HIGHLIGHTS FROM THE YEAR
MARCH JANUARY KiwiRail safely completed 24hour shifts during a Block of Line over the Christmas period. In Mt Eden they prepared the NAL so that a single rail line could run from July 2020.
2020
8
CRL Ltd contributed to the development of panconstruction industry COVID-19 health and safety (H&S) protocols. These supported a safe and successful restart of construction across CRL sites after COVID-19 Alert Level 4 was lifted.
FEBRUARY The last strut was safely removed from Albert Street as part of Contract 2 works. This marked the end of 18-months of high-risk activity successfully completed without incident.
MAY The Link Alliance installed the first water treatment plant at Mercury Lane. These have now been rolled out at all Link Alliance sites.
City Rail Link Limited | Health, Safety, Environment & Sustainability Report 2020
JUNE The first independent annual review of safety maturity for the project was conducted using the Risk Management Maturity Model (RM3).
JULY Six rangatahi joined Link Alliance's Progressive Employment Programme.