CONSTRUCTION UPDATE 6 FEBRUARY 2023
We have already made a great start to 2023. The permitter wall and footings for the Majid are nearing completion with foundation works well under way. Half of the podium has been formed and with scaffolding removed you can now see the scale of the building which is clearly demonstrated with the ladies car park.
the
Work is well underway on
Majid foundations Ladies car park
Podium & car ramp access to community building and parking
First level community building. Ladies car park below
Mosque podium& parking
Mosque foundation aera