Swing-away lattice 4.3 Checklists for rigging work

6. Folding out the run-up rail; à p.4-48.

7. Securing the swing-away lattice with guide rope; à p.4-39.

8. Check, –that the connection in the Middle area is in the position Section1/ Section2; à p.4-54. –that the connection between section1 and section2 is established in the Rear area; à p.4-60.

9. Disconnect the connection between section2 and the main boom in the Rear area; à p.4-57.

10. Swinging the lattice extension on to the main boom head; à p.4-66.

11.

14. Pin section1 to main boom head, on the left-hand side; if necessary release the bearing points or use the hydraulic rigging aid (additional equipment); à Left-hand connection, p.4-62, à Relieving the connecting points , p.4-63, à Hydraulic rigging aid (additional equipment), p.4-63.

15. In the Front area, move the connection into the position Unrigging; à p.4-53.

16. If section2 is transported on a separate vehicle, install section2 in front of section1:

–Sling section2; Slinging points, p.3-6.

–Raise section2 in front of section1 and pin it there; à p.4-71.

–After installing section2, proceed as from point 22.

Swing-away lattice 4.3 Checklists for rigging work

17. If section2 is folded on section1, fasten the guide rope to the head of section2.

18. Move the connection in the Middle area into the position Section1; à p.4-55.

19. Swing section2 in front of section1; à When rigging – section2, p.4-69.

20. Establish the connection on the left between section2 and section1; à Connections to the swing-away lattice, establishing/disconnecting, p.4-71.

21. Establish the electrical connection; à p.4-74.

22. Fold out the deflection sheaves to the front and rear; à p.4-76.

23. Place the hoist rope on the swing-away lattice; à p.4-78.

24. Install the anemometer and if necessary establish an electrical connection for the air traffic control light; à Installing/removing the anemometer, p.4-83, à Air traffic control light – electrical connection, p.4-85.

25. Install the lifting limit switch; à Installing/removing the lifting limit switch, p.4-80.

26. In the case of the inclinable swing-away lattice, adjust the angle, if necessary; à Setting the angle – with the auxiliary crane, p.4-91. à Setting the angle – without the auxiliary crane, p.4-92.

27. Reeve the hoist rope on the hook block; à Possible reeving methods on the swing-away lattice, p.4-79.

28. Attach the lifting limit switch weight and place it around the hoist rope; à Operating instructions GMK5130-2/5110-1, Section 2 Superstructure – Rigging work.