12272017 business

Page 1

business@tribunemedia.net

WEDNESDAY, DECEMBER 27, 2017

$4.39

$4.49

Sarkis in $2.25bn claim against Baha Mar builder By NEIL HARTNELL Tribune Business Editor nhartnell@tribunemedia.net

S

arkis Izmirlian yesterday launched a $2.25 billion damages claim against Baha Mar’s main contractor, accusing it of “one of the largest construction-based frauds in this hemisphere”. The $4.2 billion project’s original developer, in a lawsuit filed in the New York State Supreme Court, alleged that China Construction America (CCA) and its subsidiaries perpetrated a “massive” scheme of “cover up”, “deceit”, “outright sabotage” and lies to both conceal its failures and “extort more money than it earned”.

* Claims ‘one of hemisphere’s top building frauds’ * CCA tried to ‘extort more money than was due’ * Says contractor never planned to hit deadline The action, filed in the name of Mr Izmirlian’s BML Properties vehicle, claims that the Chinese state-owned construction firm deliberately concealed its intention to use Baha Mar as “a massive training exercise” that ultimately doomed the project to failure. Besides alleging that CCA’s “real intent” was never to complete Baha Mar “on time and on budget”, Mr Izmirlian and BML Properties also claim that it falsified and misrepresented reports on the

mega resort’s construction progress and the size of its workforce. The claim, for breach of contract and fraud, alleges that the Chinese contractor earned “tens of millions, if not hundreds of millions” more than it should as a result of uncorrected defects plus inflated and “sham” billings. And the lawsuit also details numerous alleged construction defects that, if not caught, would have compromised the health SARKIS IZMIRLIAN

SEE PAGE 2

$4.39

$4.39

Sarkis says CCA misused my $54m to acquire Hilton By NEIL HARTNELL Tribune Business Editor nhartnell@tribunemedia.net BAHA Mar’s original developer yesterday accused the project’s main contractor of misusing a disputed $54 million payment to finance its British Colonial Hilton acquisition. Sarkis Izmirlian, in a $2.25 billion damages claim against China Construction America (CCA) and its Bahamian affiliates, alleged that the contractor used funds intended to “accelerate” its work at Baha Mar to instead fund the purchase of its downtown Nassau property. Mr Izmirlian and his BML Properties vehicle are claiming that the misuse of the $54 million, which

* FUNDS SUPPOSED TO ‘ACCELERATE’ BAHA MAR WORK * REJECTS CONTRACTORS ‘OVERTIME’ PAY EXPLANATION * CLAIMS MISLED OVER POINTE ‘DIVERSION’ was to cover construction ‘change orders’ that the developer believed cost “significantly less”, amount to “yet another act of fraud” perpetrated against it. They are also alleging that CCA’s chief executive

SEE PAGE 3

Sarkis alleges multiple construction defects By NEIL HARTNELL Tribune Business Editor nhartnell@tribunemedia.net BAHA Mar’s original developer yesterday revealed multiple alleged construction defects that could have endangered guests and staff at the $4.2 billion project. Sarkis Izmirlian, in a $2.25 billion damages lawsuit against China Construction America (CCA) and its Bahamian affiliates, alleged that the development’s main contractor failed to inform Baha Mar Ltd of these problems “accurately or at all”. As a result, the thendeveloper and his management team were never informed about

* Lists numerous safety threats not reported * Claims CCA got ‘millions’ it didn’t deserve * Works Ministry noted ‘alarming level’ of woe

resistant material at the convention centre. Fire alarm system testing for the elevators was another problem.

how CCA was charging them (and their $2.45 billion construction loan) for problems it should pay to remedy. They were also unaware of work schedule changes required to fix these woes, which delayed the construction completion and helped to miss two opening deadlines. This, Mr Izmirlian alleges, resulted in CCA earning potentially “hundreds of millions” that it did not deserve. Among the problems alleged by Mr Izmirlian and

* “Defective” interiors in hotel rooms and corridors. Mr Izmirlian alleged that CCA failed to properly seal the drainage connections for 200 bathtubs in the Rosewood property, “meaning that any water on the bathroom floor drains into the ceiling of the room below”. * Bamboo strand flooring was installed in all guest bedrooms and suites without being properly acclimated and no environmental control, “resulting in warped flooring in 70 per cent” of the units.

his BML Properties in their lawsuit were: * Defective tower railings, which could result in them “snapping under minimal pressure, such as a human leaning on them 25 floors up”. * CCA allegedly “improperly installed miles of fire alarm cabling” through the hotels without placing it inside a fire-resistant conduit, and tried to bill Baha Mar for this despite being in non-compliance with the Bahamas Building Code.

Mr Izmirlian alleged the contractor tried to overbill him for this work by $475,000, while the developer “incurred the expense of hundreds of man hours” to remedy the problems, costing it $130,000. * The original Baha Mar developer alleged that CCA’s fireproofing work at the project was also “of poor quality”. He referred to reports by Bahamian engineering firm, Graphite Engineering, that the contractor had failed to resolve defects in the sprayed fire

* In the Grand Hyatt, Mr Izmirlian and BML Properties claim that millwork was not installed with proper environmental controls, leading to “the louver detail of bathroom doors splitting in over 80 per cent of the rooms”. * CCA allegedly “compounded” its original error in “incorrectly screeding” the SLS hotel’s corridor floors by spraying water on the screed during curing, thereby allowing mould and other “microbial growth” to be absorbed into the baseboard and sheet rock. * Water intrusion issues impacted Baha Mar’s development throughout construction, according to

SEE PAGE 6

TAXPAYERS ‘DODGE BULLET’ ON $65M LUCAYAN DEAL By NEIL HARTNELL Tribune Business Editor nhartnell@tribunemedia.net BAHAMIAN taxpayers “will dodge a bullet” if the Wynn Group can complete its $65 million ‘all-cash’ Grand Lucayan purchase, a prominent QC says. Fred Smith QC, the Callenders & Co attorney and partner, told Tribune Business he was “overjoyed” that the Government will seemingly not have to acquire Freeport’s ‘anchor resort’ itself, thereby sparing the Public Treasury from having to both finance the acquisition and

* QC ‘OVERJOYED’ IF WYNN PURCHASES CLOSES * APPROVAL ‘CONDITIONED’ ON SUNWING/MEMORIES TIE-UP * DPM SAYS LOI SHOWS ‘LIGHT AT TUNNEL’S END’ subsequent maintenance/ operating losses. But he also described the Wynn

SEE PAGE 4

SARKIS: CCA’S ‘UP FRONT’ FAILURE COST OVER $50M By NEIL HARTNELL Tribune Business Editor nhartnell@tribunemedia.net BAHA Mar’s original developer yesterday alleged that the project’s main contractor cost it more than $50 million by failing to deliver on its ‘up-front’ obligations. Sarkis Izmirlian, in a $2.25 billion damages claim filed against China Construction America (CCA) in the New York Supreme Court, claimed that despite receiving up to $210 million prior to starting work the contractor only delivered on 75 per cent of its commitments. These obligations related to CCA’s

* FAILED TO DELIVER DESPITE $210M AT START * INADEQUATE STAFF DESPITE $83M FOR LABOUR * FELT CONTRACTOR ‘IN OVER HEAD’ FROM 2012 General Conditions Work Package (GCWP), but Mr Izmirlian and his BML Properties vehicle alleged that it failed to perform by

SEE PAGE 5

Use your Fidelity Credit or Prepaid Card

EARN DOUBLE REWARD POINTS NOVEMBER 1ST - DECEMBER 31ST

Shop. Save. Enjoy. Nassau: t 356-7764 Freeport: t 352-6676/7 Marsh Harbour: t 367-3135


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.