Scs fs outline scope of work 11 2m option

Page 1

Shelburne Community School | Outline Scope of Work - $11.2M Option

OUTLINE SCOPE OF WORK – $11.2 M OPTION Part 1 – Demolition a. D-wing (13,405 sf) and E-wing (12,530 sf) open classroom areas (does not include Library): Demolish all interior partitions, movable partitions, suspended ceilings, floor finishes, mechanical, electrical and plumbing leaving only floor slab and exterior envelope construction. Part 2 – Renovations a. Roof Replacement: i. Remove existing membrane and insulation down to the deck. Provide new tapered roof insulation (R-40 avg) over entire membrane roof areas (does not include modular classrooms) 116,530 sq. ft. ii. Replace existing membrane roofing with new fully adhered white EPDM roofing – 123,200 sq. ft. (entire building and modular trailers). iii. Add 6 new roof drains iv. Repair masonry and roof blocking at perimeter of 1967 roof b. 1967 Window Replacement Only: v. Replace all large windows in 1967 portion of building with high performance doublepane low-e aluminum thermal curtain wall system –39 openings vi. Replace all small windows in 1967 portion of building with high performance double-pane low-e windows –4 openings c. Structural vii. Reinforce roof structure of 1967 wing around gym to accommodate potential snow drifting viii. Reinforce roof beam supporting folding partition at large gym ix. Provide structural reinforcement at new rooftop mechanical unit locations d. Architectural x. Provide new walls, doors, and finishes in D&E wings to accommodate new layout of classrooms. This includes, flooring, painting, ceilings, marker boards, tackboards, casework, etc. e. Mechanical, Electrical, Plumbing, Lighting and Fire Alarm Upgrades at D & E Wings Only: i. Mechanical a. Remove existing Air Handling Units (AHU) from D-wing, E-wings. Provide new efficient AHUs on roof. Provide new ductwork throughout. b. Provide displacement ventilation and new fin-tube radiation through D and E Classroom wings c. Perform a more in depth evaluation the heating system in the south end of the 1967 portion of the school to determine the cause for the lack of heat d. Add corridor ventilation in D&E wings. This can be accomplished by new roof top heat recovery units Dore & Whittier Architects, Inc.

G-1


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.
Scs fs outline scope of work 11 2m option by Wind Ridge Publishing - Issuu