Infographics Avelingen ENG 2015

Page 1

Flood plain excavation at Avelingen

New situation Nieuwe situatie

Current situation

A channel is being excavated next to Avelingen industrial site to give the river BovenMerwede more space during high water and to improve the water safety at Gorinchem.

Merwedebrug (bridge)

flood plain

high water

high water

To prevent the channel from flooding continuously, a bar is being created under the bridge. This will also help reinforce the bridge's pillars and prevent the passage of sailing vessels.

A15

Merwedebrug (bridge)

Key to map: A27

planning area ‘text’

Avelingen industrial bedrijventerrein site

500 m

Boven-Merwede

E S

nevengeul floodable met drempel secondary channel

Boven-Merwede

N W

Avelingen industrial site

overflowable bar quay

modified / new situation existing objects Boven-Merwede

new, modified or replaced objects new channel motorway

The channel is being prepared for shipping and is being given a new quay. This will give the companies on the estate that are linked to the water a sustainable place of business and will encourage transport by water.

(provincial) road overflowable bar

Avelingen industrial site GORINCHEM

Merwedebrug (bridge)

Boven-Merwede

Planning 1 2 3 4

www.roomfortheriver.nl

Effect

Project decision Preparation phase Start of work Delivering water safety

1

2

2009

2010

10.7 cm drop in water level during high water.

2011 SLEEUWIJK

3

4

2012

2013

Scale: 0

500 m

Jan 2015 / 9


Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.