Sizewell C Monthly Update May 2025

Page 1


SIZEWELL C UPDATE

Preparation for the Friday Street Roundabout is ongoing. A works compound has been established and the vegetation and tree clearance along the A12 is almost complete. Site preparation along the route of the two village bypass around Farnham and Stratford St Andrew is also ongoing, and Yoxford Roundabout is being prepared for construction.

Planned Openreach works for diverting cables along the B1122 will require two-way traffic signals to manage traffic flow. Work will take place between the end of May and 2 June.

A works compound has been established at the Western end of the Sizewell Link Road beside the A12. Preparation work on our two park and ride sites continues, with construction due to begin this summer. We will be installing average speed cameras along the B1122, between Yoxford and Leiston, and the B1125 from Westleston, from the end of May. The speed limit along the B1122 is 30mph and is fully enforceable.

Railway track improvements along the Leiston branch line continue. The first freight trains are set to arrive at site this summer. These trains are for the construction works and have already started. Site deliveries for works not associated with construction of the rail project will commence Q1-26.

We are aware that the Dunwich Dynamo takes place on Saturday 12 and Sunday 13 July. The closure of Willow Marsh Lane will require cyclists to take the official diversion which is in place. We will actively communicate this diversion on social media. GPS maps have been updated and will enable riders to follow the designated route..

The Sizewell C team will be at the Suffolk Show on Wednesday 28 and Thursday 29 May. We are located at 219 Flower Show Avenue. You’ll be able to talk to the team about current works, speak to our archaeologists about what they’ve found, and you can learn more about our construction project in virtual reality. Further information about jobs and careers at Sizewell C will also be on offer.

MAIN DEVELOPMENT SITE

OVERVIEW

Marsh Harrier Reserve Project
Campus
(TCA) Temporary Construction Area
(MCA) Main Construction Area
Sizewell B Power Station
Sizewell A Power Station s Lane
Sizewell
(ACA) Ancillery Construction Area
Sizewell Branch Rail Line
Leiston Dunwich
Sizewell Link Road
Yoxford Roundabout

ANCILLARY CONSTRUCTION AREA (ACA)

Work continues in and around the main site. Earthworks are currently taking place on the Ancillary Construction Area on the outskirts of Leiston, and we are building roads around the site. The bus services are also up and running.

The first trains carrying ballast for the rail heads on the Ancillary Construction Area have arrived, with construction starting later this year.

First trains carrying ballast arrive at the ACA
Sizewell
Sizewell

TEMPORARY CONSTRUCTION AREA (TCA)

On the Temporary Construction Area we are continuing with earthworks and preparations for the construction of the SSSI bridge, which includes the installation of sheet piles to protect the environment. We’ve installed acoustic fencing around protected woodlands on the Temporary Construction Area. The fencing will mitigate noise while helping to support wildlife. For example, it’s been designed to accommodate bat migration.

Theberton
Lover’s Lane

OFF-SITE

INFRASTRUCTURE OVERVIEW

Orford
Woodbridge
Kesgrave
Saxmundham
Thorpeness
Farnham
Snape
Wickham Market
A12
A12
East Su olk Rail Line
Orwell Logistics Park
Southern Park & Ride (Wickham Market)
Northern Park & Ride (Darsham)
Two Village Bypass (Farnham & Stratford St Andrew)
Sizewell Branch Rail Line
Leiston
Dunwich
Sizewell Link Road
Yoxford Roundabout

WORKS IN AND AROUND LEISTON

The site of the plaza roundabout, which will connect the main entrance of Sizewell C with the B1122 Abbey Road and Eastbridge Road, is being prepared for construction. Work includes site establishment, root removal from previous cut vegetation and utility diversionary works.

In June, we will start work on the new Lover’s Lane and Abbey Road junction, which enables the subsequent construction of a level crossing for the Green Rail Route.

The roundabout will be completed in early 2026.

Community Road Improvements

We are installing average speed cameras along the B1122 and B1125 to further enhance road safety in the new 30mph speed limit.

We are upgrading the temporary Sizewell C A-frame signs across the county along the A14, A12 and local roads to be permanent signs mounted on posts. An existing layby on the northbound carriageway of the A12, near the B1078, will be upgraded to accommodate Abnormal Indivisible Loads (AIL). This is to enable us to manage our wider load HGV

movements that are escorted by the police to and from site.

In Autumn 2026 we will start road improvements along the B1122 and B1078, along with the B1078/A140 and B1119/A12 junctions. Further details and updates will be given to communities as the works programmes are finalised.

Average speed cameras on B1122 & B1125

TEMPORARY SEA DEFENCE

Construction of the northern section of the temporary sea defence will begin at the end of May. Sheet piles will be installed over the next few months. The public footpath will remain open throughout. We apologise for any noise disturbance.

SIZEWELL BEACH

Two small storage compounds have been set up on the shoreline of Sizewell beach. These areas have been fenced off and will not affect the public footpath. These will be used for temporary marine outfall install.

Sizewell beach

STATUTORY HARBOUR AREA

We have submitted planning permission to replace the beach sign with important information about our marine activities -as well as content contained in the existing sign. The new sign will show how these activities will be managed under our Statutory Harbour obligations.

Neil Glendinning, Sizewell C Habour Master

NORTHERN PARK & RIDE

(DARSHAM)

Works on the Northern Park and Ride in Darsham continue. The first stage of construction will be to build the roundabout that will link the park and ride to the A12. From May we will be installing welfare cabins, and diverting utilities along the A12. This work will require a temporary speed reduction along the A12 to 30mph, and some traffic light management will be required. A 30mph speed limit will be introduced along the A12 north of the Darsham station level crossing to ensure road safety whilst HGV movements are made during the construction of the Park and Ride roundabout.

Work continues at the Northern Park & Ride

Darsham
A12
Northern Park & Ride (Darsham) Dunwich
Sizewell Link Road
Yoxford Roundabout

SOUTHERN PARK & RIDE

(WICKHAM MARKET)

Our archaeologists continue their work on the Southern Park and Ride which is expected to conclude this summer. As archaeology is completed, areas will start building work from the summer. There are on-going works to realign BT Openreach network wires along the slip road, which are expected to run to the end of May.

Farnham
Snape
Wickham Market
Southern Park & Ride (Wickham Market)
Two Village Bypass (Farnham & Stratford St Andrew)
Archaeologists at work on the Southern Park & Ride

ORWELL LOGISTICS

K

The Freight Management Facility at Orwell Logistics Park is now operational. The facility is a vital part of how we manage our lorries and goods travelling to Sizewell. The Freight Management Facility will be for HGVs to check-in and be security checked before going to site.

Orwell Logistics Park also has office space for the project. This helps to distribute our workforce across the region, therefore reducing the number of workers in Leiston. The first team of workers that had been based in Leiston have now started at the site.

Orwell Logistics Park
Orwell Logistics Park offices

SIZEWELL LINK ROAD

We have now created all the required accesses at the sites to build the Sizewell Link Road, while archaeology and vegetation clearance works continue . Main construction works will commence in phases as archaeology progresses throughout the site.

A 30mph speed limit has been implemented along the A12 between Yoxford and Saxmundham. This limit is to ensure road safety as HGVs will be turning onto site at the SLR and at the Yoxford Roundabout.

Saxmundham
A12
Sizewell Branch Rail Line
Sizewell Link Road
Archaeology on the Sizewell Link Road

FRIDAY STREET

ROUNDBAOUT & TWO VILLAGE BYPASS

(FARNHAM & STRATFORD ST. ANDREW)

Preparations for the new Friday Street roundabout have started. We have now established the required site accesses, installed fencing and built compounds for worker welfare facilitates. The archaeological works have also begun at the Friday Street site.

Work begins at Friday Street

Farnham
Snape
Wickham Market
Southern Park & Ride (Wickham Market)
Two Village Bypass (Farnham & Stratford St Andrew)

YOXFORD ROUNDABOUT

Early earthworks at the Yoxford roundabout will start later this year, which will include bringing the level of the site nearer to the current A12 level. During this first phase of construction, we will need to transport surplus earth to the Sizewell Link Road site along the A12.

From 31 May to 2 June Openreach will be undertaking works at Middleton Road in Yoxford to move their cable to underground. This will require temporary traffic lights which will be operational between 8am and 5pm. The lights will be manually operated to allow traffic to flow with minimal congestion. The final works on 2 June will be to remove telegraph poles.

The roundabout will be connected to the A12 later this year. The work will be completed in phases and we will keep you informed of works and dates as they develop.

Work continues at the Yoxford roundabout

Darsham
A12
Northern Park & Ride (Darsham) Dunwich
Sizewell Link Road
Yoxford Roundabout

RAILWAY SCHEMES

Rail works continue with the first trains beginning to move down the Leiston branch line to bring materials to the Ancillary Construction Area and Buckleswood Road compound. This will mean we can begin upgrading the track from June. We have set up a new compound for the rail works at Leiston Airfield which we will share with Scottish Power Renewables. This area, which includes welfare facilities, will be where workers park. The site will mean less worker traffic will need to go through Leiston. A programme of level crossing upgrades along the Sizewell branch line will start in August, which will be done in stages to minimise the impact on the local community.

Works on the East Suffolk branch line, which runs between Ipswich and Lowestoft, include level crossing improvements and track upgrades which were completed earlier this year. We will be conducting surveys during the summer at Darsham Station and Melton Station level crossings, where the works will start in 2026. Network Rail will also be delivering upgrades to other level crossings on the East Suffolk branch line from Q3 2025.

Essex and Suffolk Water will be carrying out works at the Saxmundham level crossing which will require traffic management and possible road closures. There will also be works carried out at the Leiston Level Crossing, which will also require traffic management.

Saxmundham
A12
Sizewell Branch Rail Line
Leiston
Sizewell Link Road
First trains bring material to the ACA

FORUM SCHEDULE

(arrival from 18:00)

All meeting papers and slides can be accessed on our website. If you have any questions or would like any further information please do not hesitate to contact us. We are available in person at the Information Office on the High Street in Leiston Monday –Friday 09:30 - 17:00, via the 24 hour helpline on 0800 197 6102 or email us at info@sizewellc.com.

Main Development Site Forum Wednesday 15 Janua ry 2025

Leiston Town Athletic Association

Northern Transport Forum Wednesday 12 Februar y 2025 Darsha m Village Hall

Southern Transport Forum Wednesday 5 Ma rch 2025

Communit y Forum Thursd ay 27 Ma rch 2025

Stratford St And rew Riversid e Centre

Main Development Site Forum Wednesday 2 April 2025 Leiston Town Athletic Association

Northern Transport Forum Wednesday 7 May 2025

Southern Transport Forum Wednesday 4 Ju ne 2025

m Village Hall

Stratford St And rew Riversid e Centre

Main Development Site Forum Wednesday 2 Ju ly 2025 Leiston Town Athletic Association

Northern Transport Forum Wednesday 6 August 2025D arsham Village Hall

Southern Transport Forum Wednesday 3 Se ptembe r 2025 Stratford St And rew Riversid e Centre

Main Development Site Forum Wednesday 8 Oc tobe r 2025 Leiston Town Athletic Association

Communit y Forum Thursd ay 23 Oc tobe r 2025

Sizewell Sport s an d So cial Club

Northern Transport Forum Wednesday 5 November 2025D arsham Village Hall

Southern Transport Forum Wednesday 3 De cember 2025

Stratford St And rew Riversid e Centre

All imagery is copyright Sizewell C Ltd unless otherwise stated and must not be reproduced without permission.