4.3 Long-time storage (> 6 months
from Cat Electric Rope Shovel 295HD/ HR Drive Converter Cabinet Bucyrus Shovel Operation & Maintenance Ma
When DCC is stored for long periods of time, the ambient temperature should be below 40°C (preferably below 25 °C).
A general inspection of the DCC must be carried-out after it has been stored for a long time (corrosion, rust, dust, cobwebs etc.)
If required: • Clean the DCC • Carry-out an insulation test • Visual check for water hose – damages if any • Check the fan bearings in the DCC • Check the fan bearings in the SIBAS rack (refer to SIBAS documentation) • Test the SIBAS battery (refer to the SIBAS documentation) • Check the capacitors (electrolytic capacitors) in the SIBAS (refer to the SIBAS documentation) • Check the electrolytic capacitors in the IGBT Driver power supply. • Check the tantalum electrolytic capacitors in the IGBT Driver cards. • Check the electrolytic capacitors in the SIBAS filter:
The electrolytic capacitors must be re-formed (i.e. the electrolyte must be regenerated) if the DCC was stored for more than 2 years.
Procedure when forming capacitors: • Observe the filter polarity • Use a 100 Ohm series resistor • Connect a voltage of 120 V DC across the series resistor at connections from Channel 2 • (Duration: 1 hour). • After 1 hour: Disconnect the voltage, discharge the capacitor in the filter • Store the filter for 48 hours • The capacitors in the filter are now formed