IMIESA July 2021

Page 23

WATER & WASTEWATER Mpolweni pump station

Laying the 700 mm diameter steel pipe

Dalton and Wartburg integration A prestressed concrete structure with a flat concrete roof slab, the 10 Mℓ Dalton Reservoir was constructed adjacent to an existing 0.8 Mℓ reservoir that currently supplies the town of Dalton. The 8 Mℓ Wartburg Reservoir was constructed adjacent to an existing 1.5 Mℓ reservoir under a separate contract. The integration of the Dalton Reservoir, the Wartburg Reservoir and the existing 1.5 Mℓ reservoir was added to the scope of the Phase 2 project during the course of construction and required the construction of new chambers, pipework and control systems on the Wartburg site. The development of a complex design and control philosophy allows the three reservoirs to be filled via the Mpolweni pump station in any

combination of one, two or three concurrently. This was achieved by using programmable logic control systems that were configured based on predetermined (but adjustable) settings that allow for the operation of either one or two pumps, and for the speed of the pumps to be varied according to the preset rates – made possible due to the upfront design of VSDs at the pump station.

Steel pipeline The buried pipeline (15.1 km long) comprises a continuously welded 700 mm diameter steel pipe with a 6 mm wall thickness and 3LPE anticorrosion coating. This pipeline connects the new 8 Mℓ reservoir in the town of Wartburg (part of Phase 1) to the 10 Mℓ Dalton Reservoir. During the design phase, a net present value

Pipe jacking in progress

PHASES OF THE UMSHWATHI REGIONAL BULK WATER SUPPLY SCHEME Phase 1: 850 mm diameter steel pipeline (including the new Mpolweni booster pump station) from the existing Claridge Reservoir to Wartburg Phase 2: 700 mm diameter steel pipeline from Wartburg to a new 10 Mℓ reservoir at Dalton, including the new Dingle pump station Phase 3: Bulk pipeline from the Dalton Reservoir, which supplies water through a series of trunk mains to the Nadi and Ozwathini reservoirs, from which Phases 4 and 5 will be supplied

analysis was conducted to determine the optimal pipe diameter, considering the power, capital and maintenance costs of the various diameters and associated pumps. Through this analysis, it was determined that a 700 mm diameter pipeline would offer the best rate of return to the client. When crossing provincial roads and Transnet railways lines, the pipeline construction required the driving of five separate 2 130 mm diameter pipe jacks. Soil testing at the design stage revealed the need for cathodic protection, and this was installed through a specialist subcontractor, with temporary protection being provided during the construction phase. This necessitated the installation of two transformer/rectifier units, as well as test posts and current isolating flanges, along the pipeline route. Regular monitoring of the pipeline during construction and after commissioning of the system ensures that it performs as designed and the pipeline is fully protected. When steel pipelines are located near high-voltage overhead power lines, there is the danger of stray currents from the pipeline earthing through personnel working in the chambers. During the course of construction, following the recommendations of the cathodic protection specialist consultants, a decision was made to retrofit alternating current mitigation (ACM) measures on all chambers on the Phase 2 pipeline. This involved the construction of internal and external earth mats and monitoring points, and cross-bonding the systems to the pipeline and chamber reinforcing. Following the success of the Phase 2 work, a variation order was issued to further retrofit ACM measures on identified chambers on the Phase 1 pipeline. The communities of Mpolweni, Wartburg and Bruynshill can now benefit from an improved, reliable water supply while the vital supply of water to communities in Efaye, Ozwathini and Southern iLembe is now possible.

IMIESA July 2021

21


Articles inside

Admixture accelerators for cold conditions

2min
page 57

Turning concrete waste into a resource

2min
page 54

The FUSO FJ26-280C HYP receives a stamp of approval

6min
pages 50-51

A variety of solutions for driver management

2min
page 53

Lifting with a difference

4min
pages 48-49

Local knowledge key to success of cross border projects

6min
pages 44-45

Affordable technology that builds brick businesses

4min
pages 46-47

Infrastructure news from around the continent

4min
pages 42-43

Inclusionary housing: addressing the elephants in the room

3min
page 40

Youth participation in the social housing value chain

2min
page 41

University switches to green energy

1min
page 39

Working towards a just energy transition

2min
page 38

Substation upgrade for new data centre

2min
page 37

Trenchless techniques are optimal for urban zones

1min
page 35

Energy efficiency starts with consumption

2min
page 36

Riverbank training and protection

4min
pages 28-29

Whistleblowing hotlines for municipalities

5min
pages 30-31

Unpacking barriers for women in construction

4min
pages 32-33

Geogrids in civil engineering applications

5min
pages 26-27

Empowerment through quality, education and training

6min
pages 24-25

uMshwathi Regional Bulk Water Supply Scheme Phase 2

5min
pages 22-23

Asset maintenance is a lifelong journey

4min
pages 18-19

The BUILD programme makes every project count

6min
pages 12-13

The future of surveying

6min
pages 14-16

Editor’s comment

4min
pages 5-6

Repairing concrete with concrete in sewer systems

8min
pages 8-11

The durability of steel for bulk water delivery

4min
pages 20-21

Establishing a new docking site for MSC

3min
page 17

President’s comment

2min
page 7
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.