COSF D1 Public Works Presentation - November 2022 Townhall

Page 1

PUBLIC

WHO we are WHAT do we do and WHY do we do it

DISTRICT 1 TOWNHALL MEETING November 17, 2022
WORKS
MAINTENANCE – EVERY 2 WEEKS Cascade
• Weekly FIB
• 45 Miles, Bi-Weekly
ROW
Road Medians
Area
City Staff

STATUS OF CIP/T-SPLOST PROJECTS

STATUS OF CIP/T-SPLOST PROJECTS

STATUS OF CIP/T-SPLOST PROJECTS

STATUS OF CIP/T-SPLOST PROJECTS

STATUS OF CIP/T-SPLOST PROJECTS

STATUS OF CIP/T-SPLOST PROJECTS

STATUS OF CIP/T-SPLOST PROJECTS

STATUS OF CIP/T-SPLOST PROJECTS
Installation of 5’ wide concrete ADA (Americans with Disabilities Act) compliant sidewalks. Additional improvements include curb and gutter, drainage and pedestrian lighting on both sides of Danforth Road from Rehoboth Circle to Cascade Road. The approximate length of the project is 0.8 mile. • Project is in Advertisement Phase • Total Parcels: 35; Acquired: 35; Remaining: 0 • ROW acquisition complete • Project Advertised for Construction November 10, 2022. • Bid Opening December 19, 2022, Construction Begin May 2023
DANFORTH ROAD SIDEWALKS

WATER MAIN BREAK ORKNEY ROAD

• Water from the broken water main undermined Orkney Lane and caused the road to buckle.

• A City of Atlanta Vactor truck traveling on Orkney Lane fell into a section of the damaged roadway.

• COSF will install road closure signs to prevent thru traffic in the area of the watermain break.

• Orkney Lane is maintained by the COSF but will be repaired by the City of Atlanta due to their water line break causing damage to Orkney Lane and Loch Lomond Trail.

• Watermain will be repaired first, followed by the reconstruction of Orkney Lane and a portion of Loch Lomond Trail.

• Road will be reconstructed to COSF standards.

• CoSF to request timeline for the repairs from the City of Atlanta.

URA DISTRICT I- SANDTOWN GYM PROJECT STATUS

Summary of Sandtown Gym Project

Task Scope of Work/Observations

1. Exterior Waterproofing

Replacement of existing damaged exterior below grade waterproofing with new materials, wall repair and below grade drainage installation. New Waterproofing membranes applied, and drainage completed

Status

Completed

2. Interior Waterproofing

Interior gym walls and lower walls are being repaired; scraped and new waterproofing coatings were applied to the interior walls. New Waterproofing sealant applied

Completed

3. Replacement Roofing

Both roofs above gym and administrative area to be replaced. Roofing and Downspouts are completed

Completed

4. Basement-level Exterior metal Doors

5. Gym HVAC

Replacement of exterior doors on the basement level, due to extensive damage. The vendor is ordering the replacement doors.

New HVAC system installation in the basketball gymnasium (does not currently have a system installed). ITB has been published

6. Mold Remediation

Mold Remediation (addition to existing scope). Mold assessment in progress to identify cause.

Delayed- forecast completion date of 11/2022 due to special order doors

Delayed forecast completion date of 11/2022. Start-up of HVAC units forecast to start the week of 11/07/22

Bidding Phase –Project bids December 2.

DISTRICT
& Post Renovation Conditions Exterior below grade waterproofing (complete)
URA
I-SANDTOWN GYM PROJECT STATUS Pre
DISTRICT I- FIRE STATION 4 (PLUMMER RD)
Scope of Work /Observations
Generator Replacement Replacement of current defunct generator. Generator currently on order and scheduled to arrive in the beginning of June Complete 2. Kitchen Upgrade Renovation and Upgrade of existing kitchen. Materials are on order and submittals are being prepared by the vendor. Delayed Forecast completion date of 11/2022. See schedule at end of report.
URA
PROJECTS STATUS Tasks
Comments 1.
Fire Station 4
Installation of cabinets, counter, stove, refrigerator and hood. Final connections and adjustments are on going
Summary of
Project Recent Activities:
Emergency Generator Before After

SIGNALS/SIGNS RELATED ISSUES

Riverside Dr @ Campbellton Rd and Riverside Dr @ Plummer Rd –Removed No Truck sign from Riverside and Campbellton then reinstalled in correct place at Riverside and Plummer. Signs on FIB being cataloged by Traffic Operations for replacement by GDOT. South Fulton Stickers applied to cover Fulton County logo on FIB. Waycrest Dr – installed 2 No Dumping signs installed. 1 in the cul-de-sac and 1 before the culde-sac.

TRAFFIC STUDIES

• Boat Rock Rd, Campbellton Rd to FIB

• Counts were done from November 8-15, 2022

• 2 locations (N of Easton Dr & N of Regency Hills)

• Data is being tabulated

• Site Visit: Week of Nov 28

• Analysis & Report: Week of December 12

• Sandtown Center (Stone Bay Dr, Sandtown Center Blvd (2), Sandrock Ln, and Lakerock Dr)

• Counts were done from November 8-15, 2022

• Data is being tabulated

• Site Visit: Week of Nov 28

• Analysis & Report: Week of December 12

• Enon Road

• Ongoing counts

• Dublin Drive & Enon Mill Drive and Calverton Lane and Campbellton Rd

• Data will be tabulated after holidays

• Site Visit: Week of December 5

• Analysis & Report: Week of December 19

• Fulton Industrial Blvd @ Bakers Ferry Road

• Atlas completed traffic study in 2021

• Analysis shows a LOS B at signalized location

• Plan to perform Safety Analysis based on Crash Data

• Enon Pines Subdivision Traffic Calming

• Speed tables on order- Will be installed upon receipt

BOAT ROCK ROAD AT BAKERS FERRY ROAD

Analysis warrants the construction of an allway stop control on Boat Rock Road at Bakers Ferry Road (2 Solar LED)

70% reduction in serious and fatal crash

43% reduction in vehicle / pedestrian crash

reduce potential of angle crashes due to insufficient sight distance

Increased frequency of available gaps in southbound traffic on Bakers Ferry Road when turning onto Boat Rock Road

Traffic Assessment performed on Sep 8, 2022
Benefits:
Increased safety:
SOLID WASTE ITEMS • Waste Pro was selected as the Residential Citywide Solid Waste Service Provider (Nov 15) • Base Services include Weekly Garbage Collections & Monthly Bulky Waste • Premium services available from vendor • New Roll Carts • Comprehensive Outreach and Education Plan before new service begins • Expected to Start Late Spring Early Summer of 2023 • Street Sweeping Program • Begins in January 2023 • Emphasis is the removal of litter & protection of water quality • Focuses on collector roads & above with curb & or gutters (outside of subdivisions & office parks) Any questions related to residential sanitation, to report dumping, or to remove items from the road please call the City at 404.552.4311