CLG March 2025 Karanga-a-Hape

Page 1


Community Liaison Group

Karanga-a-Hape Station

Meeting Agenda

• 5:30 – Testing and Commissioning – Simon Mitchell, Community Manager

• 5:35 – Station Entrances and Urban Realm – Michael Coup, Construction Manager

• 5:50 – Station Design Elements – Simon Lough, Design & Delivery Manager, City Rail Link Limited

• 6:00 – Karanga-a-Hape Station precinct integration project – Manoj Nathoo, Auckland Transport

• 6:10 – Questions

• 6:20 – End​

Testing and Commissioning

Testing and Commissioning

Highlights since first test train - 12 February

- Checks on the catenary/pantograph interface with the overhead line

- Train clearance at speeds between 5 to 40 kph

- Train journeys at up to 70kph this month

- Certifying train drivers in the CRL tunnels.

Upcoming tests

- Multiple trains

- Regular journey through the CRL, stopping at the new stations

- Noise and vibration

- Tunnel Ventilation System.

Station Entrances

Mercury Lane Entrance Building –

Roof
TVS shaft
West Scaffold Roof

Mercury

Lane Entrance Building – March 2025

- Roofing complete

- Membrane completion

- Northern laneway construction begun

Mercury

- Batten ceiling - Chiller units

- TVS flushing - Balustrade installs

- Ticket gate installs

Mercury

- Platform ceilings - Adit 3 hatches and ceilings - B1 ceilings

Mercury

- Platform ceilings

- Adit 3 hatches and ceilings

- B1 (first level underground) ceilings - Adit 2 GRC arches

- Escalator fitout

Beresford

Square Buildings – December

• Glass canopy install and cladding underway

• Entrance paving complete

Beresford

Square Buildings – March

• Glass canopy install and cladding underway

• Entrance paving complete

Beresford Square below ground – March

- Shadowbox install

- Crossbeam cladding and escalator fitout

Urban Realm

Beresford

Square – December

- Concrete paving base complete

- Pavers - Approx 40% complete

- Vector works complete

Beresford

Square – March 2025

Pitt Street – December

- Station connections ongoing (approx 95% complete)

- Pavement on Pitt Street East complete

- Traffic switch completed and handed to Project K

- Vector 22kV works complete

Pitt Street – March

- Cladding panels for pou installed

- Bollard installs

- Paving ongoing

Mercury Lane – Exterior Works and Station Connections

- Entrance planters underway

- Noise shed removal preparation underway

Station design elements

Beresford Square Entrance Building

Beresford Square Bench

Beresford Square Service Building

Beresford Square Sun and Moon

Karanga-a-Hape Station precinct integration project

Mercury Lane progress

• Western side – laying ducting, installing light pole foundations, preparing base layers of the footpath.

• Karangahape Road frontage – laying ducting, installing traffic light foundations, preparing the new cycle lane.

Pitt Street progress

Works include:

• Installing a new watermain in front of the Fire Station

• Installing new intersection at Poynton Terrace

• Ducting between Poynton Terrace and Karangahape Road

• Tree pit and footpath works between Poynton Terrace and the Methodist Church.

CPTED: Crime prevention through environmental design

Our recommendations:

• Improve lighting:

o Add better pedestrian orientated lighting

o Reinstate streetlights on the northern side of Canada Street and Lower Mercury Lane

o There is a need for lighting to filter down into the Mercury Theatre driveway from the station building

o Install beacons at the Greys Avenue pedestrian crossing

o Ensure existing lights are well maintained and veranda ceiling lights are left on at night

• Install more CCTV cameras to enhance surveillance and deter criminal activity, particularly around the Mercury Lane entrance, behind Beresford Square, and in East Street behind the station

• Provide support on activations to increase foot traffic and for more natural surveillance

• Provide clear wayfinding signage

• Work with Auckland Council to ensure there is a regular maintenance schedule to keep the area clean and free of graffiti.

Questions?

Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.
CLG March 2025 Karanga-a-Hape by City Rail Link Ltd - Issuu