Appendix A
Village of Bensenville CY2012 Community Investment Plan Project Information Title Project # Account # Location Department Type Useful Life
Project Snapshot
Stormwater Management Initiatives
Various Village Locations Public Works Stormwater 50+ Years
CY 12 Total Cost: $200,000 Description Stormwater issues have plagued the Village. This project consists of developing a stormwater plan to identify the areas of greatest need and identify the most cost effective methods to reduce the impacts. The Residential Drainage program provides up 50% assistance to our residents who would like to address flooding issues on their property.
Justification Reduction of the impact of stormwater on the residents of the Village is a priority of the Village. Implementing the most cost effective projects can only be accomplished by identifying the most impactful and cost effective projects.
Capital Expenditures Stormwater Initiatives 50/50 Program
Prior ‐ ‐
2012 150,000 50,000
2013 150,000 50,000
2014 150,000 50,000
2015 2016 150,000 150,000 50,000 50,000
Total 750,000 250,000
Total Expenditures: ‐
200,000
200,000
200,000
200,000 200,000
750,000
Prior ‐ ‐
2012 ‐ ‐
2013 ‐ ‐
2014 ‐ ‐
2015 ‐ ‐
2016 ‐ ‐
Total ‐ ‐
Total Revenues: ‐
‐
‐
‐
‐
‐
‐
Revenues Sales Tax G.O. Bonds
Impact on Operating Budget Initiatives will be funded through the Capital Plan and not affect the operating budget.
156