(2)
Public Art DWP – there is no identified public art located within or adjacent to the Karangahape Station early works; and Urban Design DWP – an Urban Design DWP will be prepared at the completion of the main construction works for the Karangahape Station. A Construction Environmental Management Plan and the following Management Plans for certification, as required by the conditions of the A2N regional resource consents: (i)
Erosion and Sediment Control Plan;
(ii)
Air Quality Management Plan;
(iii)
Contaminated Soils Management Plan; and
(iv)
Groundwater and Settlement Monitoring and Contingency Plan.
Where the designation and resource consent conditions require Delivery Work Plans and Management Plans to be prepared for the same aspect of environmental management – i.e. Construction Environmental Management Plan, Contamination, and Air Quality – then a combined plan has been prepared addressing the requirements of both sets of conditions. These combined plans are submitted for both Outline Plan and certification purposes. This Outline Plan is submitted under Tonkin + Taylor’s account with Auckland Council, as a member of the Link Alliance. The details of this are:
Account name: Tonkin Account number: 2650624004 PO reference: 1007807.1000R.01
The Link Alliance’s PRR number for processing of this Outline Plan is PRR00032302. Please do not hesitate to contact the undersigned should you wish to discuss any aspect of the documents submitted.
Yours sincerely,
Peter Roan Consents Lead – Link Alliance