ACTUAL FY 2016
ESTIMATED FY 2017
TARGET FY 2018
Number of Development Plans reviewed (in process) during the reporting period
5
3
4
Number of Plats reviewed (in process) during the reporting period
7
6
4
100%
100%
100%
Number of zoning code amendments initiated
5
3
2
Number of zoning code amendments adopted
5
2
3
Number of major general plan amendments processed
0
0
0
Number of required General Plan updates performed
0
0
0
Percentage of positive comment cards received
100%
100%
100%
Percent of zoning complaints investigated within 3 business days of the complaint
100%
100%
100%
ACTUAL FY 2016
ESTIMATED FY 2017
TARGET FY 2018
Total number of building inspection stops
4,538
4,300
4,400
Percentage of building inspection stops completed on time or when requested
100%
100%
100%
277
230
260
Average time for single family residence (from a model plan) plan review (in business days)
1
1
1
Percentage of single family residence (from a model plan) plan reviews completed within 5 business days of a complete submittal
100%
100%
100%
Total number of permits issued - Commercial
26
18
20
Average time for commercial plan reviews (in business days)
6
9
8
50%
85%
90%
Percent of reviews completed within target goal (4 weeks)
Total number of permits issued - Residential
Percentage of commercial plan reviews completed within 10 business days of a complete submittal