4 Mounting 4.1 Additional control unit 7433
– Install the drive wheel. - Use the wheel bolt tightening torques specified in the Operator's manual. – Lower down the machine. 12296
4.1.2 Prepare and carry out a test run – If necessary, carry out the following work prior to a test run: - Retighten threaded joints of all newly installed parts. - Refit any safety features previously removed. - Check hydraulic oil level. Top up if necessary. Check tightness of hydraulic system. - Check gearbox oil levels of fitted components. Top up if necessary. - Put back all tools used. - Check retrofitted and/or removed electric connections. - Grease all newly added grease points. – Check machine settings. – Carry out a test run. – Check hydraulic oil level. Top up if necessary.
24
000 294 779 0 - ABA ZSG JAGUAR 900-830 - 11/06