From:
Nick Roberts
Office: Kansas City Date:
3.23.11
Re:
Sporting Kansas City Project Update – Week of 3.23.2011
To: David Ficklin - OnGoal Rory O’Connor – OnGoal Lee Turner – OnGoal Andy Heitmann – Turner Dave Dudzik - Turner Brandon Valdez-Turner
Current Activities this Week: Site/Playing field/Bowl: Grading on plaza is onging. Installation of underground drainage at plaza is ongoing. Installation of fence around field is ongoing. Final field preparation for sod is nearly complete. Seating support install is ongoing. Concrete Flatwork: Area 3-Topping slab at cauldron club is complete and protected. Area 1- SOG work at SW toilet entry to be completed. SE vomitory road was poured. Masonry: Block installation at NW transformer area to be ongoing. Block installation at Terrace Bar is nearly topped out. Sealing and final wash of block on the East side to be ongoing. Washing and sealing F-line will be complete this week. Finishing concourse exterior walls will be ongoing.
Irrigation of field and protective fence.
Stone: Area 1-Stone installation in area H is nearly complete. Steel: Installation of dock overhead doors is complete. Wind columns will be complete. Installation of tube header at NE retail will be complete. RFI 971 stone support is complete. NE entry gate steel installation is ongoing. Conduit for NW Main Entry sign in stone.
Building the Future