UPDATE 05 DECEMBER 2022
CONSTRUCTION
Monday December 5, 2022, a major concrete pour to complete the Community floor area is underway. A convoy of over 70 trucks delivers the concrete under the watchful eyes of the TFA Construction team.





7am December 05 2022

By 7am progress of the concrete pour can clearly be seen as the crew screed back from the existing pad


A lot has been achieved in just in just 9 months.



7am
March
December 05 2022
2022
By 3pm, job well done with a few of the crew remaining to complete the finishing touches. The entry ramp to Community building will be built to the bottom right.
The existing temporary construction buildings will eventually be removed to accommodate this entry point.



3pm December 05 2022


commenced for the Masjid Building. 2 2 3 4 5 6 7 7 7 1 1 Janazah foundations under construction Community building floor now complete. 4 Entry ramp yet to be built. 3 Kitchen, Cold Store and function hall walls being erected. Water Tank 5 Masjid foundations commenced 6 7 Northern boundary retaining wall
Floor plan shows the complete foot print with the Community Centre at top of page.