Fiscal Year 2015 Key Issues Focus: Capital projects throughout the Old Town, Textile Corridor, and Knowledge Park Overhead to underground conversion Minimize outages and improve service
Financial Highlights: Overhead to underground- $346,340 Substation Feeders- $90,000 Line relocations- $90,000
Substation work