1 minute read
844/642 Telehandler ELECTRICAL
STEP 18
FUEL SHUT-OFF SOLENOID TEST
Step 20
Install the positive (+) test lead to the fuel shut-off solenoid. Turn the key switch to the ON position. The multimeter should read 12 to 13 volts.


If there is no voltage, proceed to the next step.
If there is 12 to 13 volts, but the engine will not start, replace the fuel shut-off solenoid valve.
Step 21
Check the fuel shut-off solenoid fuse (#2) (1) and test power to the fuse (Step 4) and ignition relay (2) (Steps 5 and 6).
If the fuel shut-off fuse and ignition relay are operating properly, repair or replace the red wire between the fuse and the fuel shut-off solenoid.