441
59
75
GEORGIA STATE EDITION
Cornella 19
A Supplement to:
Rome 85 27
Athens 441
Atlanta
20
Madison Augusta
85
20
Griffin 1
129
Milledgeville
75
La Grange
Macon
301
185 19
16
Dublin
Swainsboro Oak Park
Columbus
Statesboro
341 441 16
Lyons Americus
September 5 2012 Vol. XIV • No. 18
301
1
82
Dorchester
341
Cuthbert
75
Albany
84
Douglas Tifton
82
95
82
Blakely
Pearson
“The Nation’s Best Read Construction Newspaper… Founded in 1957.”
Savannah
McRae Cordele
27
27 84
Moultrie
19 319
Bainbridge
84
Valdosta Thomasville
Waycross Brunswick 82
1 441
Your Georgia Connection: Rich Olivier, Atlanta, GA • 1-800-409-1479
SGMC Undergoes Extensive Renovations, Improvements By Cindy Riley CEG CORRESPONDENT
Major construction at South Georgia Medical Center (SGMC) promises significant change at the non-profit hospital. Crews in Valdosta are putting in long hours, working to complete projects ranging from a patient tower, a new parking deck, infusion room and generator building. Drainage upgrades and nursing station renovations also are among the hospital’s recent improvements and renovations. “We are working an average of 50 tradesmen right now,” explained Mark Fernung, senior project manager of general contractor Robins & Morton of Valdosta, Ga., which is overseeing the patient tower project. “We should peak around 250.” The tower expansion and renovation involves approximately 127,000 sq. ft. (11,798 sq m) of new construction with the five-story patient tower construction and 8,000 sq. ft. (743 sq m) of renovation. According to Fernung, working in the somewhat confined space has been a challenge, along with keeping the existing areas functional and operating. Some of the equipment included as part of the job are cath labs, ceiling booms and patient lifts. The patient tower calls for 8,500 cu. yds. (6,498 cu m) of concrete, 850 tons (771 t) of reinforcing steel, 48,000 sq. ft. (4,459 sq m) of precast concrete, 180 tons (163 t) of structural steel, 20,000 sq. ft. (1,858 sq m) of metal panels, 17,000 sq. ft. (1,579 sq m) of glass and six new elevators. Crews hope to complete work on the tower by next summer. Half a dozen locations were evaluated before deciding on the current site for the patient tower, which is next to the outpatient center. The main floor of the new construction will house the Dasher Heart Center diagnostics and cath labs. The second floor of the tower is slated for the Cardiac Progressive Unit. The third floor will house the CICU, and the fourth floor will serve as the M/S ICU. A specialized surgical unit will be on the fifth floor. A bridge will connect the existing hospital with the new patient
Photo courtesy of Aero Photo
Working in the somewhat confined space has been a challenge, along with keeping the existing areas functional and operating.
tower. Chuck Smith, owner of Cauthan Construction Company Inc. said the SGMC Cancer Center expansion/renovaton and the new hospital parking deck both began in June 2011. “Both projects are in the final stages of construction with occupancy in approximately 45 days. Some of the biggest challenges or concerns on this project have included infection control, noise, parking and maintaining services to SGMC. Also, because we’re working through an existing building to enclose a courtyard and building over an existing detention pond, weather was a concern and a variable every day.” Equipment used by Cauthan’s crews included a tower crane, mobile cranes, boom truck, concrete pumps, backhoes, bulldozers, excavators, dump trucks, power buggies, demo equipment, concrete finishing equipment and pneumatic equipment. Materials have included structural fill, ready-mix concrete, masonry, metal studs,
many sub-contractors and suppliers.” Valdosta Mechanical Co. Inc. CEO Jimmy Scruggs says coordination is crucial on a project of this magnitude. “We’re responsible for the mechanical/HVAC work. We started on the bridge connector addition in March of 2012, and will start physical work on the patient tower in September. We are almost finished with the Cancer Center addition/renovation which started in late 2011, and have just started working in the new parking deck.” Valdosta Mechanical is working on the new generator building, and has just completed the air handling unit replacement, which is three projects combined into one, replacing air handling units for operating rooms and adjacent spaces, lab area and the radiology area. “Access to the site and coordination with other trades to make sure the owner has access to all components involved for maintenance is one of the biggest challenges. Hospitals have a lot more services than most buildings, but the allotted space never seems to increase proportionally. Chilled water piping, steam, heating water, supply duct, return duct, exhaust duct, fire protection piping, medical gases, domestic water, sanitary, and storm piping are all trying to fit into some very tight spaces. We are using building information modeling (BMI) to help accomplish this on the patient tower. Core drilling for the new patient tower kept “It’s even more challenging on the crews busy as they worked on one of SGMC’s renovation areas,” Scruggs explained. highest profile projects. “There are existing spaces so tight we can’t even remove the ceiling tiles. EIFS, hollow metal wood, door, pre-cast We’ve also had issues dealing with some of concrete, aluminum storefront/curtain wall the existing systems old enough that no one and structural steel. The Cancer Center expansion includes 27 knows where or what many of the compoinfusion bays and calls for fresh paint, floor- nents are. We’ve tracked and found dampers ing, cabinetry and new furniture as part of closed, blocking air to different areas, found the renovation. The parking deck, mean- in-line pumps no one knew the purpose of, while, is expected to feature a walkway from found piping that had eroded bad enough to stop up the HW system, etc. These are issues the deck to the main cafeteria hallway. Smith added, “These two feature projects typical in an aging facility that can’t be preare a successful reality due to the pre-plan- dicted. SGMC has been good about working ning and the close working/team relation- with us on these issues, but it takes a lot of see SGMC page 6 ship with our client, our design team and our