SWANLEA SCHOOL, LONDON

Often the works we carry out for schools will need to be during their holiday shutdowns.

Advertisement

The timings on this particular school project were extremely tight as we needed to complete the works within a six week period. Our contract was to erect and dismantle scaffolding to facilitate our client to carry out the works required within this time frame. Efficiency was of the upmost importance during this project.

On erection we had two teams on site working day and night, one team starting at 08:00hrs and finishing at 18:00hrs, then handing over to the second team who would finish at 04:00hrs. This gave us the advantage of being operational for 20 hours during every 24 hour period. We also had a team working on Saturdays and Sundays to maximise production.

With careful time management and teamwork, we achieved the successful completion of this scheme and were able to look forward to future projects with this now regular client.

This article is from: