdoesnotabsorbwaterbycapillaryaction(seesection2.1.10).

Behaviourinrelationtofire-theSystemisclassifiedasEuropeanClassificationE,inaccordancewithBSEN13501-1(seesection2.1.10)

Durability-theSystemisstable,rot-proof,waterresistantanddurableandwillhaveaservicelifeequivalenttothatofthelifeofacavitywallinwhichitis installed(seesection2.1.8).

CEmarking-theproductmanufacturershavetakenresponsibilityforCEmarkingoftheproductsusedintheSysteminaccordancewithallrelevant harmonisedEuropeanProductStandards.Anasterisk(*)appearinginthisAgrémentindicatesthatdatashownisgivenintherelevantproductmanufacturers DeclarationofPerformance(DoP).

Page2of11
IssueDate:July2019 ©2019KiwaLtd.
CONTENTS Chapter1-Generalconsiderations 1.1-Conditionsofuse 1.2-InitialFactoryProductionControl(FPC) 1.3-QualityManagementSystem(QMS) 1.4-Annualverificationprocedure-continuoussurveillance Chapter2-Technicalassessment 2.1-PointsofattentiontotheSpecifier 2.2-Examplesofdetails 2.3-Installation 2.4-IndependentlyassessedSystemcharacteristics 2.5-Ancillaryitems Chapter3-CDM,nationalBuildingRegulationsandThird-Partyacceptance 3.1-TheConstruction(DesignandManagement)Regulations2015andTheConstruction(DesignandManagement)Regulations(NorthernIreland)2016 3.2-NationalBuildingRegulations 33-Third-Partyacceptance Chapter4-Sources Chapter5-Amendmenthistory

1.1-CONDITIONSOFUSE

1.1.1Designconsiderations

Seesection2.1.

1.1.2Application

TheassessmentoftheSystemrelatestoitsuseinaccordancewiththisAgrémentandtheAgrémentholdersrequirements.

1.1.3Assessment

KiwaLtd.hasassessedtheSystemincombinationwithitsrelevantDoPs,testreports,technicalliteratureandfactoryandsitevisits.FactoryProductionControl hasbeenassessed.

1.1.4Installationsupervision

TheAgrémentholderonlymanufacturesandsuppliestheSystem.InstallationcompaniesaretrainedandapprovedbytheAgrémentholder.

Thequalityofinstallationandworkmanshipmustbecontrolledbyacompetentpersonwhoshallbeanemployeeoftheinstallationcompany.

TheSystemshallbeinstalledstrictlyinaccordancewiththerequirementsofthisAgrément.

Seealsosection2.1.6

1.1.5Geographicalscope

ThevalidityofthisdocumentislimitedtoEngland,Wales,Scotland,NorthernIrelandandIreland,withdueregardtochapter3ofthisAgrément(CDM,national BuildingRegulationsandThird-PartyAcceptance)

1.1.6Validity

ThepurposeofthisBDAAgrément®istoprovideforwell-foundedconfidencetoapplytheSystemwithintheScopedescribedThevalidityofthisAgrémentis threeyearsaftertheissuedate,andaspublishedonwww.kiwa.co.uk/bda.Afterthis,thevalidityofthisAgrémentcanbeextendedeverythreeyearsaftera positivereview.

1.2-INITIALFACTORYPRODUCTIONCONTROL(FPC)

KiwaLtd.hasdeterminedthattheAgrémentholderhasfulfilledallprovisionsofthespecificationsdescribedinthisAgrémentinrespectoftheSystem TheinitialFPCauditdemonstratedthattheAgrémentholderhasasatisfactoryQualityManagementSystem(QMS)andiscommittedtocontinuously improvingtheirFPCoperations.

AdetailedProductionQualitySpecification(PQS)hasbeencompiledtoensuretraceabilityandcomplianceunderthetermsofthisAgrément

1.3-QUALITYMANAGEMENTSYSTEM(QMS)

TheAgrémentholder:

o hasaneffectiveandwellmaintainedQMSinoperationwhichcoversthenecessaryclausesrequiredforBDAAgrément®;

o iscommittedtocontinuallyimprovingtheirFPC,QMSandassociatedprocedures.

Documentcontrolandproductionlineproceduresweredeemedsatisfactory,withsufficientevidenceprovidedinsupportofBDAAgrément®requirements.

1.4-ANNUALVERIFICATIONPROCEDURE-CONTINUOUSSURVEILLANCE

TodemonstratethattheFPCisinconformitywiththerequirementsofthetechnicalspecificationdescribedinthisAgrément,thecontinuoussurveillance, assessmentandapprovaloftheFPCwillbedoneatafrequencyofnotlessthanonceperyearbyKiwaLtd.

Page3of11
IssueDate:July2019 ©2019KiwaLtd.
CHAPTER1-GENERALCONSIDERATIONS

CHAPTER2-TECHNICALASSESSMENT

ThisAgrémentdoesnotconstituteadesignguidefortheSystem.Itisintendedasanassessmentoffitnessforpurposeonly.

2.1-POINTSOFATTENTIONTOTHESPECIFIER

2.1.1Designresponsibility

ProjectspecificdesignistheresponsibilityofanApprovedInstallertrainedandapprovedbytheAgrémentholder.

2.1.2Appliedbuildingphysics(heat,airmoisture)

ThephysicalbehaviourofthewallincorporatingtheSystemshallbeverifiedassuitablebyacompetentspecialist,whocanbeeitheraqualifiedemployeeofthe Agrémentholderoraqualifiedconsultant.TheSpecialistwillcheckthephysicalbehaviouroftheexternalwalldesignandifnecessarycanofferadvicein respectofimprovementstoachievethefinalspecification.AcondensationriskanalysisshallbecompletedatdesignstageinaccordancewithBS5250.Itis recommendedthattheSpecialistco-operatescloselywiththeAgrémentholder.

2.1.3Generaldesignconsiderations

Considerationshallbegiventothelocalwind-drivenrainindexandthesiteexposurezoneaccordingtoBS8104

Theminimumcavitywidthtobefilledmustbenolessthan50mm

The50mmcavitybetweentheinnerfaceoftheexternalmasonrywallandouterfaceoftheinnerleafmustbefreefromobstructiontoensurethatthereisnota bridgethatallowswatertocrossthecavityfromtheexternalmasonrywalltotheinnerleaf

Avapourcontrollayer(hereinafterVCL)canbeappliedontheinternalfaceoftheinnerleaftoensurethatthemoisturecontentofthetimberiskeptatorbelow 20%,andtoensuretheairtightnessofthebuilding.

2.1.4Projectspecificdesignconsiderations

Pre-installationsurveyrequirements

Apre-installationsurveymustbeundertakentotheAgrémentholdersspecification;itisamandatoryrequirementtouseatapemeasureandborescope,to assessthewidthofthecavityandtoensureaclearvoidexists.Thefindingsofthissurveymustberecordedonasurveyorsreport.Selectionofanappropriate drillingpatternmusttakeintoconsiderationthenatureofthebuildinganditsconstruction.

2.1.5Permittedapplications

OnlyapplicationsdesignedaccordingtothisAgrémentareallowed,ineachcasetheSpecifiermustcooperatecloselywiththeAgrémentholder.

TheSystemshallbespecifiedinexistingbuildingstocomplywiththerequirementsofthenationalBuildingRegulations.

2.1.6Installercompetencelevel

TheAgrémentholderoperatesanApprovedInstallerSchemefortheSystemunderwhichinstallersareapproved,registeredandregularlyreviewedbythe AgrémentholdertodemonstratethattheyarecompetenttocarryoutinstallationsoftheSysteminaccordancewiththisAgrément.DetailsofApprovedInstallers areavailablefromtheAgrémentholder.ApprovedInstallersarefullyresponsibleforeachinstallationoftheSystemthattheyundertake.Furthermore,installers aretobemonitoredunderanIndependent3rdPartyCWIInstallationAssessment&SurveillanceSchemeoperatedorapprovedbyKiwaLtd.

2.1.7Delivery,storageandsitehandling

Seesection2.3

2.1.8Durability

Onceinstalled,theSystemisprotectedinservicefromagentsliabletocausedeteriorationandwillbeeffectiveasinsulationforthelifeofthebuildinginwhichit isinstalled.Ifitisdeemednecessaryforanyreason,theSystemcanbeextractedfromthecavityvoid

2.1.9Maintenanceandrepair

Onceinstalled,theSystemdoesnotrequireregularmaintenanceprovidedtheweather-tightnessoftheexternalcavitywallismaintained.Foradviceinrespect ofrepair,consulttheAgrémentholder.

2.1.10PerformancefactorsinrelationtotheMajorPointsofAssessment

Adequacyoffill

Acavitywallcanbefullyfilled(withoutgapsandwithaconsistentdensity)usingtheSystem.ThebondingadhesiveensuresthattheSystemremainsstable withinthecavityandhasadequateresistancetosettlement.

Thermalinsulationproperties

ForthepurposeofU-valuecalculationsandtodetermineiftherequirementsofnationalBuildingRegulationsaremet,thethermalresistanceandU-valueof cavitywallsincorporatingtheSystemshouldbecalculatedinaccordancewithBSENISO10211(takingintoconsiderationBSENISO6946,BSENISO10456, BREReport443,PAS2030andPAS2035),usingtheSystemsdeclaredthermalconductivity(D)value.

Condensationrisk

ExternalcavitywallsincorporatingtheSystemwilladequatelylimittheriskofsurfaceandinterstitialcondensationwhendesignedinaccordancewithBS5250.

Page4of11
IssueDate:July2019 ©2019KiwaLtd.

Resistancetoprecipitationincludingwind-drivenrainpenetration

TheSystemwillresistanywind-drivenrainpenetrationacrossacavitytotheinnerleaf.

ThegapsthatoccurbetweentheEPSbeadsallowanywatertodraindownfreelytotheground,ratherthanacrosstheSystem.

Resistancetogroundmoisture

TheSystemdoesnotabsorbwaterbycapillaryaction.TestsconfirmtheSystemwillnottransmitmoisturebycapillaryactionacrossthecavity.

Behaviourinrelationtofire

TheSystemisclassifiedasEuropeanClassificationEinaccordancewithBSEN13501-1.

ForresidentialbuildingsinEngland,WalesandNorthernIreland,thefollowingappliesinaccordancewiththenationalBuildingRegulations: theSystemisrestrictedtobuildingswithnofloormorethan11maboveground.RefertothenationalBuildingRegulationsfortypesofbuildingsandany exclusionsthatmayapply; boundaryrestrictionswillapply,dependentontheexternalsurfacematerialsoftheexternalwallincorporatingtheSystem,facingtheboundary.

ForallbuildingsinScotland,theSystemisrestrictedtobuildingswithnofloormorethan11mabovegroundandnotlessthan1mfromtheboundary.Insuch cases,theSystemmaybeexcludedfromtheunprotectedareacalculationregardlessofopenings.RefertothenationalBuildingRegulationsfortypesof buildingsandanyexclusionsthatmayapply.

FordwellingsinIreland,theSystemshallnotbeusedonbuildingswithastoreyof15mormoreabovegroundlevel;theSystemcanbeusedwithoutany boundaryrestrictions.RefertotherelevantnationalBuildingRegulationsfortypesofbuildingsandanyexclusionthatmayapply.

Toensurethatthefireintegrityofatimberframedwallismaintained,thetimberliningboardmusthavethejointsbetweentheboardsfullysealedandsupported bytimberstudworkorbattens.

Inallconstructions,cavitybarriersshallbeprovidedtocomplywiththerelevantprovisionsofthenationalBuildingRegulations.

Fordetailedconditionsofuseregardingrequirementsforsubstratefireperformance,cavityclosersandbarriers,firestoppingofservicepenetrationsand combustibilitylimitationsforothermaterialsandcomponentsusedintheoverallwallconstruction,designersshallrefertotherelevantnationalBuilding Regulations.

Proximityoffluesandappliances

Non-combustibleinsulationshallseparateorshieldtheinstalledSystemfromanyheat-emittingdevices,fixedcombustionappliances,incinerators,recessed lighting,fireplaces,chimneysorfluepipespassingthroughexternalwalls,andfromanypotentialsourceofignitionwherethetemperatureisinexcessof70°C, inaccordancewiththeprovisionsofthenationalBuildingRegulations.

2.2-EXAMPLESOFDETAILS

IssueDate:July2019 ©2019KiwaLtd. Page5of11
Diagram1-Typicaltimberstudworkinnerleaf Diagram2-Typicallathandplasterinnerleaf

2.3-INSTALLATION

TheSystemshallbeinstalledstrictlyinaccordancewiththeSystemManualinstructionsoftheAgrémentholderandtherequirementsofthisAgrément. InstallationcanbeundertakenbyoperativestrainedandapprovedbytheApprovedInstaller(whomustbelongtotheKiwaInstallerAssessmentand SurveillanceScheme)

2.3.2Delivery,storageandsitehandling

TheEPSbeads:

aredeliveredtositeinlargebulkcontainerloadsorpolythenebagsandlabelledwiththeSystemname,AgrémentholdersnameandtheBDAAgrément® logoincorporatingthenumberofthisAgrément.TheEPSbeadisotherwiseunprotected; shouldbekeptdryandawayfromheatsourcesandavoidrainexposureandprotectedfromprolongedexposuretosunlight.

Damaged,contaminatedorwetmaterialsmustnotbeused.

Thebondingadhesive:

isdeliveredtositeinplasticdrums/containersandlabelledwiththeSystemname,AgrémentholdersnameandtheBDAAgrément®logoincorporatingthe numberofthisAgrément;

hasanoptionalwintermixadhesiveavailablewhichhasaflowadditivetoassistincoldtemperatures; containersshouldbestoredinsideandoffthegroundatatemperaturebetween5°Cand25°Candprotectedfromfrost,directsunlightandhigh temperatures.

Donotusecontaminatedbondingadhesive.

2.3.3Generalprocedure

InstallationoftheSystemisundertakenusinginjectionmachinesbasedonacompressedairdeliverysystem.Theinstallerprovidesallnecessaryhoses,drilling tools,equipment,injectiongunandmaterialsformakinggoodthewallsaftertheinstallation.

Wheneverpracticableandpossible,allofthecavityspacefromgroundleveltotherooforgablecopingsshouldbefilled.Installationmustbecarriedouttothe highestpointineachelevation,ortoaleveldeterminedbyanyverticalcavitybarrierbetweenadjacentproperties(whicheveristhelower)

ThetargetmeaninstalleddensityofthisSystemis12kg/m3overtheentirewall.Localareaswithinthewallmustnothaveadensityvariationofmorethan ±2kg/m3fromthetargetmeandensityoveranareaof0.5m2

Ensurethattheexternalmasonrywallandroofisinagoodstateofrepairandthatallcavityopenings,suchasthosearounddoorsandwindows,aresealed,to avoidwateringressontotheSystem.

IssueDate:July2019 ©2019KiwaLtd. Page6of11 Diagram3-Typicaldrillpattern
2.3.1Installercompetencelevel TheAgrémentholderonlymanufacturesandsuppliestheSystem.

2.3.4Preparation

Typicalpreparatoryworksinclude,ifrequired: repairstotheinnerleaf; sleevingorotherwisemodifyingessentialventstopreventblockagebyinstallationoftheSystem; temporarysealingofalluncappedcavitywalls,windowsanddooropenings; provisionofacavitytray,stopendsandweepholesatlintellevel; removalofanydebrisinthecavity; sealingofdefectsinopeningsintheinnerorouterleafofwalls,especiallyelectricityandgasmeterboxesusingappropriatematerial; insertionofacavitybrushatthelinedividingsemi-detachedorterracedpropertiestopermanentlycontaintheSystem

2.3.5Standardfillmethod

TheSystemiscompatiblewiththefollowinginternalwalllinings: plasterboard; lathandplaster; VCLandplasterboard.

Drilling

Plasterboarddrillingoperation: core(over-drill)holesmustbe22mm.

Lathandplasterdrillingoperation: core(over-drill)holesmustbe22mm.

VCLandplasterboarddrillingoperation: core(over-drill)holesmustbe75mm.

Drillingpattern: therecommendeddrillingpatternisillustratedintheSystemManual; whereaVCLisin-situ,core(over-drill)holesmustpassonlythroughtheplasterboard; allcoresshouldbedrilledcentrallyand100-150mmfromthetopofeachpanelsection; anypanelsectionthatismorethan1.5minheightandlessthan50mminwidthshouldbedrilledintwoplaces,100mmfromthetopofthecavityand halfwaydownthecavity; amaximum22mmslitiscutintheVCLinthecentreofthe75mmcore(over-drill)holeifapplicable; core(over-drill)holesmustbedrilledsquaretotheinnerleaf; caremustbetakennottocausedamagetotheinnerleaf

Pre-fillingchecks

A360°borescopecheckshouldbecarriedoutineveryvoidbeingfilledtoensurethattheinnerleafhasbeenbuiltinlinewiththespecificationdrawings

Fillingcancommenceoncetheinstallerissatisfiedthattheinnerleafhasbeenbuilttospecification,wiringisencasedinconduitandlocationofthedrillholeis suitable.

Checksarecarriedouttodeterminetheinjectionmachinesettingsareoptimised,including: apressureswitchtestwhichensuresthattheinjectionmachinepressureswitchisoperatingcorrectly; EPSbeadandadhesiveflowratecheckwhichensuresthattheSystemwillbeinjectedintothecavitywiththecorrectamountofadhesivebeingappliedfor thevolumeofEPSbeadsrecordedatthedesiredEPSbeaddensity.

Injectionfilling

ThevoidswithintheinnerleafareinjectedwiththeSystemusingadirectionalnozzletopreventdamagetotheplasterboard/lathandplaster

SeetheSystemManualforfurtherdetailinrespectofthisprocedure.

2.3.6Finishing

ThefinishingprocessisdetailedintheSystemManual.

2.3.7Post-installationchecks

Post-installationexternalandinternalchecksarecarriedouttoensurethat:

theinstallationhasbeencompletedandthatnodamagehasoccurredtothebuilding; allareashavebeeninsulated;

allinternaldrillholesintheinnerleafarefinishedaspersection2.3.6;

allareasincludingtrunkedairvents,e.g.thoseprovidingunder-floorventilationandcombustionairforheatingappliances,arecheckedandany obstructionsorEPSbeadingressmustbeclearedandthecavitybreachsealedifpossible;

allfluesandchimneysmustbecarefullycheckedbyanappropriatetest(e.g.asmoketest)toverifythattheyareclearandunobstructed; EPSbeadsinjectedthroughthetopofthecavityintotheloftspaceareremovedandanypointsofleakagesealed; eavesintheloftareleftfreefromEPSbeadstofacilitateairflow; allelectriccircuitsandapplianceshavebeenreinstated.

IssueDate:July2019 ©2019KiwaLtd. Page7of11

2.4-INDEPENDENTLYASSESSEDSYSTEMCHARACTERISTICS

2.4.1Adequacyoffill(usingspecifiedinstallationmachineryanddrillingpattern)

ThefillingofcavitywallswiththeSystemhasbeenwitnessedin-situduringsitework,including: bespokeSystempre-installchecks; thecorrectdrillingpatternandaccuracy; correctinjectiontechniquebeingused

2.4.2EPSbeadsizeanddensity

Beadsizediameterbypassingsamplesthroughagradedseriesofsieves

2.4.3Thermalinsulationproperties

TheinstalledSystemhasdeclaredthermalconductivity(90/90

2.4.4Watervapourtransmission

2.4.5Waterabsorption

Short-termwaterabsorption(24hr)bypartialimmersiontoBSEN1609,methodA,40mmthickness, 23°C,50%rh

2.4.6Behaviourinrelationtofire

ReactiontofireclassificationtoBSEN13501-1

2.5-ANCILLARYITEMS

AncillaryitemsdetailedinthissectionmaybeusedinconjunctionwiththeSystembutfalloutsidethescopeofthisAgrément: finishingmaterials.

2)

©2019KiwaLtd. Page8of11
IssueDate:July2019
Test Result
2to8mm
12±2kg/m3overtheentireinstallation
InstalledtargetmeanapparentdensitytoBSEN16809-2andBSEN1602
Test Result
)toBSENISO10456andBSEN12667 0.033W/mK
Test Result Loose-fillEPSbeadshaveawatervapourresistancefactorµtoBSEN12524 2
Test Result
WS(valuedoesnotexceed1.0kg/m
Test Result
EuroclassE

CHAPTER3-CDM,NATIONALBUILDINGREGULATIONSANDTHIRD-PARTYACCEPTANCE

3.1-THECONSTRUCTION(DESIGNANDMANAGEMENT)REGULATIONS2015ANDTHECONSTRUCTION(DESIGNAND MANAGEMENT)REGULATIONS(NORTHERNIRELAND)2016

InformationinthisAgrémentmayassisttheclient,PrincipalDesigner/CDMco-ordinator,designerandcontractorstoaddresstheirobligationsunderthese Regulations.

3.2-NATIONALBUILDINGREGULATIONS

IntheopinionofKiwaLtd.,theSystem,ifinstalledandusedinaccordancewithChapter2ofthisAgrément,cansatisfyorcontributetosatisfyingtherelevant requirementsofthefollowingnationalBuildingRegulations.

3.2.1-ENGLAND REQUIREMENTS:THEBUILDINGREGULATIONS2010ANDSUBSEQUENTAMENDMENTS

B3(1)Internalfirespread(structure)-theSystemdoesnotprejudicethestabilityofwalls

B3(4)Internalfirespread(structure)-awallincorporatingtheSystemcaninhibittheunseenspreadoffireandsmokewithinconcealedspaces

C2(a)Resistancetogroundmoisture-theSystemdoesnotabsorbwaterbycapillaryaction

C2(b)Resistancetoprecipitationmoisture-awallincorporatingtheSystemcanresistrainpenetrationtotheinnerleafandsatisfythisRequirement C2(c)Resistancetocondensationmoisture-theSystemcancontributetosatisfyingthisRequirement

J4Protectionofbuilding-theSystemcanbeseparatedfromheatproducingappliances,fluepipes,chimneysandfireplacestopreventabuildingfrom catchingfire

L1(a)(i)Conservationoffuelandpower-theSystemcancontributetolimitingheatgainsandlossesthroughawall

Regulation7(1)-Materialsandworkmanship-theSystemismanufacturedfromsuitablysafeanddurablematerialsforitsapplicationandcanbeinstalled togiveasatisfactoryperformance

Regulation23-Requirementsrelatingtothermalelements-useoftheSystemcancontributetotheconservationoffuelandpowerinbuildingsbylimiting heatgainsandlossesthroughthermalelementsandotherpartsofthebuildingfabric

Regulation26-CO2emissionratesfornewbuildings-theSystemcancontributetosatisfyingthisRequirement

Regulation26A-Fabricenergyefficiencyratesfornewdwellings-theSystemcancontributetosatisfyingthisRequirement

Regulation26CTargetprimaryenergyratesfornewbuildings-theSystemcancontributetosatisfyingthisRequirement

3.2.2-WALES REQUIREMENTS:THEBUILDINGREGULATIONS2010ANDSUBSEQUENTAMENDMENTS

B3(1)Internalfirespread(structure)-theSystemdoesnotprejudicethestabilityofwalls

B3(4)Internalfirespread(structure)-awallincorporatingtheSystemcaninhibittheunseenspreadoffireandsmokewithinconcealedspaces

C2(a)Resistancetogroundmoisture-theSystemdoesnotabsorbwaterbycapillaryaction

C2(b)Resistancetoprecipitationmoisture-awallincorporatingtheSystemcanresistrainpenetrationtotheinnerleafandsatisfythisRequirement

C2(c)Resistancetocondensationmoisture-theSystemcancontributetosatisfyingthisRequirement

J4Protectionofbuilding-theSystemcanbeseparatedfromheatproducingappliances,fluepipes,chimneysandfireplacestopreventabuildingfrom catchingfire

L1(a)(i)Conservationoffuelandpower-theSystemcancontributetolimitingheatgainsandlossesthroughawall

Regulation7(1)Materialsandworkmanship-theSystemismanufacturedfromsuitablysafeanddurablematerialsforitsapplicationandcanbeinstalledto giveasatisfactoryperformance

Regulation23-Requirementsrelatingtothermalelements-useoftheSystemcancontributetotheconservationoffuelandpowerinbuildingsbylimiting heatgainsandlossesthroughthermalelementsandotherpartsofthebuildingfabric

Regulation26-CO2emissionratesfornewbuildings-theSystemcancontributetosatisfyingthisRequirement

Regulation26A-Primaryenergyratesfornewbuildings-theSystemcancontributetosatisfyingthisRegulation

Regulation26B-Fabricperformancevaluesfornewdwellings-theSystemcancontributetosatisfyingthisRequirement

Regulation26CMinimumenergyefficiencyrating-theSystemcancontributetosatisfyingthisRequirement

3.2.3-SCOTLAND REQUIREMENTS:THEBUILDING(SCOTLAND)REGULATIONS2004ANDSUBSEQUENTAMENDMENTS

3.2.3.1Regulation8(1)(2)Fitnessanddurabilityofmaterialsandworkmanship

TheSystemismanufacturedfromacceptablematerialsandisconsideredtobeadequatelyresistanttodeteriorationandwearundernormalservice conditions,provideditisinstalledinaccordancewiththerequirementsofthisAgrément

3.2.3.2Regulation9BuildingStandards-Construction

2.1Compartmentation-awallincorporatingtheSystemcaninhibitthespreadoffireandsmoke

2.3Structuralprotection-theSystemdoesnotprejudicetheload-bearingcapacityofwalls

2.4Cavities-awallincorporatingtheSystemcaninhibittheunseenspreadoffireandsmokewithinconcealedspaces

3.4Moisturefromtheground-theSystemcancontributetoaconstructionsatisfyingthisstandardwithreferencetoclause3.4.1oftheTechnical Handbooks

3.10Precipitation-theexternalleafofacavitywallpreventsprecipitationfromreachingtheinnerleafofthewallbyallowingwatertodraindownthe resultantcavity;theSystemdoesnotinhibitthisaction

3.15Condensation-awallincorporatingtheSystemcanbedesignedandconstructedtoinhibitcondensation

IssueDate:July2019 ©2019KiwaLtd. Page9of11

3.19Combustionappliances-theSystemcanbeseparatedfromheatproducingappliances,fluepipes,chimneysandfireplacestopreventabuildingfrom catchingfire

6.1(b)Carbondioxideemissions-awallincorporatingtheSystemiscapableofreducingthecarbondioxideemissions

6.2Buildinginsulationenvelope-awallincorporatingtheSystemcanreduceheatloss

7.1(a)(b)Statementofsustainability-theSystemismanufacturedfrommaterialsthatcancontributetosatisfyingtherelevantrequirementsof Regulation9,Standards1to6,andthereforewillcontributetoaconstructionmeetingabronzelevelofsustainabilityasdefinedinthisStandard;in addition,theSystemcancontributetoaconstructionmeetingahigherlevelofsustainabilityasdefinedinthisStandard

3.2.3.3Regulation12BuildingStandards-Conversion

AllcommentsgivenunderRegulation9alsoapplytothisregulation,withreferencetoSchedule6ofTheBuilding(Scotland)Regulations2004and subsequentamendments,clause0.12oftheTechnicalHandbook(Domestic)andclause0.12oftheTechnicalhandbook(Non-Domestic)

3.2.4-NORTHERNIRELAND REQUIREMENTS:THEBUILDINGREGULATIONS(NORTHERNIRELAND)2012ANDSUBSEQUENTAMENDMENTS

23(1)(a)(i)(iii)(b)Fitnessofmaterialsandworkmanship-theSystemismanufacturedfrommaterialswhichareconsideredtobesuitablysafeand acceptableforuseasdescribedinthisAgrément

28(a)Resistancetogroundmoisture-theSystemcancontributetosatisfyingthisRegulation

28(b)Resistancetotheweather-awallprotectstheSystemfromprecipitationtotheinnerface

29Condensation-awallshallbedesignedandconstructedtopreventinterstitialcondensation

35(1)Internalfirespread-Structure-theSystemdoesnotprejudicethestabilityofwalls

35(4)Internalfirespread-Structure-awallincorporatingtheSystemcaninhibittheunseenspreadoffireandsmokewithinconcealedspaces 39(a)(i)Conservationmeasures-theSystemcancontributetolimitingheatgainsandlossesthroughawall

40(2)Targetcarbondioxideemissionrate-awallincorporatingtheSystemshallbedesignedandconstructedasnottoexceeditstargetCO2emissionrate 43Renovationofthermalelements-therenovationworkcarriedouttoensurethewallcomplieswithrequirement39(a)(i)

73(1)Protectionofpeopleandbuildings-theSystemcanbeseparatedfromheatproducingappliances,fluepipes,chimneysandfireplacestopreventa buildingfromcatchingfire

3.2.5-IRELAND REQUIREMENTS:BUILDINGREGULATIONS1997ANDSUBSEQUENTAMENDMENTS

InordertodemonstratecompliancewithIrishBuildingRegulations,thisBDAAgrément®certifiesthattheSystemcomplieswiththerequirementsofa recogniseddocumentandindicatesitissuitableforitsintendedpurposeanduse.

B3(1)Internalfirespread(structure)-theSystemdoesnotprejudicethestabilityofwalls

B3(3)Internalfirespread(structure)-awallincorporatingtheSystemcaninhibittheunseenspreadoffireandsmokewithinconcealedspaces

B8(1)Internalfirespread(structure)-theSystemdoesnotprejudicethestabilityofwalls

B8(3)Internalfirespread(structure)-awallincorporatingtheSystemcaninhibittheunseenspreadoffireandsmokewithinconcealedspaces

C4Resistancetoweatherandgroundmoisture-awallcanpreventthepassageofmoisturetotheinsideofthebuilding

D1Materialsandworkmanship-theSystemismanufacturedfromacceptablematerialsandisconsideredtobeadequatelyresistanttodeterioration andwearundernormalserviceconditions,provideditisinstalledinaccordancewiththerequirementsofthisAgrément

J3Protectionofbuilding-theSystemcanbeseparatedfromheatproducingappliances,fluepipes,chimneysandfireplacestopreventabuildingfrom catchingfire.

L1Conservationoffuelandenergy-theSystemcancontributetolimitingheatgainsandlossesthroughwallsandconservefuelandenergy

L2(a)Conservationoffuelandenergy(inexistingdwellings)-theSystemcancontributetolimitingheatgainsandlossesthroughwalls

L4(a)Conservationoffuelandenergy(inexistingbuildingsotherthandwellings)-theSystemcancontributetolimitingheatgainsandlossesthroughwalls

L5(c)Conservationoffuelandenergy(innewbuildingsotherthandwellings)-theSystemcancontributetolimitingheatgainsandlossesthroughwalls

Regulation7Conservationoffuelandenergyinexistingdwellings-theSystemcancontributetosatisfyingthisRequirement

Regulation8(c)Conservationoffuelandenergyinnewdwellings-theSystemcancontributetosatisfyingthisRequirement

3.3-THIRD-PARTYACCEPTANCE

Nonerequired.

IssueDate:July2019 ©2019KiwaLtd. Page10of11

CHAPTER4-SOURCES

BSENISO6946:2017Buildingcomponentsandbuildingelements.Thermalresistanceandthermaltransmittance.Calculationmethods

BSENISO10211:2017Thermalbridgesinbuildingconstruction.Heatflowsandsurfacetemperatures.Detailedcalculations

BSENISO10456:2007Buildingmaterialsandproducts.Hygrothermalproperties.Tabulateddesignvaluesandproceduresfordeterminingdeclaredand designthermalvalues

BSEN1602:2013Thermalinsulatingproductsforbuildingapplications.Determinationoftheapparentdensity

BSEN1609:2013Thermalinsulatingproductsforbuildingapplications.Determinationofshorttermwaterabsorptionbypartialimmersion

BSEN12524:2000Buildingmaterialsandproducts.Hygrothermalproperties.Tabulateddesignvalues

BSEN12667:2001Thermalperformanceofbuildingmaterialsandproducts.Determinationofthermalresistancebymeansofguardedhotplateandheat flowmetermethods.Productsofhighandmediumthermalresistance

BSEN13501-1:2018Fireclassificationofconstructionproductsandbuildingelements-Classificationusingdatafromreactiontofiretests

DraftBSEN16809-1.Thermalinsulationproductsforbuildings.In-situformedproductsfromloose-fillexpandedpolystyrene(EPS)beadsandbonded expandedpolystyrenebeads.Part1.Specificationforthebondedandloosefilledproductsbeforeinstallation

BSEN16809-2:2017Thermalinsulationproductsofbuildings.In-situformedproductsfromloose-fillexpandedpolystyrene(EPS)beadsandbonded expandedpolystyrenebeads.Specificationforthebondedandloose-fillproductsafterinstallation

BS5250:2011+A1:2016Codeofpracticeforcontrolofcondensationinbuildings

BS8104:1992Codeofpracticeforassessingexposureofwallstowind-drivenrain

BREReport443:2006ConventionsforU-valuecalculations

PAS2030:2019+A1:2022Specificationfortheinstallationofenergyefficiencymeasuresinexistingdwellings

PAS2035:2019+A1:2022Retrofittingdwellingsforimprovedenergyefficiency.Specificationandguidance

Remark:apartfromthesesourcesconfidentialreportsmayalsohavebeenassessed;anyrelevantreportsareinthepossessionofKiwaLtdandkeptin theTechnicalAssessmentFileofthisAgrément;theInstallationGuidesarecurrentatthetimeofpublicationandmaybesubjecttochange,theAgrément holdershouldbecontactedforclarificationofrevision

CHAPTER5-AMENDMENTHISTORY

IssueDate:July2019
Page11of11
©2019KiwaLtd.
Revision AmendmentDescription AmendedBy ApprovedBy Date - FirstIssue CVurley CForshaw July2019 A Updatedbeadsize CDevine CVurley June2021 B Updatedbeadsize AChapman CDevine September2022 C Re-issuefollowingsuccessful3YearRenewal AChapman CDevine October2022 D UpdatestoBuildingRegulationsandFirePerformance ETaylor CDevine August2023