The Art of the RFI By Shawn Overholtzer

N

othing will ruin your day faster than getting a call from a builder reporting an issue with trusses you’ve designed. You hear their frustration as they are faced with a potential delay and additional work to implement a fix. We all desire to eliminate those calls from our daily business, and one way to do so is to work only on jobs with a perfect set of drawings. You know, the drawings with dimensions that are 100% correct, have no errors in the listed wall heights, the heel heights are clearly spelled out with the location of the HVAC equipment and lines identified, and every load path is well thought out. The truth, though, is that there’s really no such thing as a perfect set of drawings, because there will always be some area needing further clarification to ensure the trusses you design won’t have issues. Although this reality is typically viewed as a source of frustration, it can be an opportunity to provide extra value to your customers by helping them resolve issues before they become a problem in the field. To do this requires a trained eye to identify issues and the use of an RFI (Request for Information) to work through these issues with the appropriate parties involved. In this article, we will walk through some best practices of using an RFI to help eliminate those calls.

When should you use an RFI? An RFI should be used whenever there is confusion or doubt and more information is needed to accurately complete a project. If the question is asked, “Why do I need to submit an RFI when I can get my information direct?” A simple answer is for the few times when a situation becomes a dispute and multiple parties express opposing accounts of a discussion.

What format should you use to initiate an RFI? The general format of the RFI is not as critical as maintaining consistency. The easiest method is to create a format that your entire company can use easily and effectively. This can be as simple as using text editing software or a spreadsheet. If you would like to take it to the next level, there are several construction management software options with built-in tools to make an RFI easier, and even allow tracking through the process.

Write clear and concisely Be sure to present your RFI in a question format that is clear and concise. It is often better to submit multiple RFIs separately for individual issues rather than to create confusion by combining multiple requests in one submittal. Be specific about the period stakeholders have to answer the RFI before it starts to delay processes. Avoid words or phrases that come across as condescending. Provide clear references to the question through details and images. The easier you make the process the more likely you will get an answer and be able to proceed with your work. Do not hesitate to present possible solutions. As an industry expert, you may have a simple solution that never occurred to anyone else. This type of value will go a long way in building credibility within the community and might even help you win the next job when your reputation as a team player who brings innovative solutions to the table is known. In some cases, it may be helpful to provide a summary report of all preconstruction RFIs to your customer. PHONE: 800-289-5627