SUITE 3100 - 34,080 RSF FORTRESS SOLUTIONS 10/31/2029 as of 7/31/24
WATERS RIDGE II
1965 LAKEPOINTE DRIVE, LEWISEVILLE, TX 75057
LEASED
SUITE 200- 11,194 RSF
HOYA OPTICAL LABS 10/31/2025 as of 7/31/24
LEASED
SUITE 100- 22,152 RSF HORIZON HEALTH CORPORATION 7/31/2024
WATER S R IDG E II I
1825 LAKEWAY DRIVE, LEWISVILLE, TX 75057
LEASED
SUITE 200 OCCUSYSTEMS
10,386 RSF
LEASED
SUITE 400 - 15,814 RSF K12 VIRTUAL SCHOOLS 6/30/2025
VACANT
SUITE 300 - 5,783 RSF
LEASED
SUITE 500 - 12,344 RSF FORD MOTOR 11/30/2025
LEASED
SUITE 100
6,300 RSF
CARDINAL TRACKING
8/31/2024
2/28/2029 as of 7/31/24
LEASED
SUITE 700 - 19,389 RSF ALLEGIANCE TRUCKING 5/31/2025
VACANT
SUITE 800
5,071 RSF
THIRTY-FOUR
17 110 DALLAS PKWY
17110 D A LL AS PKWY
ASSET MANAGEMENT REPORTS
CONSTRUCTION/ TENANT IMPROVEMENTS
CONSTRUCTION PROJECTION
OVERALL SUMMARY
CONSTRUCTION PROJECTION
OVERALL SUMMARY
CONSTRUCTION PROJECTION
ALPHA PLAZA
Property: Parkway Plaza
Project: Vanilla Box
Suite: 110
GC: TBD
Cost: $32,312.63
Cost PSF: $13.34/SF
SF: 2,422
Status: Need approval
CONSTRUCTION PROJECTION
ALPHA PLAZA
Property: Alpha Plaza
Project: Vanilla Box
Add RR + HVAC
Suite: 120
GC: TBD
Cost: $55,965.25
Cost PSF: $23.55/SF
SF: 2,376
Status: Complete
CONSTRUCTION PROJECTION
ALPHA PLAZA
Property: Alpha Plaza
Project: Vanilla Box
Add RR + HVAC
Suite: 120
CONSTRUCTION PROJECTS
BENT TREE PLACE
Property: Bent Tree Place
Project: Spec Suite
Suite: 160
Cost: $84,770.52
Cost PSF: $42.73/SF
SF: 1,984
Status: Complete
CONSTRUCTION PROJECTS BENT TREE PLACE
CONSTRUCTION PROJECTS
BENT TREE PLACE
Property: Bent Tree Place
Project: Spec Suite
Suite: 205
Cost: $73,225.00
Cost PSF: $53.37/SF
SF: 1,372
Status: Complete
CONSTRUCTION PROJECTS
BENT TREE PLACE
WAYFINDER PACKAGE BENT TREE PLACE
WAYFINDER PACKAGE BENT TREE PLACE
WAYFINDER PACKAGE BENT TREE PLACE
CONSTRUCTION PROJECTS
BENT TREE PLACE
Property: Bent Tree Place
Project: Spec Suite
Suite: 212/215
Cost: $330,200.00
Cost PSF: $50.00/SF
SF: 6,604
Status: In Pricing
DOOR SCHEDULE
BENT TREE PLACE
DOOR SCHEDULE
BENT TREE PLACE
FCU REPLACEMENT
BENT TREE PLACE
ASSET MANAGEMENT REPORTS
1 LITIGATION – N/A 2 JPMORGAN INVESTMENT SUMMARY
ASSET MANAGEMENT REPORTS
OLD BUSINESS
CORPORATE TRANSPARENCY ACT
UPDATE:
1. Beneficial Ownership Information (“BOI”) reporting under CTA went into effect January 1, 2024, despite numerous calls for delaying the effective date of this new law.
2. The U.S. Dept. of Treasury and Financial Crimes Enforcement Network (FinCEN) did provide a reprieve for 2024 created companies to 90 calendar days instead of the initial 30day period to file its initial BOI report. This applies to new companies in 2024 only, and not for any years beyond 2024.
3. Any change in the initial reported information in the initial BOI or its beneficial owners, including change of addresses, requires the filing of a new BOI within 30 days of the changes.
4. There are still unresolved issues to be resolved. There are too many to list here.
5. CPAs are generally not filing these reports because of “unauthorized practice of law” concerns that have still not been resolved in many states.
KPH PROPERTY TAX RESERVE ANALYSIS
2025 BUDGET UPDATE
TIMELINE
1.
ASSET MANAGEMENT REPORTS
NEW BUSINESS
INSURANCE RENEWAL PROCESS
1. 24-25 Insurance Renewal for 52 Management, LP
(Renews November 1st, 2024)
• Lockton sent the submissions out to the insurance marketplace last week and have begun receiving initial feedback. They will send an updated marketing log to us in the next few days to update us on the status.
• The renewal meeting is scheduled for Monday, October 14th, at 1:00pm CT at our office. The Lockton team along with the Producers will all be in attendance that day.
2. Cyber Liability Policy Renewal
Renewal documents are currently with Quinton Skinner at Finite Consulting and stated they would be returned this week. The deadline is 09/02/24. Once received, I will email to David Adugna at Lockton. UPDATE: