|Project Management Portfolio|
|Project Management Portfolio|
Client : Aman Group
Company : Meinhardt EPCM Indonesia
Scope : Project Management Consultant QS
Construction Management
Engineering (Structure and MEP)
Role : Project Manager
Project Value : USD 58.5 Million
Start : 2023
Construction : Starting March 2025
Status : Tender Infrastructure Work
Aman Group is having a massive expansion for its well-known resort in Bali, Amankila. The expansion consists of 11 luxurious private villas sitting on top of 5,6 ha terrain, a new beach club, and a 3.000 m2 spa building on top of a hill.
Client : Aman Group
Company : Meinhardt EPCM Indonesia
Scope : Project Management Consultant
QS
Construction Management
Role : Project Manager
Project Value : USD 20 Million
Start : 2023
Construction : Starting Q3 2025
Status : Construction Documentation + Permit
This is another expansion project by Aman Group for the famous Amanjiwo in Magelang, which was built back in 90’s. The additions are 4 luxurious private villas with a footprint of 2 500 m2 each, and a 3 000 m2 spa and wellness building
Client : Digital Realty
Client : Mondelez International
Company : Meinhardt EPCM Indonesia
Scope : Project Management Consultant QS
Construction Management
Engineering
Role : Project Manager
Project Value : USD 1,3 Million
Start : End 2023
Construction : Starting July 2024
Status : Ongoing Construction
Mondelez International has commissioned Meinhardt EPCM Indonesia to design fire fighting system and sandwich panel replacement for the existing Kraft Ultrajaya plant in Bandung. The scope is then expanded into PMC, QS, and CM.
Company : Meinhardt EPCM Indonesia
Scope : Engineering Assessment
Role : Project Manager
Year : 2024
Status : Completed
Digital Realty appointed Meinhardt EPCM Indonesia to do a structural integrity assessment to its newest data center in Jakarta
Client : PT Vale Indonesia
Company : Meinhardt EPCM Indonesia
Scope : Engineering Simulation
Role : Project Director
Start : 2024
Status : Completed
Vale plans to expand the material handling capacity of its port in Morowali. Meinhardt EPCM Indonesia is commissioned to run simulation on various scenarios how to achieve the target capacity
Client : Danareksa
Company : Meinhardt EPCM Indonesia
Scope : Feasibility Study Reviewer
Role : Project Director
Start : 2024
Status : Ongoing
Pupuk Kaltim plans to develop 500 ha industrial estate in Fakfak, West Papua Danareksa has the job to do review on its feasibility study, Danareksa appoints Meinhardt EPCM Indonesia as a partner to do the review
Client : Bali CMPP and Solo CMPP
Company : Meinhardt EPCM Indonesia
Scope : Engineering
Role : Project Manager
Start : 2024
Status : Completed
Bali CMPP and Solo CMPP are companies that treat domestic wastes into RDF brickettes and use them to generate electricity. Meinhardt is commissioned to do technical verification on the system and improvement recommendation.