“OFFERTE” 14/08/2012 12 004 Bestek Architect gebouw Z CGB UNIVERSITEIT ANTWERPEN Aankoopdienst tav Elio Berardocco Middelheimlaan 1 lokaal A126 2020 Antwerpen
DEMANDS
9030,7 sqm
faculty for ME Antwerp
6050,2 sqm
faculty for ME Antwerp phase 1
5390,2 sqm
primary spaces phase 1
832 sqm
312 sqm
Lab pumps compressors and turbines
390 sqm
Lab HVAC
technological units electromechanics 130 sqm
80 sqm
1248 sqm
technological units building science
workshop area weigh and drying zone
48 sqm
workshop sifting chamber
128 sqm
workshop Climate area
16 sqm 64 sqm
workshop storage and topography room research lab for concrete and concrete production area
48 sqm
Research lab for concrete and cement -mortar lab
128 sqm
Research lab for experimental concrete lab
64 sqm
Research lab for road construction ans asphalt production area
128 sqm
Research lab for road construction and asphalt experimentals
16 sqm 32 sqm 40 sqm 360 sqm
544 sqm
515,2 sqm
480 sqm
96 sqm 1152 sqm
600 sqm
common units for Technology
workshop area and soil storage
48 sqm
48 sqm
403 sqm
Storage area
Research lab for road construction and RHEO Research lab for raod construction and recycle Research lab for EP&B storage area and measurement Didactic lab - PC analysis chamber Didactic lab - didactic chamber
390 sqm
lab materials and machinery
13 sqm
technical area ( compressiond gases
32 sqm 88 sqm
Secretariat entrance // warehouse -Z meeting room / bib1
544 sqm
meeting rooms electromechanics
112 sqm
Research lab road concrete - investigation area
112 sqm
Research lab road construction - investigation area
128 sqm
Research lab EP&B - investigation area
163.2 sqm
Offices -BK
160 sqm
Classroom-1
160 sqm
Classroom-2
160 sqm
Classroom-3
common areas for general use meeting rooms Electromechanics
office areas building technology
multifunctional classrooms
project meeting rooms computer lab
Auxiliary spaces
32 sqm 32 sqm 32 sqm
Project and meeting room 1 Project and meeting room 2 Project and meeting room 3
160 sqm
computer lab 1
160 sqm
computer lab 2
160 sqm
computer lab 3
160 sqm
computer lab 4
160 sqm
computer lab 5
160 sqm
computer lab 6
160 sqm
computer lab 7
32 sqm
office helpdesk employee
600 sqm
entrance circulation space sanitary sanitary disabled network aggregation point central heating Installations ventilation groups storage and maintenance small storage and maintenance per floor elevators with one that operates as a freight elevator shower room for staff cycling
60 sqm
Open Spaces
250 bikes 30 sqm 30 sqm
2035 sqm 2970,5 sqm
faculty for ME Antwerp phase 2
2603 sqm
88 sqm
270 sqm
Auxiliary spaces
273 sqm
Robot lab
160 sqm
lab vision
117 sqm
lab electricity
455 sqm
lab electricity machines
640 sqm
lab automation
390 sqm
lab automotive
240 sqm
lab polytechnic 1 ( expansion space )
240 sqm
lab polytechnic 2 ( expansion space )
270 sqm
circulation space
Technological units electromechanics
primary spaces phase 2
480 sqm
bicycle parking garbage zone // building rest zone for garbage containers // garbage, paper . PMD
Common units for Technology
Common and general areas
sanitary sanitary disabled
97,5 sqm
Open Spaces
97,5 sqm
test area automotive vehicle
faculty for ME Antwerp
distribution by height phase 1 Lab pumps compressors and turbines
312 sqm
9030,7 sqm
2.5m network aggregation point
entrance 3.4.1
faculty for ME Antwerp part B
small storage and maintenance per floor
3.4.5
3.4.9
x sqm
x sqm
x sqm
circulation space
central heating Installations
elevators with one that operates as a freight elevator
x sqm
x sqm
x sqm
sanitary
ventilation groups
shower room for staff cycling
3.4.2
faculty for ME Antwerp part A
3.4.6
2970,5 sqm
3.4.10
3.4.7
6050,2 sqm
Open Spaces
3.4.11
primary spaces part B
Auxiliary spaces
primary spaces part A
Open Spaces Auxiliary spaces 60sqm
97,5 sqm 270 sqm
Lab HVAC
390 sqm
x sqm
x sqm
sanitary disabled
storage and maintenance
x sqm
x sqm
3.4.4
x sqm
600 sqm
3.4.8
600 sqm
2603 sqm
5390,2 sqm
Common and general areas
Common units for Technology Technology
Technological units electromechanics
multifunctional project meeting rooms classrooms
computer lab
88 sqm
office areas building technology
common areas for general use
meeting rooms Electromechanics
96 sqm
technological units building science
common units for Technology
technological units electromechanics
120 sqm
480 sqm
480 sqm
515,2 sqm
403 sqm
544 sqm
832 sqm
Storage area
1152 sqm
130 sqm
1248 sqm
2035 sqm
workshop storage and topography room 3.3.8
technical area ( compressiond gases test area automotive vehicle 3.8.1
workshop area and soil storage
80 sqm
workshop area weigh and drying zone
48 sqm
workshop sifting chamber workshop Climate area
workshop storage and topography room research lab for concrete and concrete production area Research lab for concrete and cement -mortar lab Research lab for experimental concrete lab
48 sqm 128 sqm
16 sqm 64 sqm
2.6m
technical area ( compressiond gases
128 sqm
Research lab for road construction and asphalt experimentals
64 sqm
3.7.2
3.7.1
x sqm
x sqm
3.6.8
3.6.7
240 sqm
240 sqm
lab electricity 3.6.3
zone for garbage containers // garbage, paper . PMD bicycle parking 3.5.1
Robot lab
lab vision 3.6.2
117 sqm
3.6.1
sanitary
3.4.4
3.4.3
circulation space 3.4.2
entrance 3.4.1
3.5.1
250 pcs
x sqm
x sqm
x sqm
x sqm
storage and maintenance
ventilation groups
3.4.8
3.4.7
central heating Installations
network aggregation point
x sqm
x sqm
garbage zone // building rest
160 sqm
3.5.1
273 sqm lab automation
sanitary disabled
30 sqm
3.4.6
3.4.5
3.6.4
x sqm
elevators & shower room for staff cycling freight elevator
640 sqm
455 sqm
3.4.11
3.4.10
3.3.30
x sqm
x sqm
computer lab 2 3.3.30
computer lab 1 3.3.30
Project and meeting room 1 3.3.29
160 sqm
160 sqm
computer lab 5
computer lab 4
160 sqm
160 sqm
160 sqm
3.3.30
Project and meeting room 1 3.3.29
32 sqm
160 sqm computer lab 6 3.3.30
lab electricity machines
3.6.5
computer lab 3
3.4.9
3.3.28
3.3.27
160 sqm
160 sqm
3.3.24
Classroom-2
32 sqm
office helpdesk employee 3.3.31
x sqm
112 sqm Research lab EP&B investigation area
48 sqm 16 sqm 32 sqm
163.2 sqm
160 sqm
Research lab for road construction ans asphalt production area 3.3.12
meeting room / bib1
16sqm
Research lab for EP&B storage area and measurement 3.3.16 Research lab for road construction and RHEO 32 sqm 3.3.14 48 sqm
112 sqm
128 sqm
Research lab road construction - investigation area
Offices -BK
3.3.24
3.3.26
3.3.22
112 sqm 163.2 sqm
meeting rooms Electromechanics
zone for garbage containers //
bicycle parking
3.5.1
distribution by height 2.5m
Lab pumps compressors and turbines 3.3.1
40 sqm
30 sqm
250 pcs
360 sqm
main links & process lines
312 sqm
technological units electromechanics
Lab HVAC 3.3.2
garbage zone // building rest
3.4.1
small storage and maintenance per floor
3.4.5
technical area ( compressiond gases
3.4.9
3.3.20
workshop sifting chamber
48 sqm
48 sqm
workshop Climate area 3.3.7
x sqm
x sqm
central heating Installations
elevators with one that operates as a freight elevator
3.4.6
3.4.10
x sqm
x sqm shower room for staff cycling
x sqm
x sqm
storage and maintenance
meeting room / bib1
3.4.3
3.4.7
x sqm
88 sqm
meeting rooms Electromechanics
x sqm
80 sqm
Research lab for concrete and cement -mortar lab
workshop area weigh and drying zone 3.3.5
3.3.10
Research lab for raod construction and recycle
distribution by height
phase 1
2.5m network aggregation point
3.4.1
small storage and maintenance per floor
3.4.5
3.4.9
x sqm
x sqm
x sqm
circulation space
central heating Installations
elevators with one that operates as a freight elevator
3.4.2
x sqm
3.3.25
3.4.10
x sqm
x sqm
ventilation groups
shower room for staff cycling
x sqm
x sqm
storage and maintenance
x sqm
x sqm
3.4.3
128 sqm Offices -BK
3.4.6
x sqm sanitary disabled
sanitary
3.4.7
3.4.11
3.3.26
3.4.4
112 sqm
160 sqm
160 sqm
3.4.8
Classroom-2 3.3.28
480 sqm 160 sqm
Project and meeting room 1 3.3.29
project meeting rooms
32 sqm
600 sqm
Project and meeting room 1 3.3.29
96 sqm
32 sqm Project and meeting room 1 3.3.29
2.6m
32 sqm
computer lab
computer lab 1
computer lab 4
3.3.30
3.3.30
160 sqm
160 sqm computer lab 5
3.3.30
3.3.30
computer lab 7 3.3.30
Research lab road concrete investigation area
technical area ( compressiond gases 3.3.20
160 sqm
Research lab EP&B investigation area
3.3.23
3.3.25
13 sqm
office helpdesk employee 3.3.31
Secretariat entrance // warehouse -Z 32 sqm
3.3.21
32 sqm 5390,2 sqm
160 sqm
160 sqm
computer lab 3 6050,2 sqm
128 sqm Offices -BK 3.3.26
3.3.22
3.3.30
112 sqm
88 sqm 160 sqm
160 sqm
163.2 sqm
meeting rooms Electromechanics
bicycle parking 3.5.1
250 pcs garbage zone // building rest 3.5.1
entrance
3.3.31
3.4.1
Auxiliary spaces
network aggregation point 3.4.5
30 sqm
small storage and maintenance per floor 3.4.9
zone for garbage containers // garbage, paper . PMD 3.5.1
x sqm circulation space 3.4.2
x sqm sanitary 3.4.3
32 sqm
112 sqm Research lab road construction - investigation area 3.3.24
meeting room / bib1
computer lab 6
1152 sqm
office helpdesk employee
600 sqm
x sqm central heating Installations 3.4.6
x sqm elevators with one that operates as a freight elevator
x sqm shower room for staff cycling
x sqm
x sqm
x sqm storage and maintenance
x sqm
x sqm
3.4.11
1452,2 sqm
3.4.8
3.5m
bicycle parking
Open Spaces
30 sqm
544 sqm
3.4.10
x sqm ventilation groups 3.4.7
sanitary disabled 3.4.4
9030,7 sqm
Didactic lab - didactic chamber
3.5.1
office helpdesk employee 3.3.31
3.3.18
250 pcs
32 sqm
garbage zone // building rest
workshop area and soil storage 3.3.4
3.5.1
60 sqm
workshop area and soil storage 3.3.4
30 sqm zone for garbage containers // garbage, paper . PMD
360 sqm
3.5.1
80 sqm
30 sqm
workshop area weigh and drying zone 3.3.5
Lab pumps compressors and turbines 3.3.1
48 sqm workshop sifting chamber 3.3.6 48 sqm workshop Climate area 3.3.7
312 sqm Lab HVAC 3.3.2
360 sqm
128 sqm
Technological units electromechanics
Robot lab 3.6.1
80 sqm
lab electricity machines 3.6.4
workshop storage and topography room 3.3.8
lab automotive
16sqm
3.6.6
Classroom-2
390 sqm
3.3.29
Storage area 3.3.3 273 sqm lab vision 3.6.2
workshop area weigh and drying zone 3.3.5
455 sqm lab automation
390 sqm 130 sqm
Project and meeting room 1
3.6.5
3.3.29
32 160sqm sqm
Classroom-1 160 sqm
faculty for ME Antwerp part B
primary spaces part B
3.3.27
Project and meeting room 1 3.3.29
lab electricity 3.6.3
32 sqm
2035 sqm
Project and meeting room 1
160 sqm 117 sqm
3.3.29
Classroom-2 32 sqm
3.3.28
640 sqm
computer lab 4 3.3.30
160 sqm research lab for concrete and concrete production area 3.3.9
48 sqm workshop sifting chamber 3.3.6
Common units for Technology Technology
160 sqm computer lab 5 3.3.30
lab polytechnic 1 ( expansion space ) 3.6.7
64 sqm Research lab for concrete and cement -mortar lab 3.3.10
160 sqm computer lab 6
48 sqm 240 sqm
3.3.30
Research lab for experimental concrete lab 3.3.11
lab polytechnic 2 ( expansion space ) 2603 sqm
3.6.8
160 sqm
2970,5 sqm 128 sqm
480 sqm
Research lab for road construction ans asphalt production area 3.3.12
240 sqm
computer lab 7 3.3.30
64 sqm Research lab for road construction and asphalt experimentals 3.3.13
Common and general areas
112 sqm
48 sqm workshop Climate area 3.3.7
312 sqm
160 sqm
Research lab for road construction and RHEO 3.3.14
128 sqm
48 sqm
computer lab 1 3.3.30
Research lab for raod construction and recycle 3.3.15
88 sqm
16sqm Research lab for EP&B storage area and measurement 3.3.16
160 sqm computer lab 2 3.3.30
32 sqm Didactic lab - PC analysis chamber 3.3.17 40 sqm
160 sqm computer lab 3 3.3.30
circulation space
3808 sqm
3.7.1
160 sqm
Lab HVAC 3.3.2
Auxiliary spaces
x sqm sanitary
6.0m
3.7.2
x sqm 270 sqm
sanitary disabled 3.7.3
lab materials and machinery x sqm
112 sqm
128 sqm
3.3.19
390 sqm
Open Spaces
390 sqm
test area automotive vehicle 3.8.1
97,5 sqm
workshop storage and topography room 128 sqm
16sqm
97,5 sqm
phase 2
2.6m
Common and general areas
88 sqm
Classroom-2
390 sqm
88 sqm
3.3.29 lab vision 3.6.2
163.2 sqm
3.5m
lab automation 3.6.5
160 sqm lab electricity machines 3.6.4
Storage area 3.3.3
640 sqm
455 sqm
lab automotive 3.6.6
lab polytechnic 1 ( expansion space ) 3.6.7
circulation space 3.7.1
x sqm sanitary 3.7.2
240 sqm 390 sqm
lab polytechnic 2 ( expansion space ) 3.6.8
x sqm sanitary disabled 3.7.3
240 sqm
Classroom-1 160 sqm
130 sqm
Project and meeting room 1
x sqm
2350 sqm Robot lab 3.6.1
3.3.29
4.0m
273 sqm lab electricity 3.6.3
117 sqm
32 160sqm sqm
Classroom-1
test area automotive vehicle 3.8.1
97,5 sqm
3.3.27
Project and meeting room 1
Classroom-2 160 sqm
3.3.29
32 sqm Project and meeting room 1
160 sqm
Classroom-3 160 sqm
3.3.29
Classroom-2 32 sqm
3.3.28
computer lab 4 3.3.30
32 sqm
160 sqm
32 sqm 32 sqm 160 sqm
research lab for concrete and concrete production area 3.3.9
160 sqm computer lab 5 3.3.30
64 sqm Research lab for concrete and cement -mortar lab 3.3.10
160 sqm
160 sqm
computer lab 6
48 sqm
3.3.30
Research lab for experimental concrete lab 3.3.11
computer lab 3
160 sqm
computer lab 4
160 sqm
computer lab 5
160 sqm
160 sqm 128 sqm Research lab for road construction ans asphalt production area 3.3.12
computer lab 7 3.3.30
64 sqm Research lab for road construction and asphalt experimentals 3.3.13
160 sqm
Research lab for road construction and RHEO 128 sqm 160 sqm
48 sqm
computer lab 1 3.3.30
Research lab for raod 3.3.15 16sqm
160 sqm
Research lab for EP&B storage area and measurement
160 sqm computer lab 2 3.3.30
32 sqm Didactic lab - PC analysis chamber 3.3.17
32 sqm 600 sqm
40 sqm
160 sqm computer lab 3 3.3.30
circulation space sanitary sanitary disabled
160 sqm
network aggregation point
3808 sqm
central heating Installations ventilation groups storage and maintenance small storage and maintenance per floor elevators with one that operates as a freight elevator shower room for staff cycling
6.0m lab materials and machinery
250 bikes
3.3.19
30 sqm 30 sqm
390 sqm
390 sqm
Common and general areas
Robot lab
2.6m 88 sqm
Common and general areas
88 sqm
273 sqm
88 sqm
lab vision
160 sqm
lab electricity
117 sqm
3.5m lab vision 3.6.2
lab electricity machines
455 sqm
160 sqm
lab automation 3.6.5
lab electricity machines 3.6.4
455 sqm
lab automation
640 sqm
640 sqm
lab automotive 3.6.6
lab polytechnic 1 ( expansion space ) 3.6.7
240 sqm 390 sqm circulation space
lab polytechnic 2 ( expansion space ) 3.6.8
3.7.1
sanitary
lab automotive
390 sqm
240 sqm
x sqm sanitary disabled 3.7.3
x sqm
lab polytechnic 1 ( expansion space ) 240 sqm
lab polytechnic 2 ( expansion space ) 240 sqm
2350 sqm
4.0m Robot lab 3.6.1
273 sqm
circulation space
270 sqm
lab electricity 3.6.3
sanitary 117 sqm
sanitary disabled test area automotive vehicle
test area automotive vehicle
97,5 sqm
97,5 sqm
487,5 sqm
3.3.29
160 sqm
160 sqm
273 sqm lab electricity 3.6.3
3.7.3
117 sqm x sqm test area automotive vehicle 3.8.1
97,5 sqm
Project and meeting room 1
3.3.30
3.3.30
3.3.30
640 sqm
3.3.29
3.3.29
32 sqm
lab automotive 3.6.6
160 sqm
160 sqm
computer lab 2
computer lab 5
3.3.30
3.3.30
lab polytechnic 1 ( expansion space ) 3.6.7
160 sqm office helpdesk employee 3.3.31
Project and meeting room 1 32 sqm
160 sqm
160 sqm
computer lab 3
computer lab 6
160 sqm
160 sqm
3.3.30
Research lab EP&B investigation area
112 sqm Research lab road construction - investigation area
3.3.29
3.6.1
3.7.2
x sqm sanitary disabled
455 sqm
computer lab 7
240 sqm
32 sqm
3.3.21
Classroom-2
Robot lab
sanitary
3.6.4
3.6.5
360 sqm computer lab 4
32 sqm
32 sqm
3.3.27
160 sqm lab electricity machines
lab automation
64 sqm Research lab for road construction and asphalt experimentals 3.3.13
computer lab 1
3.3.29
entrance
primary spaces part A
Classroom-2
3.3.27
160 sqm
163.2 sqm
faculty for ME Antwerp part A
Classroom-1
3.3.28
600 sqm
Secretariat entrance // warehouse -Z
Classroom-1
workshop storage and topography room 3.3.8
128 sqm
Classroom-2
360 sqm
88 sqm
faculty for ME Antwerp
16sqm
130 sqm
40 sqm
3.3.20
3.3.24
multifunctional classrooms
Storage area 3.3.3
Project and meeting room 1
3.3.16 32 sqm
Didactic lab - didactic chamber 3.3.18
128 sqm
515,2 sqm
3.7.1
x sqm 88 sqm
390 sqm
40 sqm Didactic lab - didactic chamber
390 sqm
lab polytechnic 2 ( expansion space ) 3.6.8
3.3.30
64 sqm
3.3.19
3.3.23
circulation space
3.6.2
3.3.19
32 sqm Didactic lab - PC analysis chamber 3.3.17
3.3.18
Research lab for road construction and asphalt experimentals 3.3.13
lab materials and machinery
technical area ( compressiond gases
Research lab road concrete investigation area
Common and general areas
lab materials and machinery
Research lab for raod construction and recycle 3.3.15 Research lab for EP&B storage area and measurement 3.3.16
30 sqm
30 sqm
Didactic lab - PC analysis chamber 3.3.17 128 sqm Research lab for road construction ans asphalt production area 3.3.12
48 sqm
Research lab for road construction ans asphalt production area 3.3.12
3.5.1
544 sqm
3.3.15 16sqm
Research lab for experimental concrete lab 3.3.11
3.3.6
128 sqm workshop storage and topography room 3.3.8 16sqm
Research lab for concrete and cement -mortar lab 3.3.10
Research lab for experimental concrete lab 3.3.11
128 sqm
128 sqm
Research lab for EP&B storage area and measurement
48 sqm
48 sqm workshop sifting chamber
48 sqm workshop Climate area 3.3.7
1248 sqm
common units for Technology
Research lab for road construction and RHEO 3.3.14 48 sqm
64 sqm
48 sqm workshop sifting chamber 3.3.6 48 sqm workshop Climate area 3.3.7
390 sqm
4.0m
3.5m
2.6m
6.0m
research lab for concrete and concrete production area 3.3.9
16sqm
312 sqm Lab HVAC 3.3.2
163.2 sqm
zone for garbage containers // garbage, paper . PMD
3.3.14
3.3.22
Lab pumps compressors and turbines 3.3.1
80 sqm workshop area weigh and drying zone 3.3.5 128 sqm
3.3.26
112 sqm
3.5.1
250 pcs
Research lab for road construction and RHEO
48 sqm
64 sqm
meeting room / bib1
3.5m
3.5m Lab pumps compressors and turbines workshop area and soil storage 3.3.4 3.3.1
3.3.25
Offices -BK
3.3.24
bicycle parking
3.5.1
research lab for concrete and concrete production area 3.3.9
workshop area and soil storage 3.3.4
technological units building science
common areas for general use
3.3.18
Research lab EP&B investigation area
112 sqm Research lab road construction - investigation area
3.4.11
3.4.8
garbage zone // building rest
1452,2 sqm
Didactic lab - didactic chamber
3.3.23
3.3.22
sanitary
544 sqm
544 sqm
3.3.21
32 sqm x sqm ventilation groups
x sqm sanitary disabled
128 sqm
120 sqm
88 sqm
Research lab road concrete investigation area
13 sqm
x sqm
Secretariat entrance // warehouse -Z
workshop area weigh and drying zone 3.3.5
3.4.4
390 sqm
13 sqm 32 sqm
phase 1 phase 2
2.6m
lab vision network aggregation point
entrance
circulation space 3.4.2
Storage area 3.3.3
meeting rooms Electromechanics
bicycle parking garbage zone // building rest zone for garbage containers // garbage, paper . PMD
Research lab for raod construction and recycle 3.3.15
360 sqm
office areas building technology
office helpdesk employee entrance
64 sqm
Didactic lab PC analysis chamber 3.3.17
3.3.25
13 sqm
computer lab 7
390 sqm
research lab for concrete and concrete production area 3.3.9
64 sqm
40 sqm
487,5 sqm
1452,2 sqm
3808 sqm
240 sqm
390 sqm
88 sqm
Lab pumps compressors and turbines 3.3.1
130 sqm
Research lab for concrete and cement -mortar lab 3.3.10 48 sqm
128 sqm
Research lab EP&B investigation area
403 sqm
computer lab 6
Research lab for experimental concrete lab 3.3.11
Lab HVAC 3.3.2
3.3.4
80 sqm
Research lab for road construction and asphalt experimentals 3.3.13
3.3.30
390 sqm
computer lab 2
48 sqm
Storage area 3.3.3
Secretariat entrance // warehouse -Z
544 sqm
Project and meeting room 1 Project and meeting room 2 Project and meeting room 3 computer lab 1
48 sqm 128 sqm
390 sqm 544 sqm
128 sqm
computer lab 7
30 sqm
Offices -BK
workshop area weigh and drying zone 3.3.5 workshop area and soil storage
390 sqm
Research lab road concrete investigation area
130 sqm
Research lab EP&B - investigation area
32 sqm
workshop sifting chamber 3.3.6
128 sqm
390 sqm
Research lab road construction - investigation area
3.3.19
3.3.21
88 sqm
3.3.25
3.3.18
130 sqm
Research lab road concrete - investigation area
workshop Climate area 3.3.7
Didactic lab - didactic chamber
Storage area 3.3.3
meeting rooms electromechanics
3.3.22
lab materials and machinery
13 sqm
160 sqm
832 sqm
technical area ( compressiond gases Secretariat entrance // warehouse -Z meeting room / bib1
Secretariat entrance // warehouse -Z
32 sqm
lab automotive 3.6.6
3.3.23
88 sqm
Research lab for road construction and RHEO
lab materials and machinery
3.3.23
112 sqm Offices -BK 3.3.26
3.3.29
meeting room / bib1
3.3.30
x sqm
small storage and maintenance per floor
meeting rooms Electromechanics
32 sqm
Project and meeting room 1 3.3.29
Classroom-1
16sqm
3.3.20
Research lab road concrete Research lab road construction - investigation area investigation area
Classroom-2
128 sqm
Research lab for raod construction and recycle Research lab for EP&B storage area and measurement Didactic lab - PC analysis chamber Didactic lab - didactic chamber
3.7.3
x sqm
lab polytechnic 1 ( expansion space )
13 sqm
32 sqm
Research lab for road construction ans asphalt production area
lab polytechnic 2 ( expansion space )
circulation space
30 sqm 97,5 sqm
3.3.20
48 sqm
sanitary disabled sanitary
2350 sqm 487,5 sqm
312 sqm
EXISTING
EVOLUTION
20000
15000
In 1852 the Jesuit Order founded a college for higher education in commerce and trade in the port city of Antwerp.
10000
5000
1900
1880
1840
1820
1800
1800
NSTRAATNAAM VESTIGING ANTWERPEN Posthofbrug 10, Antwerpen tel: 002600 fax: 03/221 55 01 Email: info.be@anteagroup.com www.anteagroup.be Antea Group is gecertificeerd volgens ISO9001 Stad Antwerpen Distrikt Wilrijk Opmeting terrein| Groenenborger ZNA Middelheim Universiteit Antwerpen LEGENDA BESTAANDE TOESTAND MONOLIET GEBOUW AUTO BERGPLAATS/GARAGE LICHTSIGNAAL VOETGANGER GRACHT BENEDENKANT SIGNALISATIE WEGWIJZER BOVENKANT VERKEERSTEKEN ONDERKANT PLAATSNAAM TALUD BOVENKANT TEORISTISCH OMTREK STRUIK BUS/TRAM RAND BOS LAAGSPANNING LOOFBOMEN VERLICHTING RIJ NAALDBOMEN PAAL DIVERSE DRAADGAAS VLAGGEMAST OMHEINING HOUT WATER PRIKKELDRAAD STRAATKAP GAS MUUR ELEKTRICITEIT KABINE/KAST VANGRAIL ENKEL KABINE/KAST TV BETONPLATEN TELEFOON HAAG TELEFOON SCHEIDING VERHARDINGEN DEKSEL/STRAATKAP VOLDIVERSE WITWITT PUTDEKSEL WEGMARKERING STREEP STRAATKOLK BRANDKRAAN BETON MEETPUNT AD-E KASSEI Opdrachtgever: MERKPAAL PRIVAAT BETONKLINKERS KILOMETERPAAL BETONDALS HEKTOMETERPAAL STEENSLAG HOOGTEPEIL MAAIVELD STRUIK Marc Verbruggen GEBOUW LOOFBOOM DORPELPEIL GARAGE NAALDBOOM FRUITBOOM Universiteit Antwerpen Prinsstraat 10 | KWS 2000 Antwerpen Stelsel Referentie Datum X-Y Flepos 12/06 ambert G.P.S. of ref nr de040464 Opgesteld door AnteaCoord. Group Kris Eddy Mertens Lodewyckx Landmeter-expert ,ZLT.A.W. beëdigd door Rechtbank van Eerste Aanleg van Antwerpen Contractmanager infratop Inschrijvingsnummer tableau : LAN AANGEBRACHTE Dos. nr. Antea WIJZIGINGEN Group: 224735 INDEX GET. AARD DATUM A B C Plan D Schaal: FEJI Planopp. m² nr: G H Gemeten: Bestand: 224735.dwg /Users/user/Desktop/Antwerp/Research/UA/UA Timeline.dwg
Alain Verschoren
The RUCA was housed in the buildings of the former Colonial School near the Middelheim Park.
In 2002 UFSIA, RUCA and UIA decided to merge into the University of Antwerp, the first explicitly pluralistic university in Belgium
In the late 1960s the college was granted university status
Craeybeckx Lode
RUCA was established in 1965 relating to the university expansion. strong advocate of the former mayor of Antwerp Craeybeckx Lode
2040
2020
2000
1980
1960
1940
1920
In 2003 three Institutions, each with a rich history and past, were consolidated into a single institution: The University of Antwerp. UA’s dilemma, or perhaps its greatest opportunity, is to develop a singular and unified identity without sacrificing the history and character of the three institutions.
Given its prominent location, Building Z has the potential to be a catalyst for a transformation far beyond the demands of the brief; success resides in the project’s ability to unite departments once separated.
Building Z is NOT solely a container for a lab, but a lab itself. Separating the functions into unique towers and cubes allows for maximum flexibility and change. However, the cubes are linked via shared program; thus the building can perform as one machine, without sacrificing the unique demands of each user. Simultaneously, the building could serve as a catalyst for a larger urban transformation. The laboratory fosters a spirit of innovation that extends itself to the practical functions of the program it supports.
CONTENTS
Concept
04
Content
15
Design
16
Urban Strategy Process Site Constraints Program Site Plan Campus Deck Lab Tower Office Tower Learning Bridge Building Options Landscape Facades
16 32 34 40 44 52 74 82 92 96 102 108
Technical
124
Structure Building Technology and Sustainability Labs Costs Costs Summary Program Summary Phasing
126 135
Drawings
160
Plan Matrix Plans @ 1:250 Sections and Elevations @ 1:250
162 164 170
Credits
187
112
148 150 154 156 158
CITY CAMPUS
MIDDELHEIM CAMPUS
GROENEBORGER CAMPUS
DRIE EIKEN CAMPUS
16
URBAN STRATEGY
CITY CAMPUS
4 CAMPUSES
MIDDELHEIM CAMPUS
GROENEBORGER CAMPUS
DRIE EIKEN CAMPUS
The University’s amalgamation of multiple institutions has resulted in its division between four campuses. Their distribution throughout the city has left the University without a true centre or ‘heart.’ If connected, the University stands to assert its presence throughout the entirety of Antwerp. 17
MIDDELHEIM CAMPUS
BUILDING Z
GROENEBORGER CAMPUS
18
CONNECTION TO SOFT SPINE
MIDDELHEIM CAMPUS
BUILDING Z
GROENEBORGER CAMPUS
19
Building Z negotiates a void between two of UA’s campuses and a proposed ecological zone.
20
MIDDELHEIM CAMPUS
GROENENBORGER CAMPUS
BUILDING Z
21
GROENENBORGER CAMPUS
22
MIDDELHEIM CAMPUS
23
2 BECOME 1
24
UNIVERSITY OF ANTWERP CAMPUS
25
UA CAMPUS
26
4 BECOME 1
CITY CAMPUS
MIDDELHEIM CAMPUS
GROENEBORGER CAMPUS
DRIE EIKEN CAMPUS
Linking the Middelheim and Groenenborger campuses could help create a unified campus for the UA and give the institution its center, literally and symbolically. As a whole, the combined campus holds a value greater than the sum of its parts. 27
UA CAMPUS
Z
28
29
Building Z can be the link, which unites the Middelheim and Groenenborger campuses, creating a true centre for UA, and ultimately generating a larger urban transformation.
? 30
31
PROCESS
34 ET_B30
PROCESS
35 ET_B30
SITE
34
35
SITE
36
37
SITE
38
39
SITE CONSTRAINTS
158.7
88.0
SITE DIMENSIONS - B / TU .25
45 30.0
ROOF SLOPE 45 AFTER 30M 40
35.0
MAXIMUM HEIGHT LIMIT 35M
12.0
12M SETBACK FROM ROAD 41
SITE CONSTRAINTS
8.0
MAXIMUM BUILDING HEIGHT 8M ON SOUTH
30.0
30M SETBACK FROM ADJACENT BUILDINGS 42
ZONING ENVELOPE
43
PROGRAM
7993.2 sqm
faculty for ME Antwerp
5390.2 sqm
base project
option
2603 sqm
44
3547 sqm
primary spaces
1843.2 sqm
services
1805 sqm
primary spaces
798 sqm
services
1700 sqm
LABS
220 sqm
concrete lab
230 sqm
road construction lab
3.3.9. concrete_production 3.3.10. concrete_mortar 3.3.11. concrete_experimental 3.3.24. research space_concrete 3.3.12. road construction_asphalt production 3.3.13. road construction_experimental 3.3.14. road construction_Rheo 3.3.15. road construction_recycle lab 3.3.25. research space_road construction 3.3.16. EP&B_storage lab 3.3.26. research space_EP&B
40 sqm 30 sqm 80 sqm 70 sqm 40 sqm 80 sqm 30 sqm 10 sqm
100 sqm 550 sqm
EP&B lab HVAC & compression lab
70 sqm 20 sqm 80 sqm
3.3.1. lab pumps
240 sqm
577 sqm
OFFICES
workshops
400 sqm
machinery and materials lab
400 sqm 442 sqm
3.3.2. lab HVAC 3.3.20. technical space (gases & compressor) 3.3.4. workshop_storage 3.3.5. workshop_weigh and drying zone 3.3.6. workshop_sifting chamber 3.3.7. workshop_climate area 3.3.8. workshop_storage and topography room
300 sqm 10 sqm
200 sqm
50 sqm 30 sqm 30 sqm
entrance/secretary offices
80 sqm 10 sqm
300 sqm
3.3.19. lab materials & machining
100 sqm 20 sqm
3.3.3. storage 3.3.21. secretary entrance
3.3.23. offices EM 3.3.27. offices BK 3.3.29. project meetingroom 3.3.29. project meetingroom 3.3.29. project meetingroom 3.3.22. meetingroom / bib 1 3.3.17. didactic lab_pc-analysis
340 sqm
1270 sqm
OFFICES
115 sqm
meetingrooms
102 sqm 20 sqm 20 sqm 20 sqm
250 sqm
didactic labs
55 sqm 25 sqm
300 sqm
classrooms
225 sqm
3.3.18. didactic lab_didactic space
100 sqm
3.3.28. classroom
100 sqm
3.3.28. classroom
100 sqm
3.3.28. classroom
100 sqm
3.3.30. computerroom
100 sqm
3.3.30. computerroom
100 sqm
3.3.30. computerroom
100 sqm
3.3.30. computerroom
100 sqm
3.3.30. computerroom
100 sqm
3.3.30. computerroom
100 sqm 20 sqm
3.3.30. ICT-helpdesk computerroom 3.3.31.
250 sqm 30 sqm 30 sqm
3.5.1. bike storage 3.5.2. garbage zone materials 3.5.3. garbage containers
720 sqm
1843.2 sqm
SERVICES
310 sqm
1533.2 sqm
computerrooms
open spaces
auxiliary spaces
X X X X X X X X X X X
3.4.1. entrancehall 3.4.2. circulationspace 3.4.3. sanitary 3.4.4. sanitary disabled people 3.4.5. server 3.4.6. central heathing 3.4.7. ventilation groups 3.4.8. storage and maintenance 3.4.9. smalle storage and maintenance, each floor 3.4.10. elevators, one service elevator 3.4.11. shower room for cycling
1532.95 sqm
1750 sqm
55 sqm 798 sqm
LABS
OFFICES SERVICES
560 sqm
robotica + lab electric mach 210 sqm
3.6.1. lab robotica
300 sqm
automotive
350 sqm
3.6.3.lab electric machines
490 sqm
lab electricity + automotion
300 sqm
3.6.5. automotive
90 sqm
3.6.3. lab electricity
100 sqm
400 sqm
3.6.4. automation
150 sqm
lab vision lab mechatronics
100 sqm
3.6.2. lab vision
150 sqm
lab polytechnic
150 sqm
3.6.6. mechatronic
55 sqm 723 sqm
meetingrooms auxiliary spaces
150 sqm
3.6.7. polytechnic lab 3.6.8. meetingroom
55 sqm
X X X
75 sqm
3.7.1. circulationspace 3.7.2. sanitary 3.7.3. sanitary disabled people
723 sqm
open spaces
75 sqm
45
3.8.1. automotive test vehicles
PROGRAM CLUSTERS
BASE OPTION
46
Concrete lab Road Construction lab EP&B lab
LAB
Lab HVAC & Compression Workshops Machinery / Storage
LEARNING
OFFICES
SERVICES
LAB
OFFICES
SERVICES
47
PROGRAM ORGINIZATION
PROGRAM CLUSTERS
SLAB
REDISTRIBUTE GFA INTO SLAB
LEARNING BRIDGE
48
CONSOLIDATE SERVICES
CREATE CAMPUS DECK - CONNECT CAMPUSES
BASE SCHEME
OPTION SCHEME
49
BUILDING Z
50
BASE PROJECT
OPTIONAL
805
2603
PRIMARY SPACES
3547
750
2515
LAB TOWER
1700
2435
210
273
CONCRETE LAB
220
100
160
ROAD CONSTRUCTION LAB
90
117
350
BASE PROJEC
1805
2603
LAB TOWER
1750
2515
304
ROBOT LAB
210
273
230
416
LAB VISION
100
160
EP&B LAB
100
160
LAB ELECTRICITY
90
117
455
HVAC & COMPRESSION LAB
550
715
LAB ELECTRICITY MACHINES
350
455
400
640
WORKSHOPS
200
320
LAB AUTOMATION
400
640
300
390
MACHINERY & MATERIALS
400
520
LAB AUTOMOTIVE
300
390
150
240
OFFICE TOWER
577
923.2
LAB POLYTECHNIC 1
150
240
150
240
OFFICES BK
102
163,2
LAB POLYTECHNIC 2
150
240
55
88
OFFICES EM
340
544
LEARNING
55
88
55
88
PROJECTMEETING ROOMS
115
184
MEETING ROOMS
55
88
798
X
SECRETARY
20
32 1960
X
XX
1270
798
798
LEARNING
360
798
XX
X
250
SERVICES
185
DIDACTIC LABS
480
185
X
X
300
CIRCULATION SPACE
85
CLASSROOMS
1120
85
X
X
720
SANITARY
18
COMPUTER LABS
NETWORK AGGREGATION POINT
18
X
55
X
STORAGE CLEANING
55
X
117
X
ELEVATOR + STAIRS
117
X
338
X
STRUCTURE
338
X
75
97.5
75
97.5
75
97.5
75
97.5
75
97.5
75
97.5
AUXILIAIRE SPACES
PRIMARY SPACES
AUXILIAIRE SPACES
1843.2 SERVICES
1843.2
X
ENTRANCE
100
X
CIRCULATION SPACE
500
X
SANITARY
170
X
NETWORK AGGREGATION POINT
36
X
CENTRAL HEATING
17
X
VENTILATION GROUPS
10
X
STORAGE CLEANING
117
X
ELEVATOR + STAIRS
235
X
STRUCTURE
658
X
5390.2
X
TOTAL
OPEN SPACES
OPEN SPACES
AUTOMOTIVE TEST VEHICLES
322 322
X
BICYCLE STORAGE
262
X
GARBAGE
60
X
51
Building Z will serve as a gateway to the University of Antwerp. Strategically positioned With no front or back, it serves as an entrance to the Middelheim and Groenenborger campuses and mediates a critical moment along the soft spine as an open thoroughfare.
52
53
SITE PLAN
54
55
SITE CIRCULATION
56
faculty
public pedestrians
students
bikes
cars
carsparking
delivery materials
57
58
59
60
61
62
65
66
67
WEST ELEVATION
68
EAST ELEVATION
69
70
71
72
73
The Campus Deck is the hinge between Middelheim and Groenenborger campuses. A plaza for students and faculty from every department, it will be an essential place of gathering and interaction for the entire University.
CAMPUS DECK
CAMPUS DECK
76
77
A registration of its program and an honest display of its process, Building Z is itself an instrument for learning. The functions have been organized into unique towers and cubes, which will allow for maximum flexibility and inevitable changes in lab technology. 78
79
LAB TOWER
The laboratories have been liberated from all other functions, allowing for changes to occur with the least amount of interruption to the operations of the overall building. The generic shape of the plan will also provide the most flexibility for the inevitable evolutions with regards to lab technology.
3.3.9. concrete_production 3.3.10. concrete_mortar 3.3.11. concrete_experimental 3.3.24. research space_concrete 3.3.12. road construction_asphalt production 3.3.13. road construction_experimental 3.3.14. road construction_Rheo 3.3.15. road construction_recycle lab 3.3.25. research space_road construction 3.3.16. EP&B_storage lab
40 sqm 30 sqm 80 sqm 70 sqm 40 sqm 80 sqm 30 sqm 10 sqm 70 sqm 20 sqm 80 sqm
3.3.26. research space_EP&B
3.3.1. lab pumps
240 sqm
80 sqm 10 sqm
3.3.2. lab HVAC 3.3.20. technical space (gases & compressor) 3.3.4. workshop_storage 3.3.5. workshop_weigh and drying zone 3.3.6. workshop_sifting chamber 3.3.7. workshop_climate area 3.3.8. workshop_storage and topography room
300 sqm
3.3.19. lab materials & machining
100 sqm
3.3.3. storage
210 sqm
3.6.1. lab robotica
350 sqm
3.6.3.lab electric machines
300 sqm
3.6.5. automotive
90 sqm
3.6.3. lab electricity
400 sqm
3.6.4. automation
100 sqm
3.6.2. lab vision
150 sqm
3.6.6. mechatronic
150 sqm
3.6.7. polytechnic lab
300 sqm 10 sqm 50 sqm 30 sqm 30 sqm
3.3.20 13 sqm 3.4.7
technical area (compressed gases)
x sqm 3.4.6
x sqm
ventilation groups
central heating Installations
3.3.1
3.3.15
Research lab for raod 16sqm construction and recycle 3.3.14 48 sqm 3.3.13
Research lab for road construction and RHEO 312 sqm
3.3.10 48 sqm 3.3.24
ground program
112 sqm
Research lab for concrete and cement -mortar lab
128 sqm
Research lab for road construction and asphalt experimentals
3.3.25
Research concrete construction - investigation area
112 sqm
Research lab road investigation area
32 sqm
Lab pumps, compressors and turbines
3.3.2
3.3.16 Research lab for EP&B storage area and measurement
3.3.25
128 sqm
Research lab EP&B investigation area
390 sqm
Lab HVAC
3.5.1
30 sqm 3.5.1
30 sqm
garbage zone // building rest zone for garbage containers // garbage, paper . PMD
3.3.8 16sqm workshop storage and topography room 3.3.7
3.3.3
128 sqm 130 sqm
3.3.6
Storage area
workshop Climate area
3.3.19
390 sqm
48 sqm 3.3.5
workshop sifting chamber
48 sqm 3.3.4
workshop area weigh and drying zone
80 sqm
workshop area and soil storage
3.3.11
128 sqm
Research lab for experimental concrete lab
3.3.9
64 sqm
research lab for concrete and concrete production area
Research lab for road construction ans asphalt production area 3.3.12
64 sqm
lab materials and machinery MACHINERY / STORAGE
WORKSHOPS
CONCRETE
ROAD CONSTRUCTION
82
EP & B
LABS COMPRESSORS
LAB PROGRAM
LEVEL 02
LEVEL 03
LEVEL 04
LOWER GROUND FLOOR
CAMPUS DECK
LEVEL 01
COMPR. LAB HVAC LAB EP & B LAB ROAD LAB CONCRETE LAB
WORKSHOPS
83
MACHINE LAB
CONCRETE LAB
40 sqm 30 sqm 80 sqm 70 sqm
84
3.3.9. concrete_production 3.3.10. concrete_mortar 3.3.11. concrete_experimental 3.3.24. research space_concrete
MATERIAL & MACHINERY LAB
300 sqm
85
3.3.19. lab materials & machining
ROAD CONSTRUCTION LAB
40 sqm 80 sqm 30 sqm 10 sqm 70 sqm
86
3.3.12. road construction_asphalt production 3.3.13. road construction_experimental 3.3.14. road construction_Rheo 3.3.15. road construction_recycle lab 3.3.25. research space_road construction
EP & B LAB
87
20 sqm
3.3.16. EP&B_storage lab
80 sqm
3.3.26. research space_EP&B
HVAC LAB
300 sqm 10 sqm
88
3.3.2. lab HVAC 3.3.20. technical space (gases & compressor)
PUMPS, COMPRESSOR & TURBINE LAB
240 sqm
89
3.3.1. lab pumps
OFFICE TOWER
OFFICE PROGRAM
20 sqm
340 sqm 102 sqm 20 sqm 20 sqm 20 sqm 55 sqm 55 sqm
3.3.21. secretary entrance
3.3.23. offices EM 3.3.27. offices BK 3.3.29. project meetingroom 3.3.29. project meetingroom 3.3.29. project meetingroom 3.3.22. meetingroom / bib 1 3.6.8. meetingroom
92
OFFICE TOWER
LEVEL 02
LEVEL 03
LEVEL 04
LOWER GROUND FLOOR
CAMPUS DECK
LEVEL 01
OFFICE OFFICE EM OFFICE
93
The Learning Bridge serves as the link between the office and the Labs. Strategically positioned between the labs and office, the Bridge will be able to function 24 hours while the rest of the building can be securely closed. And due to its central location and shared use, the Bridge is a platform for interaction between departments. 94
LEARNING BRIDGE
95
LEARNING PROGRAM
25 sqm
3.3.17. didactic lab_pc-analysis
225 sqm
3.3.18. didactic lab_didactic space
100 sqm
3.3.28. classroom
100 sqm
3.3.28. classroom
100 sqm
3.3.28. classroom
100 sqm
3.3.30. computerroom
100 sqm
3.3.30. computerroom
100 sqm
3.3.30. computerroom
100 sqm
3.3.30. computerroom
100 sqm
3.3.30. computerroom
100 sqm
3.3.30. computerroom
100 sqm 20 sqm
3.3.30. computerroom 3.3.31. ICT-helpdesk
96
LEARNING BRIDGE
LEVEL 02
LEVEL 03
LEVEL 04
LOWER GROUND FLOOR
CAMPUS DECK
LEVEL 01
COMPUTER COMPUTER DIDACTIC
CLASSROOM
97
24 HOUR ACCESS
LEVEL 02
LEVEL 03
LEVEL 04
LOWER GROUND FLOOR
CAMPUS DECK
LEVEL 01
NORMAL CAMPUS HOURS
24 HOUR STUDENT / FACULTY ACCESS
98
LEARNING BRIDGE
OFFICE
COMPR. LAB
OFFICE
COMPUTER
HVAC LAB
OFFICE
COMPUTER
EP & B LAB
OFFICE
BICYCLE
COMPUTER
CONCRETE LAB
99
DIADACTIC
ROAD LAB
WORKSHOPS
MACHINE LAB
TESTING
LEARNING BRIDGE
BASE
102
BUILDING OPTIONS
103
PHASING
104
BUILDING OPTIONS
105
OPTION
106
BUILDING OPTIONS
107
The presence of the ecological corridor and the existing green areas in close proximity to the site of Building Z leaves only one solution to the landscape: minimal intervention. The strategy is to preserve the verdant surroundings; Building Z is to sit respectfully in the lush landscape.
LANDSCAPE
110
111
FACADES
PRIMARY FACADE
114
115
CAMPUS DECK FACADE
116
SERVICE FACADE
117
118
120
121
TECHNICAL
Antwerp Building Z Introduction The structure of Antwerp Building Z has been designed to be economic and quick to construct. Our key design though was to use simple reinforced concrete elements for the faรงade, internal wall and floors in a creative way so what looks to be a challenging long span building can in fact be built relatively simply. The structure can be extended in a straightforward manner as the faรงade can been designed to be removable at the junction of the later phase.
Figure.1 Antwerp Building Z structure
Stability Two stiff cores of conventional reinforced concrete walls resist wind and other horizontal forces in the first phase and work in conjunction with a further box of walls in the second. The cores move slightly inwards over the height of the building to help limit the span of the internal concrete truss. It may be possible to simplify the core walls in the final design by extending the truss.
Faรงade structure The building includes a clear 40m span at the first floor level of phase 1. This is achieved by using a load-bearing structural faรงade working in together with an internal truss (see later). Once phase 2 has been constructed the faรงade has to support another
126
STRUCTURE perpendicular wing of floors. Many different options for the faรงade structure were tested with the favoured option, a pre-cast/insitu concrete panel vierendeel frame found to have some distinct advantages. Firstly, the structure is most highly stressed in areas away from phase 2. That means that simple, detachable panels could be used in this area to allow the simple construction of the second phase.wing of floors. Many different options for the faรงade perpendicular structure were tested with the favoured option, a pre-cast/insitu concrete panel vierendeel frame found to have some distinct advantages. Firstly, the structure is most highly stressed in areas away from phase 2. That means that simple, detachable panels could be used in this area to allow the simple construction of the second phase.
Figure.2 Fixed pre-cast panel connection to slab
Figure.2 Fixed pre-cast panel connection to slab
127
Figure.3 Detachable pre-cast panel connection to slab Secondly, the adoption of a pre-cast faรงade allows for quick and accurate construction of the faรงade and avoids duplication of the faรงade support structure. Finally we have had recent experience of this type of structure in an office development in London where the entire faรงade was pre-cast in a similar way as proposed for Antwerp Building Z. This building, 40 Grosvenor Place, with HOK Architects, proved to be one of the most cost effective commercial buildings in London at that time due to the use of pre-cast concrete. We have also had experience of this form of construction on a residential building in London. The joints between the panels have to be carefully considered. Some suggestions are included within this document. We have analysed the faรงade structure and both maximum principle stress and deflection under imposed (varying load) are well within allowable limits. The design also takes into account the dynamic design criteria of offices or teaching areas with computer screens.
Internal floors The floor slabs are simple exposed reinforced concrete flat slabs. Practical alternatives to this include waffle and ribbed slabs. The
128
width of the building is too far to span using the floor slabs alone width of the building is too far to span using the floor slabs alone without the depth becoming impractically deep hence a row of without the depth becoming impractically deep hence a row of internal columns has been introduced. These split the floors into a internal columns has been introduced. These split the floors into a grid of 7.6m by 9.0m. Where the building is unsupported at ground grid of 7.6m by 9.0m. Where the building is unsupported at ground floor additional structure is needed to support the columns. There floor additional structure is needed to support the columns. There are many different options for this but the simplest, and the option are many different options for this but the simplest, and the option chosen for this scheme, was to incline the central columns and chosen for this scheme, was to incline the central columns and hence create a full height and extremely efficient triangulated truss, hence create a full height and extremely efficient triangulated truss, which is in turn supported by the reinforced concrete cores at which is in turn supported by the reinforced concrete cores at either end of the building. This idea echoes the key theme of the either end of the building. This idea echoes the key theme of the design, namely to design a striking and challenging building from design, namely to design a striking and challenging building from simple, repetitive and economic elements. simple, repetitive and economic elements.
Figure.4 view of internal truss Figure.4 view of internal truss
Below ground Below ground The basement level is to be constructed from conventional The basement level is to be constructed from conventional reinforced concrete retaining walls, columns and slab at ground reinforced concrete retaining walls, columns and slab at ground floor level. Although much of the load of the building is focused floor level. Although much of the load of the building is focused under the building cores the development is of relatively low height under the building cores the development is of relatively low height hence the concentration of forces will not be too high and simple hence the concentration of forces will not be too high and simple piled foundations (subject to a detailed investigation) will be piled foundations (subject to a detailed investigation) will be sufficient. sufficient.
Sequence Sequence of of construction construction The building is to be built in two phases with a short wing, at right The building is to be built in two phases with a short wing, at right angles to the first structure being added at a later date. One of the angles to the first structure being added at a later date. One of the guiding principles of the design was to allow this to happen in the guiding principles of the design was to allow this to happen in the context of a reinforced concrete frame. The key, as mentioned context of a reinforced concrete frame. The key, as mentioned earlier was to design a long span faรงade that was least highly earlier was to design a long span faรงade that was least highly
129
stressed in the middle of the span which could be easily removed once temporary propping had been introduced to support the structure above. The faรงade has also been designed to act as a cantilever in the temporary condition and in the permanent case once the second phase has been built. An appropriate sequence of works could be as below: 1. Construct phase 1 with faรงade panels in the zone of the second phase being designed to be easily removed. 2. Before construction of phase 2 temporarily support the slab edge and faรงade of phase 1 using conventional structural steel propping off the ground floor slab (the slab will be designed for these loads) 3. Unclip the pre-cast panels 4. Construct all of phase 2 except for the part attached to phase 1. 5. Construct the faรงade of phase 2, fixing to the phase 1 structure. 6. Construct the remainder of phase 2
01
02
03
04
05
06
07 130
Figure. 5 Sequence of construction of phases 1 and 2
Structural Analysis results
Figure. 5 Sequence of construction of phases 1 and 2
Structural Analysis results Figure.6 Distribution of Principle stresses in façade vierendeel truss – maximum principle stress 15N/mm2 Figure. 5 Sequence of construction of phases 1 and 2
Structural Analysis results Figure.6 Distribution of Principle stresses in façade vierendeel truss – maximum principle stress 15N/mm2 Figure.7 Global vertical deflection under imposed load – maximum deflection 4.22mm at mid span
Figure.6 Distribution of Principle stresses in façade vierendeel truss – maximum principle stress 15N/mm2 Figure.7 Global vertical deflection under imposed load – maximum deflection 4.22mm at mid span
Figure.7 Global vertical deflection under imposed load – maximum deflection 4.22mm at mid span
131
Figure.8 Forces within internal truss
Precedents
Figure.8 40 Grosvenor Place, London – Construction of pre-cast panel façade
132
Figure. 9 40 Grosvenor Place under construction
Figure.10 Construction details of the 40 Grosvenor Place load bearing facade 133
1. INTRODUCTION 1. INTRODUCTION For the development of the new university building, we propose a holistic approach, For the development thebuilding’s new university building, wewith propose a holistic approach, considering all phasesofthe lifecycle. Starting the phase of planning and considering all phases the building’s lifecycle. Starting with the phase of planning andof all integrating construction, operation as well as demolition and the recycling and reuse integrating construction, operation as well as demolition and the recycling and reuse of all used materials. used materials. 2. ENERGY STRATEGY 2. ENERGY STRATEGY A main target defined by the client is to reduce the energy for the operation of the building to A minimum. main target by the is tostandard reduce the energy for the operation of client. the building to a Indefined this context theclient Belgian K15 has been defined by the a minimum. In this context the Belgian standard K15 has been defined by the client. To reach this level, a four step strategy is proposed. Starting with a standard building as To reach this level, a four strategy is proposed. Starting with a standard building as baseline, the following fourstep steps of optimisation is used: baseline, the following four steps of optimisation is used: Energy concept- optimisation stratergy BASE
STEP 1
STEP 2
STEP 3
typical energy demand
optimisation of building geometry and orientation
optimisation of building envelope (passive)
optimisation of MEP
STEP 4 use of renewable energy (active)
Figure 1: Steps of optimisation Figure 1: Steps of optimisation Step 1: Optimisation of building geometry and orientation Steporientation 1: Optimisation of building geometry and orientation The of the T-shaped building is arranged due to urban design conditions. The orientation of the T-shaped building is arranged due urban design conditions. Nevertheless most parts of the façade are not shaded by to surrounding buildings (also see Nevertheless most parts of the façade are not shaded by surrounding buildings (also see chapter “shading”). The compact structure reaches a sa/vol-ratio of approximately 0,26. chapter “shading”). The compact structure reaches a sa/vol-ratio of approximately 0,26. Step 2: Optimisation of building envelope Step 2: Optimisation of building By using a highly insulated buildingenvelope shell on the level of a passive-house-standard the heat By using a highly insulated building shelltoon the level ofThe a passive-house-standard the heat losses via transmission will be reduced a minimum. air-tightness of the envelope losses via transmission reduceddoor to atest minimum. air-tightness of the .be A blower should The be carried out at the endenvelope of the should be maximum 0,7will h-1 -1 . A blower door test should be carried out at the end of the should be maximum 0,7 h construction to ensure that this targeted air tightness is respected. construction to ensure that this targeted air tightness is respected. Step 3: Optimisation of MEP Step 3: Optimisation MEPbuilding service equipment is the next step. An intelligent The optimisation of theof entire The optimisation of the entire building service the equipment is the due nexttostep. An intelligent Energy-Management-System (EMS) controls MEP system the current user Energy-Management-System (EMS) controls the MEP system due to the current userenergy conditions. Presence-, CO² - and daylight controlled management help to reduce the daylight controlled management helpMEP to reduce the energy conditions. Presence-, ² - and minimise demand. Heat recoveryCO systems the energy losses through systems. demand. Heat recovery systems minimise the energy losses through MEP systems. Step 4: Use of renewable energy Step 4: Use renewable With the first of three steps theenergy remaining energy demand will be reduced to a minimum. With the first three steps the remaining energy demand will be reduced to a minimum. 09/08/2012 09/08/2012
5/19 5/19
134
Building Z, Antwerp Building Z, Antwerp
BUILDING TECHNOLOGY AND SUSTAINABILITY The rest of the remaining demand will be covered my natural energy sources as far as possible. The ground source heat pump technology uses geothermal energy to heat, cool or booth the spaces and seems to be a viable option for the Building Z. An analysis of the soil quality in Antwerp should be carried out to ensure the effectiveness of this technology for the Building Z. If the groundwater on site is reserved for drinking water supplies (what may be the case in Antwerp), a separate water based circle for the heat pump could ensure that the water quality is not affected. The use of photovoltaic panels on the rooftop could generate electricity and cover a part of the electricity needs of the building. Surpluses go to the grid or can be stored thermally by a Summersun 61, 7°
Photovoltaics
Providing energy for building service and heat pump (grid connected)
Wintersun 14,9° Rain water collection Use for toilets & cleaning
Natural Ventilation
special automatic openings in facade offset
underfloor heating
High selectivity glass
very low g - value, high reflexion, minimum solar penetration
concrete core activation
for cooling and heating system
Heat recuvery from exaust air
efficient LED lighting all artificial lights with LED technologie, day-light and presence controlled
Ground sorce Heat Pump (Heating & Cooling)
buffer storage hot water
buffer storage could water
as natural source for regenerative heating and cooling energy via concrete core and underlay heating
geothermal energy
buffer storage feed by the heat pump. Figure 2: Overall Energy Concept
09/08/2012
6/19
135
Building Z, Antwerp
OPAQUE FACADE-
3FORM FACADE PANNEL INSULATION SUBCONSTRUCTION CONCRETE WALL TOTAL U VALUE <0.15W/m <k
NATURTAL VENTIALTION-
automated ventilation openings night cooling and individual vantilation invisuble on facade
UNDERFLOOR HEATING
TRANSPARENT FACADE-
triple Glazing ( with additional 3 form layer u value glas ( glas + frame ) < 0,9W/M<k g value : 0.35 facade offset: 600 mmno external schading internal sun shild recommended
CONCRETE CORE ACTIVATION- heating & cooling- no suspended ceiling- instalations in double floor
Figure 3: section facade
09/08/2012
7/19
136
Building Z, Antwerp
3.
ENERGY CONSUMPTION FOR HEATING
3.1.
PHVP (simplified PHPP tool)
To prove the possible achievement of the K15 standard a simplified calculation with the tool PHVP (provided by the German Passive-House institute) was realised. This tool uses the similar methodology like the tool PHPP (commonly used in Belgium), but offers a simplified data input for preliminary planning phases. 3. ENERGY CONSUMPTION FOR HEATING For the calculation the building envelope was used as shown below. For thisPHVP calculation just one underground level was integrated in the data model. All the 3.1. (simplified PHPP tool) facades are of the same type with a glazing ratio of 33%. To prove the possible achievement of the K15 standard a simplified calculation with the tool PHVP (provided by the German Passive-House institute) was realised. This tool uses the similar methodology like the tool PHPP (commonly used in Belgium), but offers a simplified data input for preliminary planning phases. For the calculation the building envelope was used as shown below. For this calculation just one underground level was integrated in the data model. All the facades are of the same type with a glazing ratio of 33%.
Figure 4: Building geometry used for calculation
The results of this calculation are shown in the following table and also in Appendix A. (Note: This calculation is a first estimation for competition stage. Detailed calculations need to be carried out in further steps.) Table 5 : calculation results and assumed data:
netto energy demand forused heating: Figure 4: Building geometry for calculation
<15
kWh/m²a
The results of this calculation are shown in the following table and also in Appendix A. assumed and u-values: (Note: Thisdata calculation is a first estimation for competition stage. Detailed calculations need External wall 0,15 W/m²K to be carried out in further steps.) Roof 0,15 W/m²K Basement top 0,15 W/m²K Windows u-value results and assumed data: 0,9 W/m²K Table 5 : calculation g-value 0,35 netto energy demand for heating: <15 kWh/m²a heat recovery from exhaust air 80 % internal heat source (value for office 3,5 W/m² build.) assumed data and u-values: External wall Roof Basement top Windows u-value g-value 09/08/2012 heat recovery from exhaust air internal heat source (value for office build.)
0,15 0,15 0,15 0,9 0,35 8/19 80 3,5
137
W/m²K W/m²K W/m²K W/m²K % W/m²
Building Z, Antwerp
4.
SHADING
Figure 6: Shadow Range- Top View, June 21st
Figure 7: Shadow Range â&#x20AC;&#x201C; Top View , December 21st
09/08/2012
9/19
138
Building Z, Antwerp
Figure 8: Shadow range June 21st, perspective view Figure 8: Shadow range June 21st, perspective view
Figure 9: Shadow range 21st Dec, perspective view Figure 9: Shadow range 21st Dec, perspective view
139
5.
SUMMER INSULATION & OVERHEATING
Summer overheating is an important issue in office and university building and labs. To prove that temperature is not going over a tolerable value a calculation according to DIN 4108 was carried out. This calculation showed that due to the relatively small glazing ratio (33%), the façade offset and by using a g-value of 0,35 there is no need of an external shading device (as preferred by the architects, a shading device on the inside is highly recommended though). However, this calculation only shows that temperatures are tolerable. To get a detailed impression of the temperature in terms of comfort a thermal simulation needs to 5. SUMMER INSULATIONdevelopment & OVERHEATING be carried out in later planning stages. Summer overheating is an important issue in office and university building and labs. For the calculation two spaces/zones in the top storey, facing south were reviewed. One To prove4x5 thatgrid temperature is not going a tolerable value calculation to DIN defining axis as a “space” and over a second defining 2x2agrid axis as aaccording closed “space”. 4108 was carried out. Detailed calculation steps can be found in Appendix B. This calculation showed that due to the relatively small glazing ratio (33%), the façade offset and by using a g-value of 0,35 there is no need of an external shading device (as preferred by the architects, a shading device on the inside is highly recommended though). However, this calculation only shows that temperatures are tolerable. To get a detailed impression of the temperature development in terms of comfort a thermal simulation needs to be carried out in later planning stages. For the calculation two spaces/zones in the top storey, facing south were reviewed. One defining 4x5 grid axis as a “space” and a second defining 2x2 grid axis as a closed “space”. Detailed calculation steps can be found in Appendix B.
Figure 10: Reviewed zones for summer overheating; (left: area with 4x5 grid axis; right: 2x2 grid axis)
Figure 10: Reviewed zones for summer overheating; (left: area with 4x5 grid axis; right: 2x2 grid axis)
09/08/2012
11/19
140
Building Z, Antwerp
6.
PHOTOVOLTAIKS
With the available roof surface of 2166 m² and 1000 solar modules (each 200 W) the local conditions could generate an annual output of ca. 176900 kWh/a. This output could already serve a significant part of the expected electricity demand. net estimated annual PV - output:
191141.8 kWh/a
January
4056.6 kWh;
February
7570.3 kWh;
March
14845.1 kWh;
April
21986.7 kWh;
May
27049.5 kWh;
June
28375.1 kWh;
July
26084.7 kWh;
August
23909.4 kWh;
September
18720.6 kWh;
October
10908.2 kWh;
November
4774.4 kWh;
December
2861.4 kWh;
gross estimated annual output (to grid):
176924.8 kWh/a
Calculation basis: 1000 x 200.00 W = 200.00 kWp Solar module: Bosch · c-Si M 48 - M200 Roof surface: ca. 2166 m²; Module surface: ca. 1340 m², inclination 30° azimuth 0°, no shading ,
Local climate data for Antwerp see Appendix C
09/08/2012
12/19
141
Building Z, Antwerp
7.
MATERIALS, RECYCLING & REUSE
7.1.
Design for Recycling
To fulfil a holistic life cycle approach the demolition has to become an integrated part of the planning process. After the operation phase as many parts of the building as possible should be reused or recycled. Therefore the planners have to think about possible conversions from an early planning stage on. In terms of construction the following â&#x20AC;&#x153;design for recycling principlesâ&#x20AC;? should be addressed:
Design for recycling- main principles Use of recycle materials Use of demoountable joints Reduction of variety of substances Figure 11: DFR principles Recycling compatible groups of materials
Docu
Documentation of materials and recycling pathways
figure 11: principles
09/08/2012
13/19
142
Building Z, Antwerp
7.2.
Material cycles
For all materials used a recycling process in the technical or biological cycle (according to the cradle to cradle principles) should be possible, as shown on the figure below:
raw material
7.2.
dary secon ck feedsto
Material cycles
ial raw mater ain grows ag
material
treatmen t
cycle
biological cycle
technical cycle
cycle
util isat ion
7.3.
withrdawl, disassembly
demolition deconstruction
deg ener atio n
technical cycle
cycle
etic
gical
cycle
energ
biolo
For all materials used a recycling process in the technical or biological cycle (according to product the cradle to cradle principles) should be possible, as shown on the figure below: use materialproductproductmaterial-
withrdawl, disassembly
biological cycle
Material choice
During detailed planning and construction phases, the following process for the choice of the materials should be addressed, in order to ensure a successful recycling process for all substances used in the construction. technical cycle
7.3.
biological cycle construction - task
Material choice
During detailed planning andNO construction phases, the following process for the choice of the basic material materials should be addressed, in order to ensurerecycable a successful recycling process for all ? substances used in the construction. YES
substitution by secondary feedstock
YES BUILT !
YES
mono material element ?
NO
Figure 12: Process for the choice of materials YES
recycling compatible components?
NO divide into recycling compatible components
09/08/2012
14/19
Figure 12: Process for the choice of materials
143
Building Z, Antwerp
144
9.
APPENDIX B - Summer Overheating, Calculated with DIN 4108
1. Nachweis für Raum "2. Example Space, OG, 2x2, Corner"
Erfassungsdaten Zone: Raum: Grundfläche Ag: Außenwandfläche AAW: Dach- o. Deckenfläche AD:
Einzelbüro 2. Example Space, OG, 2x2, Corner 57,76 m² 50,40 m² -
Fenster: Nr. Bezeichnung 1 Fenster 2 Fenster O
Orientierung Neigung > 60° > 60°
Fc * 1 1
Sonnensch utz permanent nein nein
g
gtotal
Fläche [m²]
0,35 0,35
0,350 0,350
7,20 7,20
Berechneter Sonneneintragskennwert
0,087
Maximal zulässiger Sonneneintragswert
Zuschlagswerte: Klimaregion Gebäudebauart Nachtlüftung Sonnenschutzverglasung Fensterneigung Orientierung
( Klimazone C - sommerheiß ) ( mittlere Bauart - 50 bis 130 Wh/(Km²) ) ( Nein ) ( Ja )
Maximal zulässiger Sonneneintragskennwert
: : : : : :
:
0,015 0,051 0,000 0,030 0,000 0,000 0,096
Ergebnis Anforderung erfüllt !
09/08/2012
0,087 < 0,096
17/19
145
Building Z, Antwerp
APPENDIX B - Summer Overheating, Calculated with DIN 4108
2. Nachweis für Raum "1. Example Space, OG 4x5 Grid fields" Erfassungsdaten Zone: Raum: Grundfläche Ag: Außenwandfläche AAW: Dach- o. Deckenfläche AD:
Einzelbüro 1. Example Space, OG 4x5 Grid fields 288,80 m² 163,80 m² -
Fenster: Nr. Bezeichnung 1 Fenster S 2 Fenster O 3 Fenster W
Orientierung Neigung > 60° > 60° > 60°
Fc * 1 1 1
Sonnensch utz permanent nein nein nein
g
gtotal
Fläche [m²]
0,35 0,35 0,35
0,350 0,350 0,350
18,00 14,40 14,40
Berechneter Sonneneintragskennwert
0,057
Maximal zulässiger Sonneneintragswert Zuschlagswerte: Klimaregion Gebäudebauart Nachtlüftung Sonnenschutzverglasung Fensterneigung Orientierung
( Klimazone B - gemäßigt ) ( mittlere Bauart - 50 bis 130 Wh/(Km²) ) ( Nein ) ( Ja )
Maximal zulässiger Sonneneintragskennwert
: : : : : :
:
0,030 0,033 0,000 0,030 0,000 0,000 0,093
Ergebnis Anforderung erfüllt !
0,057 < 0,093
* Legende: Fc = Sonnenschutzfaktor Fc = 1 - Ohne Sonnenschutzvorrichtung Innenliegend und zwischen den Scheiben : Fc = 0,75 - weiß oder reflektierende Oberfläche und geringe Transparenz Fc = 0,80 - helle Farben und geringe Transparenz Fc = 0,90 - dunkle Farben und höhere Transparenz Außenliegend : Fc = 0,25 - drehbare Lamellen bzw. Jalousien u. Stoffe geringer Transp., hinterlüftet Fc = 0,30 - Rolläden, Fensterläden Fc = 0,40 - Jalousien (allgemein) bzw. Markisen (oben und seitlich ventiliert) Fc = 0,50 - Markisen (allgemein) bzw. Vordächer, Loggien, freistehende Lamellen g = Durchlassgrad Verglasung g total = Gesamtdurchlassgrad
09/08/2012
18/19
146
Building Z, Antwerp
10.
APPENDIX C - Climate data , Antwerp
Calculation (hour) Name of site = Antwerp (Anvers) BE Latitude [°] = 51,220, Longitude [°] = 4,420, Altitude [m] = 10 Climatic zone = III, 2 Radiation model = Default (hour); Temperature model = Default (hour) Tilt radiation model = Perez Temperature: New period = 1996-2005 Radiation: New period = 1981-2000 Month Ta
RH
Bh
H_Gh H_Dh FF
DD
N
RR
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
3,8 5,1 7,4 10,1 14,2 17,0 18,3 19,1 15,7 11,5 7,1 4,2
84 80 78 70 70 69 73 73 77 80 85 85
7 13 24 43 64 65 62 61 39 21 8 3
20 36 69 108 145 149 149 132 87 53 25 15
14 23 46 65 81 85 87 71 48 32 17 12
3,6 3,8 3,3 3,1 3,0 3,0 2,8 2,4 2,6 3,3 3,1 3,4
216 191 225 211 201 234 258 251 222 191 218 218
7 6 6 6 5 5 6 5 6 6 7 7
63.0 49.0 37.0 36.0 47.0 38.0 66.0 76.0 65.0 56.0 64.0 68.0
Year
11,1
77
409
988
580
3,1
218
6
665.0
Legend: H_Gh: H_Dh: Ta: RH: N: FF: DD: H_Bh: RR:
Irradiation of global radiation horizontal Leg_H_Dh Air temperature Relative humidity Cloud cover fraction Wind speed Wind direction Irradiation of direct radiation horizontal Precipitation
Radiation in [kWh/m2 m] Temperature in [°C] Pressure in [hPa] Wind speed in [m/s] Luminance in [ lux ] Nearest 3 stations: Gh: Melle (49 km), Uccle (47 km), Vlissingen (63 km) Nearest 3 stations: Ta: ANTWERP/DEURNE (4 km), WOENSDRECHT RNLAFB (26 km), GENT/INDUSTRY ZONE (43 km)
09/08/2012
19/19
147
Building Z, Antwerp
LAB OPTION 01
LAB OPTION 02
148
LAB
LAB OPTION 03
LAB OPTION 04
149
B3 W.673 Lab Antwerpwen budgetraming bouwkundig datum: 10 augustus 2012 Elementcluster
hoev. eenh.
p.p.e.
totale kosten
per m² BVO
per m³ BGI
In % tov elementen (11) t/m (76)
35,00 15,00 5.500,00 275,00 250,00 115,00 115,00
74.881 129.415 11.000 388.035 182.000 83.767 162.269 1.031.367
13,14 22,70 1,93 68,08 31,93 14,70 28,47 180,94
3,39 5,85 0,50 17,55 8,23 3,79 7,34 46,64
0,8% 1,4% 0,1% 4,2% 2,0% 0,9% 1,8% 11,2%
150,00 235,00 205,00 125,00 115,00 105,00 175,00 4,25
311.523 140.937 88.494 37.500 894.835 42.251 176.339 222.496
54,65 24,73 15,53 6,58 156,99 7,41 30,94 39,03
14,09 6,37 4,00 1,70 40,47 1,91 7,97 10,06
3,4% 1,5% 1,0% 0,4% 9,7% 0,5% 1,9% 2,4%
1.914.375
335,85
86,57
20,8%
8,11 23,50 9 60 9,60 9,98 51,18
2,09 6,06 2 47 2,47 2,57 13,19
50,3% 1,5% 0 6% 0,6% 0,6% 52,9%
70,76 37,29 7,89 3,95 1,19 91,09 9,80 2,63 8,78 233,39
18,24 9,61 2,03 1,02 0,31 23,48 2,53 0,68 2,26 60,16
4,4% 2,3% 0,5% 0,2% 0,1% 5,6% 0,6% 0,2% 0,5% 13,2%
NL/SfB Omschrijving 2 2A
2B
2C
2D
2E
2F
2G
(11) (11) (16) (16) (16) (17) (17)
BOUWKUNDIGE WERKEN Fundering Bodemvoorzieningen algemeen Grondwerk ontgraven Funderingsconstructies overig: liftput Funderingsconstructies op staal 600 dik geisoleerd Funderingsconstructies buiten op staal 600 dik Paalfunderingen aanname (hellingbaan en put) Paalfunderingen aanname (gebouw) Totaal fundering
(21) (21) (21) (23) (23) (27) (28) (28) (38) (48)
Skelet Constr. binnenspouwblad bruto oppervlak kelderwand beton 500 geisoleerd kelderwand buiten beton 500 Hellingbaanvloer Verdiepingsvloeren (constructief) Daken (constructief) Hoofddraagconstructies kern beton 300 dik Hoofddraagconstructies staal aanname Inbouwpakketten Afwerkingspakketten Totaal skelet
(27) (37) (47) (47) (47)
Daken Dakafbouwconstructies: luifel hoofdentree Dakopeningen glasdak vide 4/5e verd. Dakafwerkingen entree D k f Dakafwerkingen ki 4 4e verd d Dakafwerkingen platte daken Totaal daken
(21) (31) (31) (31) (31) (41) (41) (41) (41) (41)
Gevels Buitenwandafbouwconstructies Buitenwandopeningen gevelkozijnen Buitenwandopeningen vliesgevel Buitenwandopeningen tourniquet Buitenwandopeningen toeslag garaged. 5x5 Buitenwandafwerking om techn. Ruimte/liftschacht Buitenwandafwerkingen buitenblad panelen Buitenwandafwerkingen buitenbl. Terras 4e Buitenwandafwerkingen buitenblad betonbak. Buitenwandafwerkingen buitenblad beeindiging hor. Totaal gevels
(22) (32) (42)
Binnenwanden Binnenwanden niet constructief bruto Binnenwandopeningen (glaswand t.p.v. viden) Binnenwandafwerkingen Totaal binnenwanden
(23) (33) (33) (43) (43)
Vloeren Vloerafbouwconstructies Vloeropeningen, begane grond Vloeropeningen, verdiepingen Vloerafwerkingen, kelder: hellingbaan Vloerafwerkingen, kelder: buiten toeslag Totaal vloeren
(24) (24) (24) (34) (34) (34)
Trappen en hellingen Trappen en hellingen: noodtrap Trappen en hellingen: hoofdtrap Trappen en hellingen: hellingen fietsenberging Balustrades en leuningen trappen Balustrades en leuningen viden buiten Balustrades en leuningen viden Totaal trappen en hellingen
2.139 8.628 2 1.411 728 728 1.411
2.077 600 432 300 7.781 402 1.008 52.352
m² m³ pst m² m² m²BO m²BO
m² m² m² m² m² m² m² kg pst pst
71 864 476 813
excl. m² m² m²² m²
650,00 155,00 115 00 115,00 70,00
46.202 133.937 54 692 54.692 56.911 291.742
645 386 3 3 34 2.077 447 300 334
m² m² stuks stuks m² m² m² m² m²
625,00 550,00 15.000,00 7.500,00 200,00 250,00 125,00 50,00 150,00
403.357 212.546 45.000 22.500 6.768 519.205 55.884 15.018 50.030 1.330.307
806 m²
405 460 300 428
m² m² m² m² m²
excl. 9 verd. 4 st incl. 122 m 50 m
150
475,00
35,00 55,00 85,00 155,00
6.500,00 5.000,00 450 00 450,00 450,00
382.722 382.722
67,14
17,31
4,2%
67,14
17,31
4,2%
14.160 25.300 25.500 66.340 131.301
2,48 4,44 4,47 11,64 23,04
0,64 1,14 1,15 3,00 5,94
0,2% 0,3% 0,3% 0,7% 1,4%
58.500 20.000
10,26 3,51
2,65 0,90
0,6% 0,2%
54 720 54.720 22.320 155.540
9 60 9,60 3,92 27,29
2 47 2,47 1,01 7,03
0 6% 0,6% 0,2% 1,7% 1/5
COST W.673 Lab Antwerpwen budgetraming bouwkundig datum: 10 augustus 2012 Elementcluster
hoev. eenh.
p.p.e.
totale kosten
NL/SfB Omschrijving
2H
3B
3C
per m³ BGI
In % tov elementen (11) t/m (76)
(45) (45) (45) (45)
Plafonds Plafondafwerkingen binnen niet verlaagd Plafondafwerkingen binnen verlaagd Plafondafwerkingen buiten 4e verd (overdekt) Plafondafwerkingen buiten entree (overdekt) Totaal plafonds
in afwerkpakket in afwerkpakket 66 m² 150,00 864 m² 275,00
9.853 237.630 247.483
1,73 41,69 43,42
0,45 10,75 11,19
0,1% 2,6%
(38) (38) (38) (38) (38) (38) (38) (38) (38) (38) (38) (38) (38) (48)
Inbouwpakketten Afwerkingspakketten Kantoren Afwerkingspakketten Conrete lab Afwerkingspakketten Road Construction lab Afwerkingspakketten EP&B lab Afwerkingspakketten Lab HVAC & Compression Afwerkingspakketten Workshops Afwerkingspakketten Machinery / Storage Afwerkingspakketten Didactic labs Afwerkingspakketten leslokalen Afwerkingspakketten Computerlabs Afwerkingspakketten algemene verkeers ruimten Afwerkingspakketten algemene ruimten overig Afwerkingspakketten fietsenstalling Afwerkingspakketten sanitaire units Totaal inbouwpaketten
577 190 260 100 550 200 400 250 300 720 749 274 262 170
129.825 28.500 39.000 17.500 96.250 35.000 40.000 43.750 52.500 126.000 205.975 45.210 26.200 55.250 940.960
22,78 5,00 6,84 3,07 16,89 6,14 7,02 7,68 9,21 22,11 36,14 7,93 4,60 9,69 165,08
5,87 1,29 1,76 0,79 4,35 1,58 1,81 1,98 2,37 5,70 9,31 2,04 1,18 2,50 42,55
1,4% 0,3% 0,4% 0,2% 1,0% 0,4% 0,4% 0,5% 0,6% 1,4% 2,2% 0,5% 0,3% 0,6% 10,2%
6.425.797
1.127,33
290,59
69,9%
95.205 222.250 595.000 107.651 -
16,70 38,99 104,39 18,89
4,31 10,05 26,91 4,87
1,0% 2,4% 6,5% 1,2%
1.020.106
178,97
46,13
11,1%
129.825 285.750 782.000 215.302 -
22,78 50,13 137,19 37,77
5,87 12,92 35,36 9,74
1,4% 3,1% 8,5% 2,3%
247,87
63,89
15,4%
m² m² m² m² m² m² m² m² m² m² m² m² m² m²
225,00 150,00 150,00 175,00 175,00 175,00 100,00 175,00 175,00 175,00 275,00 165,00 100,00 325,00
TOTAAL BOUWKUNDIGE WERKEN
3 3A
per m² BVO
(50) (50) (50) (50) (50) (52) (53) (54) (55) (56) (57) (58) (59)
INSTALLATIES Werktuigbouwkundig Werktuigbouwkundig kantoor functie Werktuigbouwkundig onderwijs functie Werktuigbouwkundig lab functie Werktuigbouwkundig algemene ruimten Werktuigbouwkundig facade gevel Afvoeren Water Gassen Koude-opwekking en distributie Warmtedistributie Luchtbehandeling Regeling klimaat en sanitair Sprinkler Totaal werktuigbouwkundig
(60) (60) (60) (60) (60) (61) (62) (63) (64) (65) (67)
Elektrotechnisch Elektrotechnisch kantoor functie Elektrotechnisch onderwijsfunctie Elektrotechnisch lab functie Elektrotechnisch algemene ruimten Elektrotechnisch facade gevel Centrale elektrotechnische voorzieningen Krachtstroom Verlichting Communicatie Beveiliging Gebouwbeheersvoorzieningen Totaal elektrotechnisch
(66) (66) (66)
Lift en transport Transport: liftinstallatie basis Transport: liftinstallatie toeslag per stopplaats Transport: goederenlift Totaal lift en transport
577 1.270 1.700 2.153
577 1.270 1.700 2.153
m²bvo m²bvo m²bvo m²bvo m²bvo incl incl incl incl incl incl incl incl
165,00 175,00 350,00 50,00
m²bvo m²bvo m²bvo m²bvo m²bvo incl incl incl incl incl incl
225,00 225,00 460,00 100,00
2 st 11 st excl.
TOTAAL INSTALLATIES
151
-
1.412.877 45.000,00 1.000,00
90.000 11.000 101.000
15,79 1,93
4,07 0,50
1,0% 0,1%
17,72
4,57
1,1%
2.533.982
444,56
114,59
27,6%
2/5
B3 W.673 Lab Antwerpwen budgetraming bouwkundig datum: 10 augustus 2012 Elementcluster
hoev. eenh.
p.p.e.
totale kosten
per m² BVO
per m³ BGI
In % tov elementen (11) t/m (76)
234.000
41,05
10,58
2,5%
234.000
41,05
10,58
2,5%
9.193.779
1.612,94
415,76
100,0%
27.038 10.000 38.080 21.760
4,74 1,75 6,68 3,82
1,22 0,45 1,72 0,98
0,3% 0,1% 0,4% 0,2%
96.878
17,00
4,38
1,1%
9.290.657
1.629,94
420,14
101,1%
NL/SfB Omschrijving 4 4A (71) (72) (73) (74) (75) (76)
VASTE INRICHTINGEN Vaste verkeersvoorzieningen Vaste gebruikersvoorzieningen Vaste keukenvoorzieningen Vaste sanitaire voorzieningen Vaste onderhoudsv: gevelreinigingsinst. Vaste opslagvoorzieningen Totaal vaste inrichtingen
excl. excl. excl. incl 1 pst. excl.
234.000,00
Totaal elementen (11) t/m (76) 5 5A (90) (90) (90) (90) (90) (90) (90) (90) (90)
TERREIN Grondvoorzieningen Opstallen Omheiningen Terreinafwerkingen; bestrating op grond Terreinvoorzieningen; verw. Hellingbaan Terreinvoorzieningen; werktuigkundig Terreinvoorzieningen; elektrotechnisch Terreininrichtingen; standaard Terreininrichtingen; bijzonder Totaal terrein
361 1 1.088 1.088
Totaal directe projectvoorzieningen (11) t/m (90) 6 (0-)
excl. excl. excl. m² pst m² m² excl. excl. proj
75,00 10.000,00 35,00 20,00
INDIRECTE VOORZIENINGEN Onvoorzien Algemene bouwplaatskosten Algemene kkosten Al t Winst en Risico CAR-verzekering Prijsstijging tot start bouw Afkoop tijdens de bouw
8,50% 5 00% 5,00% 2,00% 0,30% excl. excl.
789.706 504 018 504.018 211.688 32.388
138,54 88 42 88,42 37,14 5,68
35,71 22,79 22 79 9,57 1,46
8,6% 5,5% 5 5% 2,3% 0,4%
TOTAAL BOUWKUNDIG GEBOUW INCL. TERREIN (excl. BTW)
10.828.457
1.899,72
489,68
117,8%
TOTAAL BOUWKUNDIG GEBOUW EXCL. TERREIN (excl. BTW)
9.990.163
1.752,66
451,78
116,5%
m² bvo totaal m³ bgi totaal
5.700 m² 22.113 m³
exclusief: - btw - losse en vaste inrichting - terreininrichting - bijkomende kosten: honoraria, leges onderzoekskosten e.d.
152
3/5
W.673 Lab Antwerpwen budgetraming bouwkundig datum: 10 augustus 2012 Elementcluster
hoev. eenh.
p.p.e.
totale kosten
NL/SfB Omschrijving
per m² BVO
per mÂł BGI
In % tov elementen (11) t/m (76)
35,84
9,24
2,2%
101,94 43,16 94,90
26,28 11,13 24,46
6,3% 2,7% 5,9%
163,57 13,77 7,41 69,97 119,89 67,14 6,92 13,52 8,11 155,39 113,49
42,16 3,55 1,91 18,04 30,90 17,31 1,78 3,48 2,09 40,05 29,25
10,1% 0,9% 0,5% 4,3% 7,4% 4,2% 0,4% 0,8% 0,5% 9,6% 7,0%
16,11
4,15
1,0%
43,42 43,08 9,69 178,97
11,19 11,10 2,50 46,13
2,7% 2,7% 0,6% 11,1%
247,87
63,89
15,4%
17,72
4,57
1,1%
41,05
10,58
2,5%
17,00
4,38
Tabel naar elementen, algemeen (10) (11) (13) (16) (17) (21) (22) (23) (24) (27) (28) (31) (32) (33) (34) (37) (38) (41) (42) (43) (44) (45) (47) (48) (50) (51) (52) (53) (54) (55) (56) (57) (58) (60) (61) (62) (63) (64) (65) (66) (67) (71) (72) (73) (74) (75) (76) (90)
Sloopwerk Bodemvoorzieningen Vloeren op grondslag Funderingsconstructies Paalfunderingen Buitenwanden Binnenwanden Vloeren, galerijen Trappen en hellingen: hoofdtrap Daken Hoofddraagconstructies Buitenwandopeningen gevelkozijnen Binnenwandopeningen Vloeropeningen Balustrades en leuningen Dakopeningen Inbouwpakketten Buitenwandafwerkingen Binnenwandafwerkingen Vloerafwerkingen Trap- en hellingafwerkingen Plafondafwerkingen Dakafwerkingen Afwerkingspakketten Werktuigbouwkundig totaal Warmte-opwekking Af Afvoeren Water Gassen Koude-opwekking en distributie Warmtedistributie Luchtbehandeling Regeling klimaat en sanitair Elektrotechnisch totaal Centrale elektrotechnische voorzieningen Krachtstroom Verlichting Communicatie Beveiliging Liften en transport Gebouwbeheersvoorzieningen Vaste verkeersvoorzieningen Vaste gebruikersvoorzieningen Vaste keukenvoorzieningen Vaste sanitaire voorzieningen Vaste onderhoudsvoorzieningen Vaste opslagvoorzieningen Terrein
204.295 581.035 246.036 540.954 932.335 78.500 42.251 398.835 683.403 382.722 39.461 77.040 46.202 885.710 646.904 91.840 247.483 245.540 55.250 1.020.106 1.412.877 101.000 234.000 96.878
Totaal directe projectvoorzieningen (11) t/m (90)
9.290.657
153
1.629,94
420,14
100%
4/5
B3 W.673 Lab Antwerpwen budgetraming bouwkundig datum: 10 augustus 2012 Elementcluster
hoev. eenh.
p.p.e.
totale kosten
per m² BVO
per mÂł BGI
In % tov elementen (11) t/m (76)
Sloopwerk Onderbouw Bovenbouw Afbouw Afwerkingen Totaal elementen (11) t/m (48)
1.031.367 1.992.875 1.151.787 2.249.768 6.425.797
180,94 349,63 202,07 394,70 1.127,33
46,64 90,12 52,09 101,74 290,59
11,2% 21,7% 12,5% 24,5% 69,9%
Werktuigbouwkundig installaties Elektrotechnisch installaties Vaste inrichtingen Totaal elementen (11) t/m (76)
1.020.106 1.513.877 234.000 9.193.779
178,97 265,59 41,05 1.612,94
46,13 68,46 10,58 415,76
11,1% 16,5% 2,5% 100,0%
Terrein Totaal directe projectvoorzieningen (11) t/m (90.8)
96.878 9.290.657
415,76
105,4% 205,4%
NL/SfB Omschrijving
Tabel naar elementengroepen, algemeen
1.612,94
Tabel naar elementengroepen, functioneel Sloopwerk Lokatievoorzieningen Funderingen Vloeren Gevels Bi Binnenwanden d Trappen Daken Bouwkundig overig Totaal bouwkundig
450.332 581.035 1.311.119 1.871.262 382 722 382.722 155.540 333.993 1.339.795 6.425.797
79,01 101,94 230,02 328,29 67 14 67,14 27,29 58,60 235,05 1.127,33
20,36 26,28 59,29 84,62 17 31 17,31 7,03 15,10 60,59 290,59
4,9% 6,3% 14,3% 20,4% 4 2% 4,2% 1,7% 3,6% 14,6% 69,9%
Werktuigbouwkundig installaties Elektrotechnisch installaties Vaste inrichtingen Totaal elementen (11) t/m (76)
1.020.106 1.513.877 234.000 9.193.779
178,97 265,59 41,05 1.612,94
46,13 68,46 10,58 415,76
11,1% 16,5% 2,5% 30,1%
Terrein Totaal directe projectvoorzieningen (11) t/m (90.8)
96.878 9.290.657
1.612,94
415,76
105,4% 135,5%
154
5/5
COST SUMMARY W.673 Lab Antwerpwen budgetraming bouwkundig datum: 10 augustus 2012 TOEVOEGING VAN OPTIONEEL DEEL AAN BASIS PROJECT
uitgangspunt Voor de bouwkosten van de uitbreiding is de m2 BVO prijs van de het basis gebouw gehanteerd.
optie uitbreiding ten tijde van basisgebouw Kosten uitbreiding minderkosten aansluitgevel minderkosten gevelkozijnen minderkosten betonnen keerwand in kelder Totaal kosten uitbreiding ten tijde van basisgebouw
m2 BVO m2 m2 m2
à à à à
1.752,66 400,00 625,00 235,00
5.406.591 32.00010.00039.950€ 5.324.640,54
3084,8 m2 BVO
à
1.752,66
5.406.591 50.000 35.000 20.000 200.000 10.000 114.432 € 5.836.022,35
3084,8 -80 -16 -170
Voordeel: bouwtijd wordt bijna niet langer. geen sloopkosten optie uitbreiding na voltooiing basisgebouw kosten uitbreiding extra kosten stabilisatie bestaand gebouw extra kosten sloopwerk kelderwanden en gevel extra kosten waterdicht maken kelderniveau extra bouwtijd met bouwplaatsinrichting extra kosten afscherming en waterdicht maken prijsstijgingen 2% tgv latere start bouw Totaal kosten uitbreiding ten tijde van basisgebouw Nadeel: Bijna verdubbeling van bouwtijd en bijbehorende kosten overlast huidige gebruikers
155
Clusters
1. LAB TOWER
Space description
Space
Netto
Research lab for concrete and concrete production Research lab for concrete and cement -mortar lab Research lab for experimental concrete lab Research lab for road construction ans asphalt production area
3.3.9 3.3.10 3.3.11 3.3.12
40 30 80 40 190
Building Z
Bruto
190
64 48 128 64 304
260
112 128 48 16 112 416
100
32 128 160
550
312 390 13 715
200
80 48 48 128 16 320
Concrete lab
Road Construction lab Research lab road concrete - investigation area Research lab for road construction and asphalt experimentals Research lab for road construction and RHEO Research lab for road construction and recycle Research lab road construction - investigation area
3.3.24 3.3.13 3.3.14 3.3.15 3.3.25
70 80 30 10 70 260
EP&B lab Research lab for EP&B storage area and measurement Research lab EP&B - investigation area Lab HVAC & Compression Lab pumps compressors and turbines Lab HVAC Technical area (compressiond gases)
3.3.16 3.3.26
3.3.1 3.3.2 3.3.20
20 80 100 240 300 10 550
Workshops Workshop area and soil storage Workshop area weigh and drying zone Workshop sifting chamber Workshop klimate area Workshop storage and topography room
3.3.4 3.3.5 3.3.6 3.3.7 3.3.8
Machinery / Storage Lab materials and machinery Storage area
2. OFFICE TOWER
400 1700 LAB
3.3.21
20
20
32
Offices
Offices EM Offices BK
3.3.23 3.3.27
340 102
442
88 544
Meeting room / bib1 Project and meeting room 1 Project and meeting room 2 Project and meeting room 3
3.3.22 3.3.29 3.3.29 3.3.29
55 20 20 20 577
115 577 OFFICE
Didactic lab - PC analysis chamber Didactic lab - didactic chamber
3.3.17 3.3.18
25 225
250
40 360
Classroom-1 Classroom-2 Classroom-3
3.3.28 3.3.28 3.3.28
100 100 100
300
160 160 160
Computerlab-1 Computerlab-2 Computerlab-3 Computerlab-4 Computerlab-5 Computerlab-6 Computerlab-7 Office helpdesk employee
3.3.30 3.3.30 3.3.30 3.3.30 3.3.30 3.3.30 3.3.30 3.3.31
100 100 100 100 100 100 100 20 1270
Classrooms
Computerlabs
NETTO TOTAL Services
Entrance Circulation space Sanitary Sanitary disabled Network aggregration point Central heating installations Ventilation groups Main storage cleaning Storage cleaning Elevators
Construction
Walls Colomns Stairs TOTAL
3547 3.4.1 3.4.2 3.4.3 3.4.4 3.4.5 3.4.2 3.4.7 3.4.8 3.4.9 3.4.10
OPEN SPACES
x x x x x x x x x x x x x 1843,2
BRUTO TOTAL BASE
720 1270 LEARNING
3547
5. LAB TOWER
3.5.1 3.5.2 3.5.3
260 30 30
Robot lab
3.6.1
210
273
Lab vision
3.6.2
100
160
Lab electricity
3.6.3
90
117
Lab electricity machines
3.6.3
350
455 640
Lab automation
3.6.4
400
Lab automotive
3.6.5
300
390
Lab polytechnic 1
3.6.7
150
240
Lab polytechnic 2
3.6.7 3.6.8
TOTAL
1805
3.7.1
x
185
3.7.2 3.7.3
x x
incl. in sanitary
Network aggregation point
x
18
x
55
Elevator + stairs
x
117
x 798
2603
Automotive test vehicles
3.8.1
TOTAL PROJECT incl. Open spaces
88
85
Storage cleaning
BRUTO TOTAL OPTION OPEN SPACES
1805
Circulation space
Structure TOTAL
2515 88
55 LEARNING
Sanitary Sanitary disabled
Services
240 1750 LAB
55 55
NETTO TOTAL Services
150 1750
Meeting rooms
3. SERVICES
5390,2
5770,2
TOTAL
6. LEARNING
160 160 160 160 160 160 160 32 2032
642,2 8 105 1843,2 SERVICES
5390,2 5390,2
Bicycle storage Garbage zone // building rest Zone for garbage containers // garbage, paper . PMD
163,2 32 32 32 923,2
100 508 170 incl. in sanitary 36 17 10 117 incl. in main storage 130
TOTAL PROJECT incl. Open spaces
7. SERVICES
390 130 520 2435
Secretariat entrance // warehouse -Z
Didactic labs
4. SERVICES
300 100 400 1700
Secretariat
Meetingrooms
3. LEARNING
3.3.19 3.3.3
50 30 30 80 10 200
338 798 SERVICES
2603
2603 75 2678
156
PROGRAM SUMMARY
1. LABS 1700 M2
2. OFFICES 577 M2
3. LEARNING 1270 M2
5. LABS 1750 M2 6. LEARNING 55 M2
7. SERVICES 798 M2
4. SERVICES 1843.2 M2
BASE 5390.2 M2
OPTION 2603 M2
157
158
ONTWERPFASE REALISATIEFASE
Oplevering
Realisatie/uitvoering
Voorbereiding uitvoering
Aanbesteding+gunning
Bouwvoorbereidingsfase
Definitief Ontwerpfase
Voorlopig Ontwerpfase
Kalendermaanden
1
2
3
4
6
11 Maanden
5
10 augustus 2012 PLANNING ONTWERP- EN REALISATIEFASE gebouw "Z" basisvariant 7
8
9
10
11
12
13
14
15
16
17
18
19
20
22
20 Maanden
21
23
24
25
26
27
28
29
30
31
SCHEDULE
159
lowerground level 0 level 1 level 2 level 3 level 4
totale bouwtijd
oplevering
afbouw stroom stroom stroom stroom stroom stroom stroom stroom stroom stroom
dakafwerking
1 2 3 4 5 6 7 8 9 10
gevelsluiting lowerground level 0 level 1 level 2 level 3 level 4
ruwbouw
onderbouw inrichten bouwterrein damwanden bemaling grondwerk heiwerk keldervloer
kalendermaanden werkbare weken
10 augustus 2012 PLANNING BOUWTIJD
1
2
3
3 5 6
7
3 maanden
4
gebouw "Z" basisvariant
8
5 maanden
20 MAANDEN
5 maanden
7 maanden
5 5 7 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69
DRAWINGS
162
PLAN MATRIX
163
LOWER GROUND FLOOR
164
CAMPUS DECK
165
LEVEL 01
166
LEVEL 02
167
LEVEL 03
168
LEVEL 04
169
SECTION AA
170
WEST ELEVATION
171
SECTION BB
172
NORTH ELEVATION
173
SECTION CC
174
EAST ELEVATION
175
SECTION DD
176
SOUTH ELEVATION
177
Claus en Kaan Architecten Boompjes 55 3011 XB Rotterdam The Netherlands T: + 31 010 206 00 00 F: + 31 010 206 00 01 info@ckr.nl www.clausenkaan.com contact: Mitesh Dixit m.dixit@ckr.nl + 31 6 341 320 84
DOMAIN OFFICE Dante Borgo Mitesh Dixit Miles Gertler Sven Jansse Kees Kaan Loes Martens Exequiel Mulder Jan Van Maanen Vincent Panhuysen
Ramboll London Tom Foley Hari Lewis Stephen Mellville
Werner Sobek Malte Groner Valentin Brenner
B3 Ruud Raaphorst Patrick Lakerveld Patrick Bronwasser
CES Erwin Braekeleire
Dr. Heinekamp Peter van Heesewijk
DOMAIN