CSI MURAL PROJECT ON WASTE COLLECTION AREA

Arron Goh Swee Tien | Chin Cheong Soon | Chow Su Ling | Juergen Christian Martin | Kalvin Bong | Lim Peidi | Ng Pui Yan | Rudy Irawan




Budget To finish and Mock Up


Estimated Budget to Finish No

Items

Quantity

Price (RM)

Total (RM)

1

White Paint (1L)

3

30.00

90.00

2

Blue Paint (1L)

2

30.00

60.00

3

Yellow Paint (1L)

2

30.00

60.00

4

Red Paint (1L)

2

30.00

60.00

5

Green Paint (1L)

2

30.00

60.00

6

Black Paint (1L)

1

30.00

30.00

7

Paint Brush

8

2.00

16.00

8

Paint Roller

4

15.00

60.00

9

Masking Tape

5

3

15.00

10

Newspaper

-

-

-

Total (RM)

451.00

Suggest for sponsorship to reduce budget


Expenses for Mock Up No

Items

Quantity

Price (RM)

Total (RM)

1

White Paint (1L)

1

25.00

25.00

2

Blue Paint (1L)

1

33.00

33.00

3

Yellow Paint (1L)

1

32.00

32.00

4

Red Paint (1L)

1

28.00

28.00

5

Green Paint (1L)

2

26.00

52.00

6

Black Paint

1

29.00

29.00

7

Paint Brush 2.5”

2

3.00

6.00

8

Paint Brush 1.5”

2

1.50

3.00

9

Paint Brush 1”

2

1.00

2.00

10

Thinner

1

3.00

3.00

11

Duct Tape

1

3.00

3.00

12

Brush and Marker

1

19.10

19.10

Total (RM)

235.10


Transportation from Taylor’s University to Sri Tioman 1

RM0.70 per km travelled RM0.70 x 38km = RM26.60 Toll = RM2.10 Total = RM28.70 RM28.70 x 2 = RM57.40


Transportation from Taylor’s University to Sri Tioman 1

Date

Task

Destination

Number of Cars

Total (RM)

31/3

First site visit

Sri Tioman I

2

114.80

7/4

Painting of pegboard

Sri Tioman I

1

57.40

8/4

Interview

Sri Tioman I

1

57.40

25/4

Second site visit

Sri Tioman I

1

57.40

20/5

Survey task

Sri Tioman I

1

57.40

3/6

Mock up presentation

Sri Tioman I

1

57.40

Total

401.80


Timeline Mock up and execution


Timeline of Execution

Week 1 - 4

Week 5 - 7

Week 8 - 9

Week 10

Collection of ideas from interviews

Design and research

Refinement and feedback

Completion by mock up


Timeline of Mock Up

Week 1 - 3

Week 4 - 6

Week 7 - 9

Week 10

Collection of ideas from residents

Design and feedback

Participation of residents

Completion


Method and Option Method Statement and Variation


Method of Execution

Collection of Idea and Design

Participation of resident

Finish of Mural Art


Suggested Options



Infographic

Artistic Pattern


Mural Art Choices

Educational

Related to daily life and activity

Done by resident


Engagement How to get residents involved


Collection of Idea and Design

Participation of resident

Finish of Mural Art


Collection of Idea and Design

1. 2. 3. 4.

Participation from residents. Choose a leader to keep progress on track. Collection of idea from residents. Submission of design.


Collection of Idea and Design

Participation of resident

Finish of Mural Art


Participation of resident

1. 2. 3. 4.

Contribution of idea. Submission and feedback of design. Selection and agreement on chosen design. Delegate task to participants.


Collection of Idea and Design

Participation of resident

Finish of Mural Art


Finish of Mural Art

1. Drafting of design on wall. 2. Paint work. 3. Finishing and touch up.


END CSI - MURAL PROJECT ON WASTE COLLECTION AREA

Arron Goh Swee Tien | Chin Cheong Soon | Chow Su Ling | Juergen Christian Martin | Kalvin Bong | Lim Peidi | Ng Pui Yan | Rudy Irawan


Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.