2017 0216 roark prof portfolio

Page 7

ITEM 1 :: ALTERNATE FLOOR PLAN AS DESIGNED

ITEM 32 :: MOVE CURTAINWALL AS DESIGNED

ITEM 1 :: ALTERNATE FLOOR PLAN MODIFIED

SECTION THRU CURTAINWALL

ITEM 32 :: MOVE CURTAINWALL MODIFIED A (INBOARD COLUMNS)

SECTION THRU CURTAINWALL

PLAN OF CURTAINWALL

PLAN OF CURTAINWALL

ITEM 22 :: DELETE ELEVATORS / REDUCE PENTHOUSES AS DESIGNED

The schematic design package resulted in a $30 million delta for cost estimates. The GC provided a list of potential VE items. We explored each and every one to show the clients how such savings would affect the design intent.

ITEM 22 :: DELETE ELEVATORS / REDUCE PENTHOUSES MODIFIED

Recommend VE Solutions

Based on the studies contained herein and the VE analysis prepared by Shelco on 11.5.2014, the following represents our recommendation on how to best incorporate the accepted VE options

1. Delete two 30’ bays 4E. Reduce precast returns from 2’-2” to 4” and retain precast edging 5. Provide open stair/elevator at parking garage

In the end, we prioritized a list of potential solutions that would move the project onto its budget without sacrificing our design intent. Though many things would change, the core principles lasted from concept to final product.

6. Use MetroMont alternate thin brick wall design for parking deck 18. Delete PV array and sawtooth roof 22. Delete service elevators and reduce penthouse elements 23B. Reduce eyebrow element from 12’ to 7’ 26. Deleted sunshades 29. Delete balconies from end of building 32. Maintain outboard columns at curtainwall condition. Reduce basement area so that total rentable area is no more than 450,000 sf rentable 34. Modify parking deck spandrel to eliminate aluminum tube rail **reduce floor to floor heights from 14’-8” to 14’-0 typical. Lobby to be 18’-0”

all images property of tvsdesign.


Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.