REOstone Levee Reconstruction

Page 1

REOstone Levee Reconstruction



1,000-year rain turns REOstone Quarry into REOstone Lake REOstone Levee Reconstruction

In the first two days of May 2010, Nashville, Tennessee experienced a massive rainfall measuring 20 inches in some areas. The torrential downpour brought the Cumberland River to crest at 51.86 feet, its highest level since 1937. Nashville was declared a National Disaster Area with damage estimates near $1.5 billion. One of the more devastating results was the failure of a levee that separated Richland Creek from the REOStone Quarry owned by Rogers Group, Inc. In just five hours, the 50-year-old quarry became a 42-acre lake with depths exceeding 500 feet. Adding to the destruction were two trunk sewer lines that had washed away, spilling raw sewage into the environment.


Client

Rogers Group, Inc. Location

Nashville, Tennessee Market

Transportation Services

Civil Engineering Environmental Engineering Utility Relocation Management

PRINCIPAL-IN-CHARGE

Joseph L. Vance, Jr., P.E. PROJECT MANAGER

Diane Regensburg, P.E. Project professional

Ted A. Kniazewycz, P.E. Additional

Dwayne Knalls J. Dale Mosley Robert E. Oswalt, P.E. Ken Stewart, P.E.

D

escribe the conditions of the REOstone quarry site.

How did GS&P’s solution change as the project progressed?

Ted Kniazewycz: Prior to the flood, the REOstone rock quarry had a 50-foot-wide natural solid rock barrier that separated Richland Creek from the 500-foot deep quarry. During the flood, the water got so high and put so much pressure on the levee wall that it quickly eroded and spilled like Niagara Falls, filling the quarry in five hours.

Ted: We were initially brought in to present the Rogers Group with permanent dam options. They first thought we could build a concrete dam, but as we evaluated the situation and discovered the fissure we realized a dam wasn’t possible. We explained that what they needed was a levee, not a dam, and recommended using the available natural resources at the site.

We were called a week after the flood and were very interested because we’d watched this unfold on a live news broadcast, never dreaming we would be involved in this project. The owner took us as close to the site as we could get, and what we saw was a 42-acre lake with 7 billion gallons of water connected to what used to be Richland Creek. What we couldn’t see was that not only did the levee breach the high wall of the quarry, the existing creek bottom was completely gone. The force of the water eroded not only five feet of depth of the solid rock channel, it also eroded the rock ledge that supported the channel bottom. The levee could not be repaired in the same location because the supporting ledge no longer existed.

122

showcase 4

Once the water level went down the full measure of the fissure was exposed: 20-feet wide and 150-feet deep—a feature that had been there for hundreds or thousands of years. Since there was nothing we could do to fill or span the fissure, we had to come up with a different solution. Our role shifted to design a levee that housed the destroyed sewer system, protected the quarry from catastrophic flooding, and created a new path for Richland Creek. When you assessed the area, what emerged as the most urgent issue?

Ted: As a team, it was a lot. The Cochrill/Basswood trunk sewer line that was inside the high wall washed out, spilling raw sewage throughout 7


North

reostone quarry

Cumberland River

richland creek

North

reostone quarry

Cumberland River

richland creek

TOP: The REOstone Quarry operating normally before the flood. ABOVE: The quarry immediately after 1,000-year rain event in 2010. gresham, smith and partners

123


Richland creek

Aerial sewer line crossing

Quarry access road

Quarry HIGH wall

billion gallons of water, and creating a critical environmental situation.

flowing into the quarry, the creek and the Cumberland River.

Ken Stewart: And in addition to the 42-inch diameter sections of gravity sewer pipe that washed away, there was also a double barrel, 30-inch diameter aerial crossing—a gravity sewer that sits on concrete piers— that collapsed. So in an instant the city lost two large trunk sewer lines that served as the drainage basin for the west side of Nashville.

Next, Rogers Group stopped the creek from flowing into the quarry so they could start draining the water. They placed a temporary earthen berm, or barrier, using whatever material they had at the site. Once the sewer lines were closed off and the berm was in place we quickly got started.

Ted: The first priority was to cut off the sewer flow. Metro Water Services contracted to install temporary pumps to bypass the section of sewer line that failed, and within a week stopped the raw sewage from

124

showcase 4

What was complicated about the levee and the new sewer design?

Ted: The temporary pump system put in place by Metro Water Services was extremely expensive. It was costing an average of $125,000 a month

to operate and required 24-hour monitoring. It was exposed, which increased the chances of failure. The safest place and best fit for the new sewer lines was inside the levee and under the new creek bottom, meaning maintenance wouldn’t be an easy task. Ken: The large diameter shot rock boulders used to build the levee are roughly three feet in diameter and weigh about a ton each. Trying to dig through that material to fix a sewer line problem would be a nightmare. The other line would be underwater and underground, but there was no other acceptable option. To protect the new section of the Basswood trunk sewer located within the levee


OPPOSITE PAGE: An aerial view of Richland Creek path and REOstone quarry before the flood. VIDEO SERIES: Live video of the levee breach during the 2010 flood. The levee breach reduced downstream flooding, but severely damaged quarry operations. LEFT: The remainder of the previous quarry access road and fencing rests above one of the destroyed sewer pipes. ABOVE: The force of rushing water into the quarry is evident through the exposed fissure and remnants of the aerial sewer line that crossed over Richland Creek. The size of the void made filling it impractical.

from damage during construction, the pipe was encased in concrete. This prevents the lines from floating in a flood event, and greatly reduces the potential of a future leak into the environment. For the trunk sewer line in the levee we essentially created a monolithic structure, which is a 300-foot long section of sewer put together in 20foot joints of pipe. The advantage is that the pipe joints can’t flex or deflect in any way. Ted: We made it as stout as possible in the event that if a pipe failed the encasement of concrete would act like a pipe protecting the environment.

After looking at several options to reconnect the sewer lines, GS&P recommended an inverted siphon system. Why?

Ken: Metro Nashville Government was adamant that we were not to install another aerial crossing sewer line like the one that was washed away. One alternative was to install a gravity sewer that would have gone under James Avenue and Briley Parkway and impact an NES substation, which could have doubled or tripled the cost of the project. That gave us only a few options, and we ended up with an inverted siphon. An inverted siphon is pretty rare; it’s the first one I’ve designed in my 13 years in engineering. Typically we

use gravity sewer or force main, but because both sewer lines were now underground we used an inverted siphon to transport the sewage flow under the creek and then uphill to rejoin the traditional gravity system. An inverted siphon combines gravity flow with a short section of U-shaped pipe. Liquids flowing in one end are forced up and out the other end. What kinds of natural materials were available on site and how were they applied?

Ted: Since Rogers Group owned the quarry and all the material sites close by, they wanted us to use as many natural materials as were readily available.

gresham, smith and partners

125


JUDGES’ COMMENTS

“...impressed with response time ...thoughtful approach.” “...high pressure project ...extreme public visibility”

We ended up using clay as a core, armored with shot rock, which is a variety of rock types and sizes used to protect structures from erosion. Clay is very impermeable to water. It stays somewhat moist, but can be compacted to achieve high densities that reduce water to a slow migration over time. What were some of the more unique challenges you encountered?

Ted: The location of the utilities provided constraints to the levee layout because of Tennessee Valley Authority (TVA) easement restrictions. There can only be a certain amount of fill placed under the power lines, but we needed a slope and creek bottom to bury the lines. The toe of the levee needed to be at least 10 feet from the fissure, which was running at a 45 degree angle towards the TVA easement. This was a critical element as the levee had to fit between these two constraints and the pinch point was where the levee was at its greatest height. Also, when we started the final levee construction, we had to take out the temporary levee, so there was a period of time when the quarry was highly exposed; a significant

126

showcase 4

rain event would have flooded it. Luckily it didn’t, which was extremely fortunate. This project’s complications were compounded by public concern over the location of Richland Creek. How did you address those concerns?

Ted: On the levee side, we were able to keep pushing the project forward because there were no other options. There was a very vocal group from the Richland Creek area that wanted the creek to go back to the way it was before. We had many conversations and meetings to explain that we couldn’t put it back where it was because that didn’t exist anymore. Once we showed them pictures of where the creek used to flow, we were able to explain how the creek we were going to put back would be environmentally improved. The use of graded rock allowed for the smallest possible footprint for this levee configuration. It also provided overbank area from the relocated creek channel that could be used for habitat pools and trees and other plantings to enhance the creek and overall stream development. It would be the same length or longer, have natural trees and native

plantings. We wanted to make it as pristine as a creek could be. Which aspect of this project had the most impact on you?

Ted: I’ll never forget that first time I went to the site and saw the quarry full of water. The wind was blowing pretty stiff, and there were white caps on the water and ducks floating in it. It was literally a huge lake. I’ll always remember watching the transformation as the water was pumped out. It was pretty amazing. Ken: You don’t run across this kind of project very often. The scope and urgency made it extremely challenging. We have deadlines with other projects, but nothing of this magnitude with so many site concerns related to timing and flooding. What are you most proud of in this whole project as far as your personal involvement?

Ted: This was such a unique project. Just the fact that we pulled it off is a great feeling. The client was very stressed because his asset, the quarry, was exposed for a long period of time. He was really counting on us to get the job done. Even though they are a


The path of the quarry access road before the flood.

When the water level began to subside, the extent of the damage to the existing terrain was evident. The force of the water had removed five feet of material that was once the creek bottom, the previous natural solid rock barrier, all the material within the fissure and the wall of quarry supporting the road. Many local residents struggled to understand that returning the creek path to its original place was impossible.

gresham, smith and partners

127


The construction of the levee continued until it reached the elevation of the 1,000-year rain event. The clay core is 15 feet wide at the top and is covered with a load distributing geotextile fabric and an interlocking rock layer. The upstream armoring stone consists of angular limestone material ranging in size from 12” up to 36”. The material is free draining to allow for the rapid draining of the water after flood events to limit infiltration into the clay core.

concrete barrier

1

Riding surface shot rock berm fill

richland creek

Select berm fill

CLAY CORE FILL

sewer line

construction company, they couldn’t design it themselves. They could’ve called many engineering firms to help, but they called us. That is very gratifying. Ken: The teamwork was amazing. This is the first time I’ve collaborated with Ted and Diane and the transportation group, and they jumped in and helped wherever needed. It just feels good to be a part of a group like that. Working with three different surveyors to gather and organize information so we could produce an accurate design didn’t leave much room for error, but we worked together and made it happen.

128

showcase 4

Concrete encasement

Diane Regensburg: It was also very rewarding to know that we exceeded the owner’s expectations by designing a project that addressed all the site constraints and allowed for construction of the new levee utilizing resources readily available to the owner. Our ability to thread a design solution through the site that used readily available clay and shot rock was a bonus that they did not expect. Most of all, being able to solve a problem caused by the Nashville flood was extremely rewarding. I had personal friends and colleagues who were greatly devastated by the

keyway Depth – 2’ minimum Width – 15’ minimum Length – 600 feet

flood, and I spent many hours helping them recover. Being able to also use my engineering skills to address this problem was professionally fulfilling. I’m very proud of what we accomplished. 


The top riding surface consists of 30” – 36” of surge stone and base materials that will provide the surface for the 170,000-pound trucks working at the site.

2 quarry wall

With the site protected, work to gain access to the lower areas in the quarry continues.

gresham, smith and partners

129


ARCHITEC TURE

ENGINEERING

INTERIORS

PLANNING

Gresham, Smith and Partners provides design and consulting solutions for the built environment that contribute to the success of national and international clients. For more than 40 years, GS&P has focused on enhancing quality of life and sustainability within communities. GS&P consists of industry-leading professionals practicing architecture and engineering design as well as scientists and highly specialized planning and strategic consultants in Aviation, Corporate and Urban Design, Environmental Compliance, Healthcare, Industrial, Land Planning, Transportation and Water Services. GS&P consistently ranks among the top architecture and engineering firms in the United States.

showcase.greshamsmith.com

Š Gresham, Smith and Partners 2011


Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.