Maungawhau Station CLG September 2025

Page 1


Maungawhau Station Community Liaison Group (CLG) Meeting

17 September 2025

Agenda

Community update

o Helga Sonier

Urban realm & streets

o Opeti Prescott

Fit-out & facilities

o Sylvester de Almeida

Testing & commissioning

o Rachel Blundell

Auckland Council update

o Martin Udale

Questions & Answers

Helga Sonier Community Manager

Community

• VIPs on a train

• CLG hosted for Auckland Transport

• Shifting focus for Link Alliance

• Uptown relationship transition

Next CLG 17 December @ 5:30pm

A celebration

CRL Visitor Centre at Te Manawa

Project Engineer Opeti Prescott

Urban realm

Sylvester de Almeida Maungawhau Fit-out Manager

The last quarter has seen the installation of the giant roller door, lights, audio, hearing loops, and all the architectural features needed to finish off places and spaces.

Station platforms

Both platforms are complete but still fenced off from rail for safety during the testing and commissioning phase.

Ticketing booths and other public facilities are ready to use.

Functional testing will continue and once complete, these facilities can be commissioned.

The SGCC is now occupied by Link Alliance security and train testing teams following final preparations, including painting and decorating.

Rachel Blundell

Head of Communications &

Engagement

Testing & commissioning and wider CRL programme update

Wider CRL programme with AT and KiwiRail:

• Release of network map showing how services will use City Rail

Link and integrate with major rapid bus routes:

• Karanga-a-Hape a key transfer point for E-W and S-C lines

• O-W line will connect Maungawhau to Newmarket

• More new trains have arrived from CAF in Mexico

• Work starting on eight new bridges to replace level crossings in Takaanini and Glen Innes

CRL Testing and Commissioning:

• Testing the Tunnel Ventilation System – with and without trains

• Headway testing completed (timing between trains)

• AOR driver certification and station familiarisation ongoing

• More than 5000km travelled through the CRL tunnels

• Extensive train radio testing completed

• Desktop planning for tests involving emergency services

• Preparations for live tests for normal and degraded operations

Long-term development approach

Auckland Council

Martin Udale

Development sites approach

Oversite Development

• Market as a single precinct

• Foundation Outcomes – sets expectations

• Planning Process - consents

• Land with First Right of Refusal

• Engagement with Iwi

• Market for Development Partner

• Satellite site sales

• Market as sites become available

Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.
Maungawhau Station CLG September 2025 by City Rail Link Ltd - Issuu