Swing-away lattice 4.3 Checklists for rigging work
18. Install the anemometer and if necessary establish an electrical connection for the air traffic control light; à Installing/removing the anemometer, p.4-83, à Air traffic control light – electrical connection, p.4-85.
19. Install the lifting limit switch; à Installing/removing the lifting limit switch, p.4-80.
20. In the case of the inclinable swing-away lattice, adjust the angle, if necessary; à Setting the angle – with the auxiliary crane, p.4-91. à Setting the angle – without the auxiliary crane, p.4-92.
21. Reeve the hoist rope on the hook block; à Possible reeving methods on the swing-away lattice, p.4-79.
22. Attach the lifting limit switch weight and place it around the hoist rope; à Operating instructions GMK5130-2/5110-1, section 2 Superstructure –Rigging work.
23. Check the horizontal alignment of the truck crane and correct, if necessary.
24. Enter the current rigging mode with the rigged swing-away lattice; à Setting the SLI, p.4-99.
25. Enter current reeving; à Setting the SLI, p.4-99.
Further steps with swing-away lattice: –Raise main boom; à p.4-101. –Telescope main boom; à p.4-102.
Blank page
4.3.5 CHECKLIST: Rigging the 18 m (59 ft) swing-away lattice
HThis checklist is not a complete set of operating instructions. There are accompanying operating instructions which are referred to by crossreferences. Observe the warnings and safety instructions there.
1. Rigging the truck crane:
–Rig the truck crane according to CHECKLIST: Rigging; à Operating instructions GMK5130-2/5110-1.
–Before crane operation, check according to CHECKLIST: Checks before crane operation; à Operating instructions GMK5130-2/5110-1.
–Retract the main boom completely and lower it into the horizontal position.
–Roll the unused hoist rope on to drum.
2. Check the transport condition of the swing-away lattice; à Transport condition with folded swing-away lattice, p.4-42.
3. For derricking swing-away lattice:
–Check to see if the locking device is released on the hose drum; à p.4-45.
–Position hydraulic hoses for working with the lattice extension; à p.4-46.
4. For derricking swing-away lattice, establish a hydraulic connection; à p.4-47.
5. Establish the electrical connection; à p.4-73.