b.con 2

Page 11

STEEL BASE FRAMEWORK

5

Metal mesh was secured to the frame by welding it to the RHS framework.

6

8

Bigger RHS were welded together to form the primary member of the frame, while RHS with smaller dimension were welded together in between the primary member to form the secondary member.

5

7

It was later screwed into the RHS base frame to increase stability.

8

9

COLUMNS Long scrap steel plates 9 were welded together to form model’s 1:5 scale H column. The mild H column were 10 cut accordingly to the dimensions of the model using a steel cutter chop saw.

10

Construction process

6

7

Rectangular hollow section (RHS) were cut into the dimensions of the model

11.