ENGINEERING DEPARTMENT
CONSTRUCTION SPOTLIGHT Porpoise Avenue Beach Access Parking A preliminary plan has been completed and a preapplication meeting request has been sent to FDEP. The scope of this project will increase beach access parking by utilizing a pervious paver system like parking areas at Jetty Park and Dreamland Park.
8th Street and Edwards Stormwater Pump Station: A lift station start-up was conducted August 12, 2020 and the final acceptance of the project has been granted. This project will alleviate the repetitive flooding in the 8th Street neighborhood by pumping flood waters into the Edwards Road storm drainage system.