• 5:30 – Testing and Commissioning – Simon Mitchell, Community Manager
• 5:35 – Station Entrances and Urban Realm – Michael Coup, Construction Manager
• 5:50 – Station Design Elements – Simon Lough, Design & Delivery Manager, City Rail Link Limited
• 6:00 – Karanga-a-Hape Station precinct integration project – Manoj Nathoo, Auckland Transport
• 6:10 – Questions
• 6:20 – End
Simon Mitchell, Community Manager
Highlights since first test train - 12 February
- Checks on the catenary/pantograph interface with the overhead line
- Train clearance at speeds between 5 to 40 kph
- Train journeys at up to 70kph this month
- Certifying train drivers in the CRL tunnels.
Upcoming tests
- Multiple trains
- Regular journey through the CRL, stopping at the new stations
- Noise and vibration
- Tunnel Ventilation System.
Michael Coup, Construction Manager
- Roofing complete
- Membrane completion
- Northern laneway construction begun
- Batten ceiling - Chiller units
- TVS flushing - Balustrade installs
- Ticket gate installs
- Platform ceilings - Adit 3 hatches and ceilings - B1 ceilings
- Platform ceilings
- Adit 3 hatches and ceilings
- B1 (first level underground) ceilings - Adit 2 GRC arches
- Escalator fitout
Square Buildings – December
• Glass canopy install and cladding underway
• Entrance paving complete
Square Buildings – March
• Glass canopy install and cladding underway
• Entrance paving complete
Beresford Square below ground – March
- Shadowbox install
- Crossbeam cladding and escalator fitout
Michael Coup, Construction Manager
Square – December
- Concrete paving base complete
- Pavers - Approx 40% complete
- Vector works complete
Square – March 2025
- Station connections ongoing (approx 95% complete)
- Pavement on Pitt Street East complete
- Traffic switch completed and handed to Project K
- Vector 22kV works complete
- Cladding panels for pou installed
- Bollard installs
- Paving ongoing
- Entrance planters underway
- Noise shed removal preparation underway
Simon Lough, Design and Delivery Manager, Link Alliance
• Western side – laying ducting, installing light pole foundations, preparing base layers of the footpath.
• Karangahape Road frontage – laying ducting, installing traffic light foundations, preparing the new cycle lane.
Works include:
• Installing a new watermain in front of the Fire Station
• Installing new intersection at Poynton Terrace
• Ducting between Poynton Terrace and Karangahape Road
• Tree pit and footpath works between Poynton Terrace and the Methodist Church.
Our recommendations:
• Improve lighting:
o Add better pedestrian orientated lighting
o Reinstate streetlights on the northern side of Canada Street and Lower Mercury Lane
o There is a need for lighting to filter down into the Mercury Theatre driveway from the station building
o Install beacons at the Greys Avenue pedestrian crossing
o Ensure existing lights are well maintained and veranda ceiling lights are left on at night
• Install more CCTV cameras to enhance surveillance and deter criminal activity, particularly around the Mercury Lane entrance, behind Beresford Square, and in East Street behind the station
• Provide support on activations to increase foot traffic and for more natural surveillance
• Provide clear wayfinding signage
• Work with Auckland Council to ensure there is a regular maintenance schedule to keep the area clean and free of graffiti.