Infographics Lek ENG 2015

Page 1

Room for the River Lek Flood plain excavation Bossenwaard, Pontwaard and Heerenwaard

Current situation Bossenwaard flood plain

Channels are being created in the flood plains of the river Lek at IJsselstein, Nieuwegein, Vianen and Houten. The access dam at Hagestein and the summer quays are being lowered as well. These interventions will increase the water safety along the Lek at high water. N W

New situation Pontwaard flood plain

high water

Bossenwaard (flood plain) secondary channels

Pontwaard flood plain

secondary channel

Lek

Lek

IJSSELSTEIN

E

A2

Bossenwaard

S

NIEUWEGEIN

NIEUWEGEIN

recreation area Key to map: Merwedekanaal (channel)

planning area ‘text’

modified / new situation new, modified or replaced objects new quay/dyke new channel

Lek

Bossenwaard (flood plain)

A new summer quay will ensure better downward flow of the River Waal.

Pontwaard (flood plain)

motorway

't Waalse Waard (flood plain)

summer quay

dyke

Pontwaard (flood plain) VIANEN

Vianense waard (flood plain)

(provincial) road access dam

Le

Hagestein weir

k

The access dam at Hagestein weir island is being lowered. The Lek will be able to flow over this lowered weir island more easily during high water.

Hagestein weir island

VIANEN

Merwedekanaal (channel)

A27

Planning

Effect

1 2 3 4

8 cm drop in water level during high water level with Hagestein weir.

Project decision Preparation phase Start of work Delivering water safety

Scale: 1 2011

www.roomfortheriver.nl

2012

2

3

2013

2014

4

HAGESTEIN

0

1 km

2015 Jan 2015 / 25


Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.