Alabama 03 2016

Page 1

ALABAMA STATE EDITION

231

65

72 Florence

2

Huntsville

20 Decatur

72

565 59

43

A Supplement to:

231

431

31

5

Gadsden

78 59 Anniston

20

Birmingham Bessemer

82 Tuscaloosa

65 280

20 82 Auburn

80

85

Selma

Phenix City

Montgomery

82

February 3 2016

65

231

43 84 431 331

84

84 52

Vol. XXIX • No. 3

31

45

“The Nation’s Best Read Construction Newspaper… Founded in 1957.”

Dothan

65 98

Mobile

10

Your Alabama Connection • Rich Olivier, Atlanta, GA • 1-800-409-1479

Schools Named for Astronauts Take Leaps Forward Named for two history-making astronauts, the new Jemison High School and McNair Junior High are taking shape in Huntsville, Ala. Built on a combined campus off Pulaski Pike, both schools are expected to open in August 2016, and will house students from four existing or recently closed schools. Total cost of the project is $70 million. “Everyone is excited about this,” said Jeffrey Gattis, construction and renovation coordinator for Huntsville city schools. “The way we are doing things is so forward thinking. You’re not going to find anything like it here, or maybe in the entire country. It’s precedent setting.” Gattis said, “The old high school had served its purpose, but it was time to either do a major renovation or construct a new building. This is also part of a U.S. Department of Justice consent order to build a new school.” The consent order required the district to provide more equitable educational opportunities for its black students. In 2014, a federal judge appointed a mediator in the battle to rezone Huntsville city schools. The Jemison-McNair campus can serve 1,100 high school students and more than 500 middle-school pupils, and will have combined space in excess of 331,000 sq. ft. (30,750 sq m). Jemison will serve students from Butler and Johnson high schools, while McNair will host students from the former Davis Hills and Ed White middle schools. “Currently, we are finishing up the concrete block walls, installing brick and stone and have started roofing on parts of the buildings,” said Gattis. “We are finishing up the site grading and roughing-in the MEP.” Construction began in August 2014. Crews have completed the foundations on both buildings, along with the concrete block and floor slabs in the junior high. The floor slabs in the high school also are complete. Gattis said building more than one school at a time is a balancing act. “There are a million things going on all the time. I have a team of architects and engineers and program managers keeping me up to the minute on all things related to the buildings and schedules. It’s very busy. I actually have five buildings across the city going on.”

By Cindy Riley

CEG CORRESPONDENT

Bailey-Harris Construction photo

In total, the project called for approximately 500,000 cu. yds. (382,277 cu m) of dirt to be moved.

The Huntsville school board approved a contract with Auburn-based Bailey-Harris Construction to build the combined Jemison-McNair campus. Rob Flaherty BaileyHarris, senior project manager said, “The schools are side by side, with only a walkway separating the junior high from the high school, so the same activities are basically taking place. We have placed approximately 98 percent of the slab on grade, and have been working diligently in getting our load bearing block walls installed all summer for the entire project.” All load bearing block is complete at McNair, as is struc-

tural steel and joist. In half the junior high, the mechanical, electrical, plumbing and fire sprinkler rough-in is virtually finished. Brick work has begun, and crews should have the buildings in the dry in the next two months. Due to the overall mechanical plan, it will be early January before workers will have conditioned air and be able to start finish trades in the available buildings. At Jemison, load bearing block is complete in four of the five buildings, and crews are working on completing the task on the last structure by the end of November. Structural steel see SCHOOLS page 2


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.
Alabama 03 2016 by Construction Equipment Guide - Issuu