Reading Station Area Work Package Contractor’s Quality Plan Principle Contractors: JDI (Shaylor Group) Project Number: 106499/6.12.1

25. Helpline The contractor shall use the project helpline number for the reporting of any environmental enquiries from t he general publ ic. Where an enq uiry r equires ac tion, t he c ompany s hall respond appropriately to information provided by the IPT. The Shaylor Group HSEQ Office for this project is Andrew Rolinson. Mobile: 07816 662422 Email: andrew.rolinson@shaylorgroup.com

26. Dust The company shall take all reasonably practicable measures to avoid nuisance arising from dust or fumes, or any other air-borne pollutants.

27. Air Pollution The project EIA identifies nitrogen oxides (NOx) and dust par ticles of diameter l ess than 10Îźm (PM10) as significant pollutants in urban areas. PM10 is particularly associated with dust from construction sites. The c ompany s hall t ake al l pr acticable m easures t o prevent t he oc currence o f s moke emissions o f fumes from pl ant, t raffic, fuel oi ls or o ther substances, and pr event any emissions or fumes drifting into nearby premises, including those that contribute to PM10. The company shall ensure that all plant and equipment is maintained in good conditions and conforms to manufacturers and legislative emission standards. All plant shall be switched off when not in use.

28. Watercourses Any dr ains, s prings or watercourses t hat may be i nterfered w ith or c ut t hrough s hall be preserved and pipes, and other means provide so as not to stop or diminish their present flow. S hould any dr ain be di scovered or l eft uncovered, ade quate measures s hall be provided to convey the water to a s uitable outlet and ev ery reasonable precaution taken to protect the environment from harm as a consequence of the works. Appropriate c onsents s hall be obt ained f rom Local A uthorities ( or s imilar) pr ior t o any discharge to watercourses. Once the consent(s) have been obtained, the company shall submit a P ermit t o P roceed – Discharge C onsent t o t he I PT M &E r epresentative f or authorisation to p roceed pr ior to any di scharge commencing. The I PT will c o-ordinate t he interfaces within the project for various discharge consents. The company shall not make any temporary or permanent connections to the mains, pipes, drains, watercourses and other utility services without prior approval.

Page 10 of 13