Strategic Plan - 2021 Q2 Report

Page 1

2020-2025 STRATEGIC PLAN 2ND QUARTER REPORT The 2020-2025 Strategic Plan Second Quarter Report provides an overview of the number of tasks completed within each action plan, by goal, to demonstrate the progress against what was scheduled to be completed between April 1, 2021 through June 30, 2021. OVERALL PROGRESS FOR 2021 Q2 81%

52 out of 65 (81%) tasks completed in Q2

WATER AND ELECTRIC SUPPLY AND DISTRIBUTION 2ND QUARTER 2021 PROGRESS 86%

Goal One: Optimize Water and Power Assets to Increase Reliability and/or Decrease Costs (4.6 of 6 tasks completed - 77% progress to goal in Q2) Goal Two: Manage, Maintain, or Replace Water and Power Assets in the Most Cost Effective Manner (5 of 5 tasks completed - 100% progress to goal in Q2) Goal Three: Implement Additional Water and Power Storage Projects to Increase Reliability, Improve Water Quality, and/or Decrease Costs (.25 of 1 tasks completed - 25% progress to goal in Q2) Goal Four: Proactively Leverage Regulatory, Legislative, and Technological Opportunities to Best Serve Our Community Through Intentional Collaboration (3.85 of 4 tasks completed - 96% of progress to goal in Q2) Notable Q2 Accomplishment: Completion of August Feeder 5 and Rogers Feeder 2 Reconductor Projects Benefit to the District and Customers: Enhancement and maintenance to TID’s distribution system, through reconductor projects, will increase system reliability and help to prevent transmission system overload. In addition to improving the current-carrying characteristics, the August Feeder 5 project also significantly improved voltages at the end of the feeder. The Rogers Feeder 2 project delivers a complete back-feed solution in the Patterson area, specific to Feeder 3.


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.