A COMPLETE RENEWAL OF THE CAPACITIES FOR THE SWH

We Started A New Project For A Complete Renewal Of The Capacities For The Swh

Our goal is before 2026, to have an annual capacity of:

Advertisement

• 120,000 enamelled SWH, up to 500 litres

• Plus 10,000 SWH, from 800 to 2000 litres (enamelled and buffered in total)

The indicative term for the implementation of the project is 3 years and is divided into 4 stages:

Phase 1. New enamelling line 3, including chemical cleaning, application and heat setting.

Phase 2. Increasing the capacities for the production of coils.

Phase 3. A new line for final assembly for the SWH.

Phase 4. A new line specialised for the production of buffers only.

The project is going to be implemented with the joint efforts of the following departments: “Production of SWH”, “Strategic investment projects”, IPDQ and “Product management”. The project manager is going to be Krasi Kolev. During the implementation, we are going to produce buffers using the spare capacities of the new heat pump plant, the upgraded enamelled SWH line and the electrical water heaters factory.