21 October 2019 Warwick Pascoe Principal Project Lead Premium Resource Consents Auckland Council Private Bag 92300 Auckland 1142
Dear Warwick, City Rail Link – Outline Plan submission and Management Plans for Certification – Karangahape Station early works Please find enclosed an Outline Plan and Management Plans for the Karangahape Station early works required to enable construction of the City Rail Link (CRL) Karangahape Station. The works relate to utility relocations, tree removal, building demolition and Construction Support Area (CSA) establishment in the vicinity of Beresford Square, Pitt Street and Mercury Lane. The Karangahape Station early works are authorised and provided for by CRL Designation 2500-4 in the Auckland Unitary Plan Operative in Part (AUP), for which City Rail Link Limited (CRLL) is the requiring authority. The works are also authorised by the CRL ‘Aotea to North Auckland Line’ (A2N) regional resource consents. The following documents are now provided: (1) An Outline Plan under section 176A of the Resource Management Act 1991, for works to be undertaken in accordance with CRL Designation 2500-4, including: (a) Communication and Consultation Plan; (b) Construction Environmental Management Plan. (c) Delivery Work Plans: (i)
Social Impact and Business Disruption DWP;
(ii)
Air Quality DWP;
(iii)
Trees and Vegetation DWP;
(iv)
Transport, Access and Parking DWP;
(v)
Construction Noise and Vibration DWP;
(vi)
Historic Character DWP (Built Heritage Section);
(vii)
Historic Character DWP (Archaeology Section);
(viii) Contamination DWP and; (ix)
Groundwater and Settlement Monitoring and Contingency Plan.
The following Delivery Work Plans are also required by the designation conditions, but are not included in the Outline Plan for the reasons set out below: Link Alliance – 100 Carlton Gore Road, Newmarket, Auckland 1023