PUBLIC



• Water from the broken water main undermined Orkney Lane and caused the road to buckle.
• A City of Atlanta Vactor truck traveling on Orkney Lane fell into a section of the damaged roadway.
• COSF will install road closure signs to prevent thru traffic in the area of the watermain break.
• Orkney Lane is maintained by the COSF but will be repaired by the City of Atlanta due to their water line break causing damage to Orkney Lane and Loch Lomond Trail.
• Watermain will be repaired first, followed by the reconstruction of Orkney Lane and a portion of Loch Lomond Trail.
• Road will be reconstructed to COSF standards.
• CoSF to request timeline for the repairs from the City of Atlanta.
1. Exterior Waterproofing
Replacement of existing damaged exterior below grade waterproofing with new materials, wall repair and below grade drainage installation. New Waterproofing membranes applied, and drainage completed
Completed
2. Interior Waterproofing
Interior gym walls and lower walls are being repaired; scraped and new waterproofing coatings were applied to the interior walls. New Waterproofing sealant applied
Completed
3. Replacement Roofing
Both roofs above gym and administrative area to be replaced. Roofing and Downspouts are completed
Completed
4. Basement-level Exterior metal Doors
5. Gym HVAC
Replacement of exterior doors on the basement level, due to extensive damage. The vendor is ordering the replacement doors.
New HVAC system installation in the basketball gymnasium (does not currently have a system installed). ITB has been published
6. Mold Remediation
Mold Remediation (addition to existing scope). Mold assessment in progress to identify cause.
Delayed- forecast completion date of 11/2022 due to special order doors
Delayed forecast completion date of 11/2022. Start-up of HVAC units forecast to start the week of 11/07/22
Bidding Phase –Project bids December 2.
• Boat Rock Rd, Campbellton Rd to FIB
• Counts were done from November 8-15, 2022
• 2 locations (N of Easton Dr & N of Regency Hills)
• Data is being tabulated
• Site Visit: Week of Nov 28
• Analysis & Report: Week of December 12
• Sandtown Center (Stone Bay Dr, Sandtown Center Blvd (2), Sandrock Ln, and Lakerock Dr)
• Counts were done from November 8-15, 2022
• Data is being tabulated
• Site Visit: Week of Nov 28
• Analysis & Report: Week of December 12
• Enon Road
• Ongoing counts
• Dublin Drive & Enon Mill Drive and Calverton Lane and Campbellton Rd
• Data will be tabulated after holidays
• Site Visit: Week of December 5
• Analysis & Report: Week of December 19
• Fulton Industrial Blvd @ Bakers Ferry Road
• Atlas completed traffic study in 2021
• Analysis shows a LOS B at signalized location
• Plan to perform Safety Analysis based on Crash Data
• Enon Pines Subdivision Traffic Calming
• Speed tables on order- Will be installed upon receipt
Analysis warrants the construction of an allway stop control on Boat Rock Road at Bakers Ferry Road (2 Solar LED)
70% reduction in serious and fatal crash
43% reduction in vehicle / pedestrian crash
reduce potential of angle crashes due to insufficient sight distance
Increased frequency of available gaps in southbound traffic on Bakers Ferry Road when turning onto Boat Rock Road