CM 3111 Module 2 Quiz Construction Estimating (Grade 100.00 out of 100.00) NEW UPDATE 2025-2026 Louisiana State University Module 2 Quiz Status
Finished
Started
Sunday, November 2, 2025, 12:06 PM
Completed Sunday, November 2, 2025, 12:09 PM Duration
3 mins 38 secs
Points
20.00/20.00
Grade
100.00 out of 100.00
Question 1 Correct4.00 points out of 4.00Flag question Question text During the construction of a recent office building, your company’s framing crew installed 515 lineal feet of 8-foot-high, metal-stud wall in two days. The crew consisted of two carpenters and one helper and worked eight hours per day. Determine productivity rate in labor hours per foot of wall for installing metal-stud walls on this project.
Question 1Select one:
a. 0.093 lhr/lft
b. 0.084 lhr/lft
c.