SECTIONIMPROVEMENTS PUBLIC TITLE FUND PROJECTS: OTHER Capital Project: Medians and Entryways Lighting and Landscaping

DESCRIPTION This budget item provides funding for median landscaping on currently non-landscaped roadway medians within the Town.

PURPOSE/DISCUSSION The Town currently has a backlog of non-landscaped medians within the Town. These include (but are not limited to) Mainstreet from Chambers Road to Bradbury Ranch Drive, Jordan Road from Mainstreet to Bradbury Parkway, Jordan Road from Cedar Gulch Parkway to Bradbury Parkway and Twenty Mile Road from Pony Express Drive to Bar CCC Park. Town Council previously provided direction that the next unfinished median to receive landscaping is the Lincoln Avenue median between Keystone Boulevard and Jordan Road. The concrete work to accommodate planned improvements on Lincoln Avenue was completed in the first half of 2019 and the landscaping will follow. A water source for this location will need to be acquired from the Stonegate Village Metropolitan District (SVMD) to support this median landscaping. Over the past several years, the Town has received complaints from residents relating to the unfinished median. It is an entry point into the Town’s incorporated boundary on Lincoln Avenue from the west.

PROJECT BUDGET Year Actual 2019 Projected 2020 Budgeted 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 TOTAL

Expenditures $ 534,627 25,000 300,000 300,000 300,000 300,000 300,000 300,000 300,000 300,000 300,000 300,000 $ 3,559,627

FUNDING SOURCES Public Improvements Fund Revenue; some locations have funds from adjacent developments in a reserve account for this purpose

IMPACT ON OPERATING COSTS Based on the size of this median island, it is anticipated to cost approximately $10,000 per year for a maintenance contract service. In addition, the water needed to irrigate these medians would run approximately $5,000 per year.

IMPACT ON OTHER DEPARTMENTS None

TOWN STRATEGIC GOALS ACHIEVED Enhance Economic Vitality This program’s improves the aesthetics of the Town’s roadway network and complements adjacent commercial development.

Develop a Visionary Community Through Balanced Growth This program’s effort is part of the needed infrastructure to support the planned development of the Town. Median landscaping infrastructure creates a sense of place that can help tie the community together.