Karanga-a-Hape CLG 10 September 2025

Page 1


Community Liaison Group

Karanga-a-Hape Station

• Wider CRL programme and testing & commissioning update

o Rachel Blundell, Head of Communications & Engagement

• Works update and urban realm

o Michael Coup, Construction Manager

• Questions

Wider CRL programme

Testing & Commissioning

Rachel Blundell

Testing & Commissioning and wider CRL programme update

Wider CRL programme with AT and KiwiRail:

- Release of network map showing how services will use City Rail Link and integrate with major rapid bus routes:

- Karanga-a-Hape a key transfer point for E-W and S-C lines

- O-W line will connect Maungawhau to Newmarket

- More new trains have arrived from CAF in Mexico

- Work starting on eight new bridges to replace level crossings in Takaanini and Glen Innes

CRL Testing and Commissioning:

- Testing the Tunnel Ventilation System – with and without trains

- Headway testing completed (timing between trains)

- AOR driver certification and station familiarisation ongoing

- More than 5000km travelled through the CRL tunnels

- Extensive train radio testing completed

- Desktop planning for tests involving emergency services

- Preparations for live tests for normal and degraded operations

Station entrance buildings

Mercury Lane – June 2025

- Roofing Complete

- Membrane Completion

- Northern Laneway Construction Begun

Mercury Lane – September 2025

- Laneway Complete - Planters Complete - Signage Complete

Mercury Lane – June 2025 vs September 2025

- Battens Complete

- Snail Ceiling Complete

- Signage Underway

- PID’s Installed

Mercury Lane Substructure – June 2025

- Escalator Cladding and Fitout

- Tiling B2, B1 and B6

- BOH Fitout

Mercury Lane – September 2025

- Lighting Complete

- Signage Installs Underway

- Commissioning of VT ongoing

Mercury

- Escalator Cladding and Fitout

- Tiling B2, B1 and B6

- BOH Fitout MFH

Mercury Lane – September 2025

- Lighting Complete

- Signage Installs Underway

- Tiles Complete

- Cable Containment

- PID Installs

- Adit 3 & 4 Ceiling Complete

- Adit ¾ Ceiling Complete

- Lighting Complete

- Platforms Signs Complete

Beresford

Square – June

- Scaffold Removal

- Moon Elements Completed

- Escalator commissioning ongoing

Beresford

Square – September

- Ticket Gates Installed

- Fountains Installed

- Signage Installed

- VT Commissioning Ongoing

Urban Realm

Beresford

Square – June 2025

Beresford

Square – September 2025

- Treepit Complete

- BSQ West Complete

- Entrance Complete

June 2025

September 2025

Mercury Lane demobilisation – June 2025

Mercury Lane demobilisation – September 2025

- Adit 1 Complete and Backfilled

- Sheetpiles Removed

Station design elements - Beresford Square bench

From design…

Station design elements - Beresford Square Pou

Pupurangi concept and fabrication

Pupurangi installation progress

Pupurangi completion

The largest shell spans 9.8 metres, the two smaller ones are 6.5 metres across.

Suspended between 7 and 8.6 metres above the ground, the three shells are made up of 225 unique pieces.

Questions?

Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.