Pregrouting combined with double shield TBMs

Page 1

Direct by Design

Pregrouting combined with double shield TBMs Of the 36km of 9.9m o.d. (9.1m i.d.) segmentally lined double-shield rock TBM excavation required on the twin tube Follo Line railway between Oslo and Ski in Norway, nearly 8,000m or 22% required systematic pre-excavation grouting to lower the pore pressure and ground water levels in the host geology and protect against the surface settlement that alteration of the groundwater table can induce. This detailed review of the pregrouting operations developed, optimised and applied by the Acciona Ghella JV during the project is extracted from a paper presented by Acciona at the 2020 WTC World Tunnel Congress, Malaysia.

T

he Follo Line construction contract established strict criteria to avoid settlement and damage to environment and any existing structures and building along the alignment of the 20km long twin tube TBM bores on the new railway connection

between Oslo and Ski. To meet the criteria, the contract specified two main methods for protecting the natural ground water regime and to avoid water ingress during excavation: • A watertight precast concrete, bolted and gasketed segmental lining and

Acciona reporting from a paper presented at WTC 2020, Malaysia • Systematic and specified pre-excavation grouting as a mandatory requirement at specific locations and in others, a requirement for the contractor to determine the extent of pre-excavation grouting required to maintain the ground water levels. The contract established and defined grouting requirements, and also provided information on grouting concepts, with the contractor required to further develop these concepts and the chosen methods of construction to maintain the existing ground water levels. Assessing the potential for water ingress into the headings was via probe drilling by drill rigs installed on the first backup gantry close to the shields and drilling 44m long probe holes. The contract pre-established the number of probe holes that were required in areas previously classified as highly sensitive. Pre-grouting was triggered by ingress of ground water through the probe holes. Initially, Bane Nor, the client, estimated pre-grouting quantities in the TBM headings as about 1,600m in total or some 4.4% of total 36km of bored tunnel length when excavation of the parallel tubes by four double shield TBMs from a central access adit towards the portals began their work in 2016. When both tubes and the last two TBMs completed their drives in February 2019, the total length of pre-excavation grouting executed was in fact 8,000m or some 22.22% of the total bored length. Preexcavation grouting was a major part of the excavation process and required team work with the client to optimise the process, meet the water control criteria and maintain the project programme. The contract described the drilling equipment to be installed on the TBMs to comply with the probing and pregrouting requirements. Based on this, the following equipment was installed on each machine: • Two Atlas Copco COP3038 drill rigs with 185º rotation capacity • A TC 42 short twisted splins shank adapter • 12ft x 39mm round TC 42 extemsopm rods • A C12ft x 46mm round TC 42 RND 46 speed guiding rod

Above: A two-hole probe drilling concept with the litres of water per minute from each triggering the need for pre-excavation water control grouting Below: Drilling equipment on the first gantry of the TBM backup allowed for full 360˚ grout injection arrays

T U N N E LT E C H

Underground in Action U

Rigs 1, 2 and 3 of the mobile pregrouting equipment

1


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.