ALABAMA STATE EDITION
231
65
72 Florence
2
Huntsville
20 Decatur
72
565 59
43
A Supplement to:
231
431
31
5
Gadsden
78 59 Anniston
20
Birmingham Bessemer
82 Tuscaloosa
65 280
20 82 Auburn
80
85
Selma
Phenix City
Montgomery
82
April 4 2012 Vol. XXIIV • No. 7
65
231
43 84 431 331
84
84 52 31
45
“The Nation’s Best Read Construction Newspaper… Founded in 1957.”
Dothan
65 98
Mobile
10
Your Alabama Connection • Rich Olivier, Atlanta, GA • 1-800-409-1479
‘Busiest Two Miles’ of Interstate in Ala. Gets Major Rebuild By Cindy Riley CEG CORRESPONDENT
Crews rebuilding the original, 30-year-old concrete roadbed on a more than 2 mi. (3 km) segment of Interstate 65 in Jefferson County, Ala., have finalized the project, which replaces an aging, maintenance intensive segment of I-65 from I-459 to U.S. 31. Work was completed in January 2012 at a total cost of $21,300,920. “The overall project went very well considering the time limitations, weather limitations and the soil condition on the project,” said Alabama Department of Transportation (ALDOT) spokesperson Linda Crockett. “These subjects, along with the vast amount of traffic, were great challenges. However, with careful planning and quick responses from personnel, it was a success. The project being completed along with others just south
of this one, means a safe, smooth ride for motorists for years to come. Now that the work is done, it’s time to move to another portion of Alabama’s roadways and continue to make improvements for motorists.” The high-profile assignment involved several ALDOT, contractor and city personnel, and was part of the ALDOT’s Progress on Alabama Roadways campaign to preserve critical highway infrastructure. ALDOT dubbed the project Progress65, and said the new concrete surface will provide an easier ride along one of the states most traveled interstate corridors. “This is a very busy area — some say the busiest two miles of interstate in Alabama,” said Nick Wolf, senior project manager, McCarthy Improvement Company, Davenport, Iowa. “The section we reconstructed was in very bad shape. Potholes, joint faulting and excessive deterioration of
the roadway made for not only a bad ride, but also a dangerous one. Our main goal for the project was to provide the traveling public with a new concrete roadway that will last for years to come in the very short time frame given to us as to not inconvenience the public any more than absolutely necessary.” McCarthy Improvement self performed the existing concrete roadway removal, all the earthwork, all the drainage/storm sewer work and placed the new concrete pavement that serves as the final riding surface. The existing roadway was removed in stages to allow traffic to still travel through the work zone. Once the existing pavement was removed, approximately 12 in. (30.5 cm) of dirt was removed to get to subgrade elevation. Six in. (15 cm) of asphalt was placed as base for the new 14-in. (35.5 cm) concrete layer which is the final riding surface. Once the concrete pavement was completed in
phases, traffic was moved onto the new concrete pavement, which allowed the old pavement to be removed and replaced. This cycle repeated until all the old pavement was replaced with new material. According to Wolf, “It means a highstrength, smooth riding concrete section of roadway that will be worry-free for years to come. Overall, the project went well, despite its many phases. “The main challenges were the traffic and logistics. The biggest issues, honestly, were issues with change. Concrete roadways, while prevalent in Alabama, have not been constructed in the state in decades. “Another major issue was the subgrade that was found under the existing roadway,” Wolf explained. “It was unsuitable, which lead to significant delays and extra work in order to condition it so it could be usable.” see PROGRESS page 2
Throughout much of the project three lanes were open in the northbound and southbound directions. To accomplish this, one lane of traffic traveled in a backwards direction on the opposing travel lanes. Most of the work was performed behind temporary concrete barrier walls to protect the traveling public and the workforce.