Construction Noise and Vibration Delivery Work Plan

Page 30

Construction Noise and Vibration Delivery Work Plan

9. Mitigation and Management 9.1 Training All staff will participate in an induction training session when they commence work on the main works. The induction will include a briefing on this CNV DWP, with attention given to the following matters: • • • • •

Roles and responsibilities for management of noise and vibration Construction noise and vibration limits Information about noise and vibration sources on-site Noise and vibration mitigation and management procedures The sensitivity of receivers to noise and vibration (including MediaWorks), and any operational requirements and constraints identified through communication and consultation Complaints management procedures

Awareness of current noise and vibration matters on, or near active worksites, will be addressed during site meetings and/or ‘toolbox’ training sessions.

9.2 Construction Hours 9.2.1. General Timing of Works Table 9-1 shows the general construction hours, and any special conditions related to timing. Table 9-1 Construction hours and conditions that require specific timing

Activity

Days

Times

Condition: Comment

General hours

Monday to Saturday:

0700 – 1900 hrs 1900 – 2200 hrs 0700 – 2200 hrs

31: Prioritise. 31: Minimise where practicable. 31: Minimise where practicable. 31: Avoid where practicable. 35.2: Amended by MediaWorks SSCNVMP in Appendix C1.

Sunday

2200 – 0700 hrs 0600 – 0915 hrs 1600 – 1700 hrs 1730 – 1915 hrs 2020 – 2330 hrs 0900 – 1230 hrs 1700 – 1915 hrs 1700 – 1915 hrs

Piling and road cutting

Monday to Saturday

0700 – 1900 hrs

36.3 (b): Restricted period.

Concrete/rock breaking

Monday to Saturday

Avoid Sensitive Times

35.2A: Within 100m of the MediaWorks building unless monitoring verifies compliance with the limits in Condition 35.2.

Blasting

Monday to Saturday

1032 and 1432 hrs as agreed with MediaWorks

32.6 and 35.10: Avoid MediaWorks Sensitive Times (above) during daylight hours.

MediaWorks Sensitive Times (3 Flower St)

Sundays & Public Holidays All other times (night) Monday to Friday

Saturday

Page 30

| Mt Eden Main Works CNV DWP


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.
Construction Noise and Vibration Delivery Work Plan by City Rail Link Ltd - Issuu