Lennox Village Vision project update
With the Byron Street/Ballina Street intersection now complete and fully reopened, Ballina Shire Council’s crews are focusing on Stage 5 of the Lennox Village Vision project at the Ballina Street and Park Lane intersection.
Stage 5 includes road and drainage upgrades, new paving, and landscaping. This will take six weeks and require a full closure of the intersection to ensure works are completed as quickly as possible.
Northbound motorists need to continue along The Coast Road to access the Lennox Head CBD via Byron Street.
TEMPORARY ROUNDABOUT - BYRON STREET AND BYRON BAY ROAD (THE COAST ROAD)
To assist traffic flow, a temporary roundabout has been installed at the intersection of Byron Street and Byron Bay Road (The Coast Road) for the duration of the works. Changed traffic conditions and reduced speed limits are in place. Please follow all signage.
OTHER TRAFFIC ARRANGEMENTS:
Motorists will be able to enter and exit Ballina Street via Byron Street. U-turn bays will be available on Park Lane and Ballina Street.
Access to businesses on Park Lane will be maintained, however at times access may be changed or unavailable for short periods.
Motorists will need to use alternative parking on either side of the construction zone. Pedestrian access will be maintained, however at times there may be pedestrian detours around construction zones.
The bus stops located on Ballina Street (Lennox Park and Lennox Head Medical Centre) will be relocated to Pacific Parade, opposite The Lennox Hotel.
For more information visit ballina.nsw.gov.au/LennoxVillageVision